This document is an attachment to a Fairfax County project specification focused on the county's Operational Energy Strategy and Sustainability requirements. The document outlines comprehensive waste management and energy sustainability guidelines for construction projects, with a primary goal of achieving carbon neutrality by 2040. The specification requires contractors to develop a Construction Waste Management Plan (CWMP) that achieves a minimum 50% salvage/recycling rate for construction and demolition waste, detailing extensive lists of materials to be salvaged or recycled across demolition and construction waste categories.
The document provides detailed instructions for waste tracking, reporting, and verification, including requirements for documenting waste generation, recycling, salvage, and disposal. Additionally, the specification mandates a rigorous process for identifying and implementing energy and sustainability opportunities across various project areas such as lighting, HVAC, water conservation, solar installations, and interior equipment sustainability. Contractors must conduct baseline condition assessments, propose energy savings opportunities, and provide post-installation verification reports that document equipment installations, performance measurements, and expected first-year energy savings. The approach emphasizes comprehensive documentation, measurement, and verification to ensure meaningful progress toward Fairfax County's environmental sustainability goals.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment C
I. Fairfax County Operational Energy Strategy and Sustainability Background
Fairfax County's commitment to environmental stewardship is demonstrated by policies, programs and projects that lower greenhouse gas emissions associated with its operations.
These efforts include reducing electricity and natural gas used in county buildings and operations, and gasoline and diesel used in county fleet vehicles and buses. Decreasing overall energy use not only provides wide-ranging environmental benefits, it also provides fiscal benefits to the county and its residents through utility cost avoidance.
On July 13, 2021, the Board of Supervisors adopted a new greenhouse gas emissions reduction goal through the Carbon Neutral Counties Declaration. Led by Fairfax County, Carbon Neutral Counties provides a mechanism for counties across the country to commit to operational emissions reductions. By signing the declaration, Fairfax County pledges to be energy carbon neutral by 2040, work with state and federal partners to advance this goal, and ensure it is implemented equitably.
Meeting this carbon neutral goal will require significant emissions reductions across all facets of county operations. As such, on July 13, 2021, the Board also adopted an update to the Fairfax County Operational Energy Strategy. First adopted in 2018, the Energy Strategy is intended to advance the objectives of the Board’s Environmental Vision through the setting of goals, targets, and actions across major focus areas. The updated Energy Strategy incorporates the carbon neutral goal in a new greenhouse gas emissions reductions focus area and includes accelerated targets across many of the remaining focus areas outlined below:
• Greenhouse Gas Emissions Reductions
• Energy Use and Efficiency
• Water Use and Efficiency
• Green Buildings
• Renewables
• Fleet Electrification
• Goods and Services
• Waste Management and Recycling
• Awareness and Engagement
• Utility Cost Management
• Reporting and Collaboration
In keeping with the Board of Supervisors requirements this project shall meet energy and sustainability requirements as set forth below.
II. Waste Management
This project shall generate the least amount of waste possible. The awarded contractor shall develop a construction waste management plan (CWMP) that results in end-of-project rates for salvage/recycling of a minimum of 50% by weight of construction and demolition waste.
A. Salvage/Recycle Requirements: Salvage and recycle as much non-hazardous demolition and construction waste as possible, including but not limited to the following materials:
1. Demolition Waste:
a. Asphaltic concrete paving
b. Concrete
c. Concrete reinforcing steel
d. Brick
e. Concrete masonry units
f. Wood studs
g. Wood joists
h. Plywood and oriented strand board
i. Wood paneling
j. Wood trim
k. Structural and miscellaneous steel
l. Rough hardware
m. Roofing
n. Insulation
o. Doors and frames
p. Door hardware
q. Windows
r. Glazing
s. Metal studs
t. Gypsum board
u. Acoustical tile and panels
v. Carpet
w. Carpet pad
x. Demountable partitions
y. Equipment
z. Cabinets
aa. Plumbing fixtures
bb. Piping
cc. Supports and hangers
dd. Valves
ee. Sprinklers
ff. Mechanical equipment
gg. Refrigerants
hh. Electrical conduit
ii. Copper wiring
jj. Lighting fixtures
kk. Lamps
ll. Ballasts
mm. Electrical devices
nn. Switchgear and panelboards
oo. Transformers
2. Construction Waste:
a. Masonry and CMU
b. All untreated wood, including lumber and finish materials
c. Wood sheet materials
d. Wood trim
e. Metals
f. Roofing
g. Insulation
h. Carpet and pad
i. Gypsum board
j. Unused (leftover) paint
k. Piping
l. Electrical conduit
m. Packaging: Regardless of salvage/recycle goal indicated above, salvage or recycle 100 percent of the following uncontaminated packaging materials:
1) Paper
2) Cardboard
3) Boxes
4) Plastic sheet and film
5) Polystyrene packaging
6) Wood crates
7) Plastic pails
n. Beverage and packaged food containers
B. SUBMITTAL
1. Construction Waste Management Plan (CWMP): It is the intent of this specification to maximize the diversion of demolition and construction waste from landfill disposal. Accordingly, not more than 30 days after receipt of Notice to Proceed and prior to the generation of any waste, prepare and submit via Procore a draft Construction Waste Management Plan to the FMD Project Manager including, but not limited to, the following:
a. Procedures for Recycling/Reuse Program to divert a minimum of 50% (by weight) of construction and demolition waste from landfill disposal, including waste resulting from demolition of any existing building and site demolition materials; any site equipment and supplies.
b. Approval of the Contractor’s CWMP shall not relieve the Contractor of responsibility for adequate and continuing control of pollutants and other environmental protection measures.
