36C78620B0028_1.docx
DOCX document 129 KB Posted
- Solicitation number
- 36C78620B0028
About this file
This invitation for bid solicits offers for construction services at Culpeper National Cemetery. The services include constructing a niche columbarium, facility renovations and improvements, repairs, and pre-placed crypts. The solicitation is set aside 100% for service-disabled veteran-owned small businesses. The bid due date is August 27, 2020, with a virtual bid opening scheduled on that date. Pricing is requested for fixed-price line items covering the construction work. The awarded firm-fixed price contract will have a one-year period of performance beginning after notice to proceed.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C78620B0028
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5.
REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE
DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL
SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
1. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than ____ ___________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C78620B0028 X 07-23-2020
TBD
839CM3028/ 839CM3030
Y 36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172 Invitation for Bid (IFB) Electronic Bid Opening, See Section: INSTRUCTIONS, CONDITIONS, AND
OTHER STATEMENT TO
BIDDERS/OFFERORS
SHERYL PALACIO-DAVIS
1-703-630-9343 The Department of Veterans Affairs, National Cemetery Administration (NCA), anticipates awarding a Firm, Fixed Price Contract, in accordance with FAR Part 14, Sealed Bidding; for Culpeper National Cemetery, under Project NO. 839CM3028 & 839CM3030. The Construction Contractor shall provide labor, material, tools, equipment and professional supervision required for the construction & performance of all work In Accordance With (IAW) the Solicitation Plans, Drawings, Specifications, required permits, terms & conditions for the Construction of Columbarium, Facility Renovation, Repairs, Improvements and Pre-Placed Crypts, per the Construction Documents and terms and conditions herein including (CLINS 0001 thru CLINS 0004 (Please see attached SOW).
This is a 100% competitive Set-Aside for Service Disabled Veteran Owned Small Business (SDVOSB) in accordance with the Veterans First Program, 38 USC 8127 and 8128. Only SDVOSB firms verified eligible in Vetbiz.gov, with the Certified Veteran Enterprise (CVE) Seal on their registration will be considered. The Vet biz database will be checked both upon receipt of an offer and prior to award. Firms must also have current registration in the System for Award Management (BetaSAM) database at www.betaSam.gov and have completed online Representatives and Certifica tions prior to award.
An organized Site Visit is scheduled for 06 Aug 2020, at 11:00 A.M. (EST) in the Admin Bldg at Culpeper Nalt Cem:
305 U.S. Avenue, Culpeper, VA 22701. Please See c lause 52.236-27 for Site-Visit information.
Questions shall be submitted to sheryl.palacio-davis@va.gov, NLT, 12 Aug 2020 at 2:00 P.M. (EST), after the Site-Visit.
Email subject line must contain line must contain the following in the subject line: Solicitation Number, Proj. Name & Proj. Number. Questions received after 12 Aug 2020 WILL NOT be accepted. Telephone inquiries are not accepted during the Solicitation period. Answers will be posted through an Amendment to the Solicitation.
A VIRTUAL BID OPENING is scheduled for 27 Aug 2020 @ 11:00 A.M. (EST). | Electronic BIDs received after 11:00 AM (EST) 27 Aug 2020, WILL NOT Be Accepted. Facsimile (FAX) submitted BIDs will not be accepted.
NOTE: Attendance for Virtual BID Opening is not Mandatory.
The North American Industry Classi fication System (NAICS) Code is 237990; Business Size Standard is $3
6.5 Million.
IAW VAAR 836.204, the Magnitude of Construction is between Between $5,000,000 and $10,000,000.
Contract award will be made to the responsible Bidder whose BID, conforming to the invitation, will be most advantageous to the Government, considering only price and price-rated factors in cluded in the invitation.
Unless otherwise noted, all references to "day(s)" throughout the solicitation documents shall be Calendar Days.
**This procurement is a 100% competitive Set-Aside for Service Disabled Veteran Own Small Business (SDVOSB)** X X 52.211-10 X 11:00 08-27-2020 X 100 Due to COVID-19
14. NAME AND ADDRESS OF
OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25.
OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on t his form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR
OR PERSON AUTHORIZED
31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Offeror's shall fill out Section B1 - Price/Cost Schedule.
CLIN 0001 $__________________________
CLIN 0002 $__________________________
CLIN 0003 $___________________________
CLIN 0004
Total Amount (Including Bonds): $______________________ 36C786 Department of Veterans Affairs National Cemetery Administration (NCA) Construction Support Division (43C2) 18434 Jopline Road Triangle VA 22172 http://www.tungsten-network.com/customer -campaigns/veterans-affairs/
1-877-752-0900 Kellyann Bruno Contracting Officer
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| A.4 PRICE/COST SCHEDULE | 10 |
| PRICE SCHEDULE-BASE BID | 10 |
| ITEM INFORMATION | 10 |
| A.5 DIGNITY STANDARDS | 11 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 13 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 16 |
| 2.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 16 |
| 2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 16 |
| 2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 16 |
| 2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 17 |
| 2.5 52.228-1 BID GUARANTEE (SEP 1996) | 18 |
| 2.6 VAAR 852.236-92 NOTICE TO BIDDERS—ADDITIVE OR DEDUCTIVE BID LINE ITEMS (APR 2019) | 19 |
| 2.7 52.233-2 SERVICE OF PROTEST (SEP 2006) | 20 |
| 2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 20 |
| 2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 21 |
| 2.10 52.204-22 ALTERNATIVE LINE ITEM PROPOSAL (JAN 2017) | 22 |
| 2.11 52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 2016) | 22 |
| 2.12 52.214-4 FALSE STATEMENTS IN BIDS (APR 1984) | 22 |
| 2.13 52.214-5 SUBMISSION OF BIDS (DEC 2016) | 23 |
| 2.14 52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984) | 23 |
| 2.15 52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999) | 23 |
| 2.16 52.214-18 PREPARATION OF BIDS—CONSTRUCTION (APR 1984) | 24 |
| 2.17 52.214-19 CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION (AUG 1996) | 25 |
| 2.18 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 25 |
| 2.19 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 25 |
| 2.20 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 26 |
| REPRESENTATIONS AND CERTIFICATIONS | 28 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) | 28 |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (DEC 2019) | 32 |
| 3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 33 |
| 3.4 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—CERTIFICATION (JUN 2018) | 34 |
| 3.5 52.215-23 LIMITATIONS ON PASS-THROUGH CHARGES (JUN 2020) ALTERNATE I (OCT 2009) | 36 |
| GENERAL CONDITIONS | 38 |
| 4.1 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008) | 38 |
| 4.2 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 38 |
| 4.3 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018) | 38 |
| 4.4 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 40 |
| 4.5 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 41 |
| 4.6 52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000) | 41 |
| 4.7 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAY 2020) | 41 |
| 4.8 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020) | 44 |
| 4.9 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) | 45 |
| 4.10 SUPPLEMENTAL INSURANCE REQUIREMENTS | 46 |
| 4.11 52.236-4 PHYSICAL DATA (APR 1984) | 47 |
| 4.12 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 47 |
| 4.13 52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014) | 49 |
| 4.14 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020) | 49 |
| 4.15 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018) | 51 |
| 4.16 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION) | 52 |
| 4.17 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 54 |
| 4.18 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 54 |
| 4.19 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 56 |
| 4.20 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 57 |
| 4.21 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 57 |
| 4.22 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (APR 2019) | 57 |
| 4.23 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 58 |
| 4.24 VAAR 852.246-75 WARRANTY OF CONSTRUCTION—GUARANTEE PERIOD SERVICES (OCT 2018) | 60 |
| 4.25 MANDATORY WRITTEN DISCLOSURES | 60 |
| 4.26 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 60 |
| 4.27 52.203-14 DISPLAY OF HOTLINE POSTER(S) (OCT 2015) | 61 |
A.3 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR: TBD
b. GOVERNMENT:
Contracting Officer (CO): Kellyann Bruno
Administrative Contracting Officer (ACO): Sheryl Palacio-Davis U.S. Department of Veterans Affairs National Cemetery Administration (NCA) Contracting Service (43C) 18434 Joplin Rd Triangle, VA 22172 Business NO. 1-703-630-9343 Sheryl.palacio-Davis@va.gov
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor shall be made in accordance with:
[X] 52.232-34, Payment by Electronic Funds Transfer.
