About this file
This file is a specification section from the Borough of Jenkintown, Pennsylvania, detailing traffic control and accommodation requirements for the 2026 Sanitary Sewer Cleaning and Video Survey project. The specification outlines comprehensive traffic management procedures contractors must implement during construction, including the provision and maintenance of barricades, safety fencing, warning signs, flashers, traffic cones, and flagpersons as indicated in drawings or directed by the Engineer. The contractor is required to maintain vehicular and pedestrian access to adjacent properties and ensure continuous access for emergency vehicles throughout construction. Specific notification requirements mandate that the Borough be informed 48 hours in advance of temporary road blockages, parking restrictions, or detour implementations, while the Pennsylvania Department of Transportation must be contacted at least 24 hours prior to any lane closures or work within state highway rights-of-way. Work on state highways is restricted to 9:00 AM to 3:00 PM or 6:00 PM to 6:00 AM. A pre-bid meeting is scheduled for October 16, 2026, at 10:00 AM at the Borough offices, with sealed bids due by 11:00 AM on October 30, 2026.
All traffic control work must comply with 67 PA Code Chapter 203 and PennDOT Publication 203 regarding work zone traffic control. Contractors are responsible for notifying emergency services, including Borough Police and Fire Departments, prior to commencing work. The work area must be properly barricaded and secured during non-work hours to maintain unrestricted full-width use of through traffic lanes. The Engineer may suspend other construction activities if traffic maintenance procedures are deemed unsatisfactory, with no adjustment to contract price or timeline for delays resulting from such corrections. Bid requirements include a certified check or bid bond of at least ten percent of the bid amount, and all bidders submitting bids of $100,000 or greater must demonstrate proof of competency and responsibility in accordance with Jenkintown Borough Ordinance No. 2008-2. Pennsylvania prevailing wage rates apply to all prime contractors and subcontractors.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACCOMMODATION AND
PIPE LINING PROTECTION OF TRAFFIC
DURING CONSTRUCTION
02010-1
SECTION 02010
ACCOMMODATION AND PROTECTION OF TRAFFIC
DURING CONSTRUCTION
PART 1 GENERAL
1.1 WORK INCLUDED
A. Maintenance, accommodation and protection of traffic during construction includes but is not limited to providing: satisfactory barricades, safety fence, warning signs, flashers, traffic cones, flag-persons and all materials, equipment and labor necessary for the acceptable maintenance and protection of traffic as indicated on the drawings, outlined in PennDOT Publication 203, entitled "Work Zone Traffic Control" or as directed by the Engineer.
1.2 GENERAL REQUIREMENTS
A. Contractor shall maintain vehicular and pedestrian access to adjacent properties at all times during construction, unless otherwise authorized.
B. Contractor shall maintain access for emergency vehicles at all times during construction.
C. Where permission for detouring traffic is granted, the Contractor shall post detour signs to the satisfaction of the appropriate Authorities, and the Contractor shall maintain such detour routes until such time as they are deemed unnecessary by the appropriate Authority.
D. No Borough roadway may be closed to traffic without the Borough’s approval. The Borough must be notified 48 hours in advance if the following in to occur
1. Road will be temporarily block during lining activities.
2. If no parking is required on the street. (The Borough will provide No Parking signs.
3. If detours are required.
E. Contractor shall provide an adequate number of flagpersons as required or as directed by the Engineer.
F. Contractor shall be responsible for notifying all emergency services including
ACCOMMODATION AND
PIPE LINING PROTECTION OF TRAFFIC
DURING CONSTRUCTION
02010-2
Borough Police and Fire Departments prior to work.
G. Maintenance and protection of traffic during construction shall conform to 67 PA Code, Chapter 203 entitled "Work Zone Traffic Control".
H. No State Highway may be occupied or closed to traffic without State approval.
The PADOT must be contacted at lease 24 hours prior to any lane closures or work within the roadway right of way. Work on State Highways can only occur between the hours of (9 AM and 3 PM or from 6 PM to 6 AM)
1.3 SPECIAL REQUIREMENTS
A. Work area shall be properly barricaded and secured during non-work hours to provide unrestricted full width use for through traffic lanes.
B. When it becomes necessary, the Engineer will inform the Contractor of unsatisfactory construction procedures and operations insofar as maintenance, accommodation and protection of traffic are concerned. If the unsatisfactory procedures and operations are not corrected promptly, the Engineer may suspend performance of other construction until the unsatisfactory condition has been corrected. There shall not be any adjustment of contract price or time for delays caused by the suspension to correct unsatisfactory conditions.
END OF SECTION