The contractor is responsible for compliance with all regulatory requirements pertaining to the legal disposal of construction and demolition waste material.
2. Submit calculations on end-of-project recycling rates, salvage rates, and landfill rates itemized by waste material, demonstrating that a minimum of 50% of construction wastes were recycled or salvaged and diverted from landfill. Include documentation of recovery rate (if commingled), waste hauling certificates or receipts, and a brief narrative explaining how and to where each waste type has been diverted.
3. Waste Reduction Progress Reports: Concurrent with each Application for Payment, submit a report via Procore, or alternative method approved by the Fairfax County Project Manager.
Include separate reports for demolition and construction waste. Include the following information:
a. Material category
i. Generation point of waste
ii. Total quantity of waste in tons
iii. Quantity of waste salvaged, both estimated and actual in tons
iv. Quantity of waste recycled, both estimated and actual in tons
v. Total quantity of waste recovered (salvaged plus recycled) in tons
vi. Total quantity of waste recovered (salvaged plus recycled) as a percentage of total waste
vii. Include up-to-date records of donations, sales, recycling and landfill/incinerator manifests, weight tickets, hauling receipts, and invoices.
4. Waste Reduction Calculations: A minimum of two weeks before request for Substantial Completion, submit via Procore the calculated end-of-project rates for salvage, recycling, and disposal as a percentage of total waste generated by the Work. Complete a table similar to the example below.
Recycled/Salvaged/Diverted Materials
Hauler or Location Quantity of Material (tons)
Total Construction Waste Diverted
Landfill Materials
Total Construction Waste Landfilled
Total Construction Waste Total Construction Waste Diverted + Total Construction Waste Landfilled
Percentage of Construction Waste Diverted from Landfill
(Total Construction Waste Diverted / Total Construction Waste)*100
5. Records of Donations: Indicate receipt and acceptance of salvageable waste donated to individuals and organizations. Indicate whether organization is tax-exempt.
6. Records of Sales: Indicate receipt and acceptance of salvageable waste sold to individuals and organizations. Indicate whether organization is tax-exempt.
7. Recycling and Processing Facility Records: Indicate receipt and acceptance of recyclable waste by recycling and processing facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
8. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills (or transfer stations) and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
C. CONSTRUCTION WASTE MANAGEMENT PLAN (CWMP)
1. General: Develop and implement a CWMP consisting of waste identification, waste reduction work plan. Include separate sections in plan for demolition and construction waste. Indicate quantities by weight or volume, but, use the same units of measure throughout the CWMP.
2. Draft Construction Waste Management Plan: Within 30 days after receipt of Notice to Proceed, or prior to any waste removal, whichever occurs sooner, the Contractor shall submit to the FMD Project Manager the Draft Waste Management Plan.
3. Final Construction Waste Management Plan: Once the FMD Project Manager has determined which of the recycling options addressed in the draft Waste Management Plan are acceptable, the Contractor shall submit, within 10 calendar days, a Final Waste Management Plan.
4. Waste Identification: Indicate anticipated types and quantities of demolition, site-clearing, and construction waste generated by the Work. Include estimated quantities and assumptions for estimates.
5. Landfill Options: Indicate the name of the landfill(s) and/or transfer station(s) and/or incinerator(s) where trash will be disposed of, the applicable landfill tipping fee(s), and the projected cost of disposing of all Project waste in the landfill(s).
6. Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, reused, recycled, or disposed of in landfill or incinerator. Include points of waste generation, total quantity of each type of waste, quantity for each means of recovery, and handling and transportation procedures.
a. Salvaged Materials for Reuse: For materials that will be salvaged and reused in this Project, describe methods for preparing salvaged materials before incorporation into the Work.
b. Salvaged Materials for Sale: For materials that will be sold to individuals and organizations, include list of their names, addresses, and telephone numbers.
c. Salvaged Materials for Donation: For materials that will be donated to individuals and organizations, include list of their names, addresses, and telephone numbers.
d. Recycled Materials: Include list of local receivers and processors and type of recycled materials each will accept. Include names, addresses, and telephone numbers.
e. Disposed Materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill and incinerator facility.
f. Handling and Transportation Procedures: Describe method that will be used for separating recyclable waste, including sizes of containers, container labeling, and designated location on Project Site where materials separation will be located.