3. INVOICES: Invoices shall be submitted in arrears:
Other [X] [Monthly]
4. GOVERNMENT INVOICE ADDRESS:
All invoices from the contractor shall be sent electronically by following instruction as stated at website: http://www.fsc.va.gov/einvoice.asp See VAAR clause 852.232-72 Electronic Submission of Payment Requests (NOV 2012).
5. ACQUISITION: Total (100%) Service-Disabled Veteran Owned Small Business Set-Aside: This is a solicitation for construction services prepared in accordance with the format in FAR Part 14 and FAR Part 36. The contract will be awarded by Government to furnish those construction tasks as stated in the SOW, Specs and Drawings. The Government anticipates awarding this solicitation as a fixed-price contract.
Historical Data:
Incumbent Contractor: None
6. TYPE OF CONTRACT: This is a Firm Fixed-Price requirement contract in accordance with FAR 52.216-1 Type of Contract.
7. CONTRACT AWARD: The contract will become effective as soon as practical with no additional cost to the Government for any elapsed time from the original effective date. It is also, understood and agreed that the effective date of this contract will be contingent upon the availability of appropriated funds and in the event, appropriations are not available.
8. ACKNOWLEDGEMENT OF AMENDMENTS:
The Offeror acknowledges receipt of Amendments to the Solicitation numbered and dated as follows:
| AMENDMENT NO |
| DATE |
9. AUTHORITIES OF GOVERNMENT PERSONNEL: Notwithstanding the Contractors responsibility for total management during the performance of this contract, the administration of the contract will require maximum coordination between the Government and the Contractor. The Government will provide, at the time of contract award, a list of Government personnel authorized to act as the Contracting Officer's Representatives (COR). Only the Contracting Officer has the authority to make changes to the contract.
10. CONTRACTOR’S FOREMAN/SUPERVISOR: Contractor must provide an English-speaking foreman /Supervisor at all times while performing the duties of the contract. This is to ensure proper communication between the Contractor and COR.
11. SITE VISIT: See 52.236-27 for site visit information
12. PRE-CONSTRUCTION CONFERENCE: Prior to commencement of work, Contractor shall attend a pre-construction conference to assure that all parties understand all contractual obligations and the role that each party serves.
13. FEDERAL HOLIDAYS:
| January |
| New Year’s Day & Martin Luther King’s Birthday |
| February |
| President’s Day |
| May |
| Memorial Day |
| July |
| Independence Day |
| September |
| Labor Day |
| October |
| Columbus Day |
| November |
| Veterans Day & Thanksgiving Day |
| December |
| Christmas Day |
Including any other day specifically declared by the President of the United States to be a national holiday.
14. LIMITATIONS ON SUBCONTRACTING – MONITORING AND COMPLIANCE:
This contract includes (VAAR) 852.219-10, VA Notice of Total Service-Disabled Veteran-Owned Small Business Set- Aside. The Contractor is advised in performing contract administration functions, the CO may use the services of a support contractor(s) retained by VA to assist in assessing the contractor’s compliance with the limitations on subcontracting or percentage of work performance requirements specified in the clause. To that end, the support contractor(s) may require access to contractor’s offices where the contractor’s business records, or other proprietary data are retained and to review such business records regarding the contractor’s compliance with this requirement. All support contractors conducting this review on behalf of VA will be required to sign an “Information Protection and Non-Disclosure and Disclosure of Conflicts of Interest Agreement” to ensure the contractor’s business records or other proprietary data reviewed or obtained in the course of assisting the CO in assessing the contractor for compliance are protected to ensure information or data is not improperly disclosed or other impropriety occurs. Furthermore, if VA determines any services the support contractor(s) will perform in assessing compliance are advisory and assistance services as defined in FAR 2.101, Definitions, the support contractor(s) must also enter into an agreement with the contractor to protect proprietary information as required by FAR 9.505-4, Obtaining Access to Proprietary Information, paragraph (b). The contractor is required to cooperate fully and make available any records as may be required to enable the CO to assess the contractor’s compliance with the limitations on subcontracting or percentage of work performance requirement.
15. RELEASE OF CLAIMS:
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relation to the contract. The Release of Claims form provided by the CO shall be used for this purpose. The form provides for exception of specified claims from the operation of release. Request a copy from the CO.
16. NOTICE TO CONTRACTORS - CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM:
a. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
b. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
c. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
d. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
e. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
1. Contractor Representatives may then provide comments in response to the evaluation or return the evaluation without comment.
2. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
3. All information provided should be reviewed for accuracy prior to submission.
4. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
5. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
6. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
f. The following guidelines apply concerning your use of the past performance evaluation:
1. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
2. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
1. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
1. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
[END OF ADMINISTRATION DATA]
A.4 PRICE/COST SCHEDULE
PRICE SCHEDULE-BASE BID
Contractor shall provide all labor, tools, materials, equipment, services, testing. submittals, supervision, approvals, and related work for the Columbarium, Facility Renovation, Improvements, Repairs, and Pre-Placed Crypt Projects, at Culpeper National Cemetery; located at 305 U.S. Avenue, Culpeper, VA 22701.
The work shall be completed In Accordance With (IAW) the Scope of Work (SOW), Specifications, and Drawings.
ITEM INFORMATION
| Contract Line Item |
| Description |
| Quantity |
| Unit |
| Unit Price |
| Total Price |
| 0001 |
| Construct Niche Columbarium, Facility Renovation, Improvements & Repairs per Construction Documents and Specifications |
| 500 |
| JB |
| 0002 |
| Construct Pre-Places Crypts |
| 1,222 |
| JB |
| 0003 |
| Plant Cedar Trees |
| 60 |
| JB |
| 0004 |
| Procure Precast Crypt Units and deliver to site |
| 1,222 |
| JB |
| 0005 |
| Mill and Repave Existing Roadway used for construction access |
| 1 |
| JB |
TOTAL FOR CLINS 0001 THRU 0005
| BID OPTION 1 |
| Full Depth Removal and Replacement of the Existing Asphalt Roadways |
| 1 |
| JB |
| BID OPTION 2 |
| Removal and Replacement of the Existing Concrete Road Entry and Removal and Replacement of the Existing Storm Sewer Structures |
| 1 |
| JB |
| BID OPTION 3 |
| Removal and Replacement of the Existing Colored Concrete Roadways Around the Flagpole |
| 1 |
| JB |
| BID OPTION 4 |
| Milling and Overlay of the Existing Asphalt Maintenance Yard |
| 1 |
| JB |
| BID OPTION 5 |
| Addition of Storm Sewer Piping and Structures and Associated Pavement Repair |
| 1 |
| JB |
| BID OPTION 6 |
| Removal of the Existing Cast Stone Columbarium Caps at Columbarium A and Replacement with Cut Indiana Limestone |
| 1 |
| JB |
| BID OPTION 7 |
| Mill & Overlay of the Existing Asphalt Roadways |
| 1 |
| JB |
| BID OPTION 8 |
| Connecting to Existing Storm Sewer Pipe |
| 1 |
| JB |
TOTAL PRICE (CLINS 0001 & 0002 PLUS BID OPTIONS 1-8:
TOTAL PRICE WRITTEN:
A.5 DIGNITY STANDARDS
1. Every action by contractor personnel at a National Cemetery must be performed with the special care, reverence, dignity, and respect that acknowledge the cemetery as the final resting place that commemorates the service and sacrifice those service members, Veterans, and their families made for our Nation. Critically important is the awareness, required of the contractor employees, of the remains buried in the grounds where the work is performed. The utmost care must be given to these remains and the headstones and flat grave markers that mark those gravesites and memorialize the service of individuals.