7. Materials: The following list of required materials, at a minimum, must be included for salvaging/recycling: CUSTOMIZE TO THE INDIVIDUAL DEC PROJECT
a. Recycling
i. Cardboard
ii. Clean dimensional wood
iii. Beverage and food containers
iv. Paper
v. Concrete
vi. Concrete Masonry Units (CMUs)
vii. Asphalt: Include the approximate weight of the asphalt paving to be crushed and utilized as granulated fill from the existing paving as a component of waste material diverted from the landfill.
viii. Ferrous and non-ferrous metals (banding, stud trim, ductwork, piping, rebar, roofing, other trim, steel, iron, galvanized sheet steel, stainless steel, aluminum, copper, zinc, lead, brass, and bronze)
ix. Stretch and shrink wrap
x. Gypsum wallboard
xi. Paint containers and other clean, empty plastic containers
b. Salvage Items
i. Door hardware
ii. Fire alarm panels
8. Plan Implementation. Who will be the waste management coordinator for the project, the person responsible for implementing, monitoring, and reporting the status of the waste management work plan.
9. Hazardous Wastes: Hazardous wastes shall be separated, stored, and disposed of according to local regulations and should not be included in the Construction Waste Management Plan’s calculations of waste.
D. ENERGY AND OTHER SUSTAINABILITY OPPORTUNITIES
Step 1
For every project design process performed for the Facilities Management Department the selected Firm provides details for each energy and/or sustainability opportunity available and recommended within the provided project. This is not a full study endeavor, however the Firm provides an overview for proposed energy and cost savings opportunities for each recommendation implemented in the provided design. For projects that move forward without
A/E stamped design it is the responsibility of the construction contractor to identify energy and sustainability opportunities that may or should be leveraged within the performance of the project work. For energy opportunities the contractor working with the equipment/material manufacturer should use the Fairfax County contracted utility rates to calculate cost savings.
Opportunities will be reviewed for acceptance by the FMD Project manager based on energy savings not just solely on ROI. At a minimum for each recommendation provide the following information:
• Details of baseline existing conditions and data collected
• Documentation of all assumptions and sources of data
• Details of engineering analysis performed
• How energy savings will be calculated
• Details of proposed energy and cost savings
• Details of post-installation verification activities, including inspections, measurements, analysis and customer project acceptance procedures
Projects may include but are not limited to:
• Lighting
• Metering
• BAS or other controls
• Roof
• Insulation
• Water conservation
• Solar
• HVAC
• Interior fit out (materials sustainability)
• Interior equipment sustainability (drinking fountains, flush valves, censored faucets, etc.)
• Exterior sustainability – vegetation and landscape management, pervious pavement
• Waste water diversion
• Other electrical efficiencies
• Retro-commissioning- HVAC
Define the Baseline Baseline physical conditions (such as equipment inventory and conditions, occupancy schedule, nameplate data, equipment operating schedules, key energy parameter measurements, current weather data, control strategies, etc.) are determined through surveys, inspections, spot measurements, and short-term metering activities. Utility bills may be used to verify that the baseline has been accurately defined depending on the method of verification selected.
Baseline conditions are established for the purpose of estimating savings by comparing the baseline energy use with the post-installation energy use. Baseline information is also used to account for any changes that may occur during the performance period, which may require baseline energy use adjustments. It is important to ensure that the baseline has been properly defined.
Documentation of assumptions is also critical for baseline development. After the Energy or
Sustainability project/equipment has been implemented, it is impossible to go back and reevaluate the baseline because it no longer exists. Therefore, it is very important to properly define and document the baseline conditions. Deciding what needs to be monitored (and for how long) depends on such factors as the complexity of the measure and the stability of the baseline, including the variability of equipment loads and operating hours, and the other variables that affect the load
Step 2
Conduct Post-Installation Verification Activities (primarily for HVAC, plumbing, and electrical equipment)
Once FMD has selected energy and sustainability opportunities to pursue the contractor will be asked to provide pricing to provide post-installation measurement and verification (M&V).
These activities will be conducted to ensure that proper equipment/systems were installed, are operating correctly, and have the potential to generate the predicted savings. Verification methods include surveys, inspections, spot measurements, and short-term metering. A post-installation M&V report is a key deliverable for energy and sustainability projects. The post-installation report at a minimum shall include the following.
• Project description
• Detailed list of installed equipment
• Details of any changes between the final proposal and as-built conditions, including any changes to the estimated energy savings
• Documentation of all post-installation verification activities and performance measurements conducted
• Performance verification—how performance criteria were met • Documentation of construction-period savings (if any)
• Status of rebates or incentives (if any)
• Expected savings for the first year. Example: “Building A” has three (3) Air Handling
Units that provide HVAC for the entire building. The units are at the end of their life expectancy and have become maintenance intensive just in the last several years. More importantly the housing for the units have failed to the point where air and water leaks have caused them to have operational issues and run inefficiently. In considering a proposed replacement for all of the units, awarded A/E Firm “X” has proposed new units be provided with low leak casings, and be equipped with direct drive fans in lieu of the existing belt driven fans. These changes/upgrades could expect the proposed, replacement units to use 10% less energy than predecessors.