a. Contractors cannot walk, stand, lean, sit or jump on headstones or markers. Nor can they drive over them. Contractor personnel should use tools approved by the Contracting Officer Representative (COR), such as shovels, pry bars or pinch bars to lift flat markers out of the ground; pick axes are not an acceptable tool.
b. No tools, equipment or other items will be placed or leaned on headstones or markers. Once headstones/markers are removed from the socket, do not place on dirt piles or mud; they should be carefully placed on each associated gravesite and protected in such a way as to prevent any soiling and be out of the way of any other work.
c. Headstones shall be removed from their sockets using wooden and/or metal clamps. If metal clamps are used, the area that contacts the headstone must be protected with a rigid fabric that will prevent damage to and marking of the headstone. Clamps may be attached to a skid steer loader (i.e., Bobcat®) or similar machine to extract the headstone from the socket. When headstones are removed from their sockets, they shall be carefully stored on each associated gravesite; do not lean headstones against each other. Use care not to scratch or damage headstones in any manner. The headstones shall be laid with front inscription side up while the headstone is lying horizontally on the ground. The headstone shall be protected from direct ground contact while lying horizontally. The protection method shall be as approved by the COR and shall be free of deterioration in weather. An approved method is to support each headstone with two wood 4X4’s. Alternate methods can be approved. Cardboard shall not be used. Wood or other suitable appropriate and attractive material shall be used to keep the headstones from contact with the soil while lying horizontally during the construction period. This also shows respect towards the families visiting the gravesites and the remains that are buried.
d. Contractor shall be responsible for replacing damaged headstones and markers and for restoring turf damaged during performance of this work.
e. Additionally, should any activity result in the exposure and/or damage to any remains, container for remains (i.e., casket or urn), or outer burial container, the Contractor must contact the COR, Director/Assistant Director, and Contracting Officer (CO) for guidance.
1. Any doubts as to proper procedures shall be brought to the attention of the COR, Director/Assistant Director, and CO for guidance or resolution.
1. The Contractor is required to discuss the guidance with their employees and have each employee sign a statement of compliance and deliver the signed statement to the COR before work may begin.
A.6 SBA ACT 8(d)(13)(B)
(B) NOTICE. —
(i) IN GENERAL.—A Prime Contractor for a covered contract shall notify in writing the Contracting Officer for the covered contract if the Prime Contractor pays a reduced price to a Subcontractor for goods and services upon completion of the responsibilities of the Subcontractor or the payment to a Subcontractor is more than 90 days past due for goods or services provided for the covered contract for which the Federal agency has paid the Prime Contractor.
(ii) CONTENTS. —A Prime Contractor shall include the reason for the reduction in a payment to or failure to pay a Subcontractor in any notice made under clause (i).
Page 1 of Page 1 of
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
SOLICITATION VIRTUAL BID INSTRUCTIONS:
VIRTUAL BID INSTRUCTIONS
1. Gender: Whenever the masculine gender is used in this solicitation and contract documents, it shall be considered to include feminine.
1. Amendments: Amendments to Solicitation will be posted at https://beta.sam.gov/search?index=opp. Paper copies of the amendments will NOT be individually mailed. Register to the receive email notifications list at https://beta.sam.gov/search?index=opp, and potential bidders will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Potential bidders are advised that they are responsible for obtaining and acknowledging any amendments to the solicitation. Failure to acknowledge an amendment may result in your bid being considered non-responsive.
1. Bid Submission:
2. All bids shall be submitted electronically. All Interested Offerors must be registered with the Department of Veterans Affairs eCMS Vendor Portal at https://www.vendorportal.ecms.va.gov. Offerors who require registration shall proceed to the Vendor Portal’s Login section and shall click on Request a user account to register. In the event an Offeror is unable to submit a proposal through the vendor portal domain, prior to the proposal closing date, contact the VAAS helpdesk at 1-877-634-3739, or via email at VA.Acquisition.Systems@va.gov. DO NOT wait until the last day to upload bid documents. Offerors are highly encouraged to submit bid packages 2-3 days in advance to avoid system lock outs.
2. If an Offeror is still having difficulties in submitting a quote via the Vendor Portal the Contracting Officer may accept an Offeror’s quote via email under the following circumstances:
1. Offeror must provide evidence that an email discussions or verbal discussion with the VAAS helpdesk could not resolve registration issues.
2. Quote submitted must meet the time constraints as set forth in the solicitation.
Quotes submitted via email without set requirements will not be accepted and will be considered to be nonresponsive. Late or incomplete Quotes will also be considered to be nonresponsive.
2. Bid package shall be submitted via the Vendor Portal. Late or incomplete Proposals will also be considered to be nonresponsive. Offers are NOT authorized to submit bid packages by US mail; CD versions; Fax; or Email, (Unless portal difficulties have been proven as noted above than email submission may be permitted by the CO prior to the bid opening time).
2. Document naming convention. S00_Bid $_ (Company Name)_(Solicitation Number) EXAMPLE: S00_Bid $1,000,000.00_ABC Company_36C78620B0000
2. Bid package shall be One (1) PDF document combining the following minimum required documents in the following order:
· Company cover letter with Solicitation number, POC name, phone number, email address, and DUNS number;
· Completed front and back blocks 14-20 of the SF 1442 and signed block 20b ;
· Completed schedule B pricing for each CLIN and grand total;
· Completed S02_Attachment-16 _IFB Contractor Cost Estimate Worksheet;
· Complete and signed SF30 Amendments;
· Scanned digital copy of the Bid Bond. (Ensure to lightly darken all raised seals) A virtual public bid opening will occur by phone conference. Once the offeror has submitted their Bid into the eCMS Vendor Portal, please RSVP by email to sheryl.palacio-davis@va.gov with a list of participates noting:
Full Name, Company Represented, Phone Number, and Email of those you wish to be on the call.
NOTE: Call Line: 1-872-701-0185 Conference ID: 397 965 301#
4. REQUESTS FOR INFORMATION (RFI)
Requests for information or clarifications to solicitation documents shall be submitted through the Vendor Portal. Last day for request for information (RFI) is 03 Aug at 2:00 P.M. (EST). Request after the deadline date and time Will Not Be ACCEPTED.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
The Government contemplates award of a of a Firm-Fixed-Price Contract resulting from this Solicitation
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| 25.2 % |
| 6.9 % |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is
(End of Provision)
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.5 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be percent of the bid price or , whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.6 VAAR 852.236-92 NOTICE TO BIDDERS—ADDITIVE OR DEDUCTIVE BID LINE ITEMS (APR 2019)
(a) Additive or deductive line items in the bid schedule shall be evaluated to determine the low offeror and the items to be awarded. The evaluation shall be made as follows—
(1) Prior to the opening of bids, the Government will determine the amount of funds available for the project.
(2) The low bid shall be the Bidder that—
(i) Is otherwise eligible for award; and
(ii) Offers the lowest aggregate amount for the first or base line item, plus or minus (in the order stated in the list of priorities in the bid schedule) those additive or deductive line items that provide the most features within the funds determined available.
(3) All bids shall be evaluated on the basis of the same additive or deductive line items.
(i) If adding another item from the bid schedule list of priorities would make the award exceed the available funds for all offerors, the Contracting Officer will skip that item and go to the next item from the bid schedule of priorities; and
(ii) Add that next item if an award may be made that includes that line item and is within the available funds.
(b) The Contracting Officer will use the list of priorities in the bid schedule only to determine the low offeror. After determining the low offeror, an award may be made on any combination of items if—
(1) It is in the best interest of the Government;
(2) Funds are available at the time of award; and
(3) The low offeror’s price for the combination to be awarded is less than the price offered by any other responsive, responsible offeror.
(c) Example: ‘‘The amount available is $100,000. Offeror A’s base bid and four additives (in the order stated in the list of priorities in the bid schedule) are $85,000, $10,000, $8,000, $6,000, and $4,000. Offeror B’s base bid and four additives are $80,000, $16,000, $9,000, $7,000, and $4,000. Offeror A is the low offeror. The aggregate amount of offeror A’s bid for purposes of award would be $99,000, which includes a base bid plus the first and fourth additives. The second and third additives were skipped because each of them would cause the aggregate bid to exceed $100,000.’’ (End of Clause)
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Sheryl Palacio-Davis (ACO) Kellyann Bruno, Contracting Officer Hand-Carried Address:
National Cemetery Administration Contracting Service Department
18434 Joplin Rd Triangle VA 22172 Mailing Address:
National Cemetery Administration Contracting Service Department
18434 Jopline Rd Triangle VA 22172
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
1. The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed:
Culpeper National Cemetery 305 U.S. Avenue Culpeper, VA 22701
(b) An organized Site Visit has been scheduled for 06 August 2020 @ 11:00 A.M. (EST).
(c) Participants will meet at Culpeper National Cemetery Complex.
(d) POC: Mr. Matthew Priest (Director) Matthew.Priest@va.gov Office: (540) 825-0027 Mobile: (540) 229-3338 Fax: (540) 825-6684
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT |
| OCT 2018 |
| 52.204-16 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING |
| JUL 2016 |
2.10 52.204-22 ALTERNATIVE LINE ITEM PROPOSAL (JAN 2017)
(a) The Government recognizes that the line items established in this solicitation may not conform to the Offeror's practices. Failure to correct these issues can result in difficulties in acceptance of deliverables and processing payments. Therefore, the Offeror is invited to propose alternative line items for which bids, proposals, or quotes are requested in this solicitation to ensure that the resulting contract is economically and administratively advantageous to the Government and the Offeror.
(b) The Offeror may submit one or more additional proposals with alternative line items, provided that alternative line items are consistent with subpart 4.10 of the Federal Acquisition Regulation. However, acceptance of an alternative proposal is a unilateral decision made solely at the discretion of the Government. Offers that do not comply with the line items specified in this solicitation may be determined to be nonresponsive or unacceptable.
(End of Provision)
2.11 52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 2016)
(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.
(b)(1) Bidders shall acknowledge receipt of any amendment to this solicitation—
(i) By signing and returning the amendment;
(ii) By identifying the amendment number and date in space provided for this purpose on the form for submitting a bid;
(iii) By letter;
(iv) By facsimile, if facsimile bids are authorized in the solicitation; or
(v) By email, if email bids are authorized in the solicitation.
(2) The Government must receive the acknowledgement by the time and at the place specified for receipt of bids.
(End of Provision)
2.12 52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)
Bidders must provide full, accurate, and complete information as required by this solicitation and its attachments. The penalty for making false statements in bids is prescribed in 18 U.S.C. 1001.
(End of Provision)
2.13 52.214-5 SUBMISSION OF BIDS (DEC 2016)
(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.
(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a) (1) and (2) of this provision when delivered to the office specified in the solicitation.
(c) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation; or
(d) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.
(End of Provision)
2.14 52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before the submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. Any information given a prospective bidder concerning a solicitation will be furnished promptly to all other prospective bidders as an amendment to the solicitation, if that information is necessary in submitting bids or if the lack of it would be prejudicial to other prospective bidders.
(End of Provision)
2.15 52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999)
(a) Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bids (IFB) by the time specified in the IFB. If no time is specified in the IFB, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that bids are due.
(b)(1) Any bid, modification, or withdrawal received at the Government office designated in the IFB after the exact time specified for receipt of bids is ``late'' and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late bid would not unduly delay the acquisition; and—
(i) If it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids; or
(ii) There is acceptable evidence to establish…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .