36C77626R0008 0005 Attachment 1 - RFI Responses.docx

DOCX document 216 KB Posted

Attached to
Z1DA--565-22-7005 | EHRM Infras Upgrades | Fayetteville, NC
Solicitation number
36C77626R0008
Issued by

About this file

This is a Request for Information (RFI) Responses Tracking Sheet for Solicitation 36C77626R0008, documenting 504 contractor questions and government responses regarding the EHRM Infrastructure Upgrades project at Fayetteville VA Medical Center in North Carolina.

The project involves comprehensive infrastructure upgrades including telecommunications, fire alarm systems (transitioning from Edwards EST to Siemens Desigo Compact FV2025), physical access control systems (Software House C-CURE 9000 version 2.70), and video management systems (Pelco VideoXpert 3.22). Key scope elements include installation of new data cabling (CAT6A with 10% allowance), fiber optic infrastructure with innerduct/MaxCell requirements, new cable tray systems, telecommunications rooms (TRs) in multiple buildings, access control devices, CCTV cameras (Avigilon H5A PTZ preferred), underground duct bank installation with concrete encasement, and associated building modifications. The contract is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside with a firm-fixed-price structure, 731 calendar days period of performance from Notice to Proceed, and includes after-hours work requirements (6:00 PM to 5:00 AM) for cable replacements, utility shutdowns, and above-ceiling activities. Critical requirements include BICSI-certified telecommunications contractors, third-party independent inspections, comprehensive site surveys by licensed Professional Land Surveyors, compliance with VA Physical Security Requirements and ICRA protocols for infection control, tax payment responsibility by contractor, and coordination with VA OIT for network outages and temporary switching support (maximum 10 temporary swing switches provided by VA). The project encompasses 14 buildings with varying scope from major telecom room renovations in Buildings 1 and 21 (including raised access floor replacement in Building 21) to telecom enclosure installations in Buildings 9, 10, 11, 45, 46, 47, 48, and 70, with extensive site infrastructure work including trenching, duct bank installation, sidewalk restoration, landscaping, and erosion control planning.

View the file

Other files

File Type Posted
36C77626R0008 0008.pdf PDF
36C77626R0008 0008 Attachment 1 - Key Personnel.docx DOCX document
36C77626R0008 0007.pdf PDF
36C77626R0008 0007 Attachment 4 - Revised IFC Set Vol 2.zip ZIP file
36C77626R0008 0007 Attachment 1 - RFI Responses.docx DOCX document
36C77626R0008 0007 Attachment 3 - Revised IFC Set Vol 1.zip ZIP file
36C77626R0008 0007 Attachment 5 - Revised IFC Set Vol 3.zip ZIP file
36C77626R0008 0007 Attachment 6 - Revised IFC Set Vol 4.zip ZIP file
36C77626R0008 0007 Attachment 2 - Bldg 21 as builts.zip ZIP file
36C77626R0008 0006 - Attachment 2 Addendum1_MCR Structured Cabling Detail.pdf PDF
36C77626R0008 0006 Attachment 1 - RFI Responses.docx DOCX document
36C77626R0008 0006.pdf PDF
36C77626R0008 0005.pdf PDF
36C77626R0008 0005 Attachment 3 - Brand Name Justification.pdf PDF
36C77626R0008 0005 Attachment 2 - Addendum to specifications.zip ZIP file
36C77626R0008 0004.pdf PDF
36C77626R0008 0003.pdf PDF
36C77626R0008 0002 Attachment A - Sign In Sheets_Site Visit - 29 January 2026.pdf PDF
36C77626R0008 0002 Attachment B - Sign In Sheets_Site Visit - 05 February 2026.pdf PDF
36C77626R0008 0002.pdf PDF
36C77626R0008 0001.pdf PDF
Attachment A - Wage Rates.pdf PDF
Attachment G - Key Personnel.docx DOCX document
Attachment E - Limitations on Subcontracting - Construction.docx DOCX document
Attachment H - HEFP SEP Design Alerts 1-9 and 11-16.pdf PDF
Attachment F - KSI.docx DOCX document
36C77626R0008_1.pdf PDF
Attachment C - Drawings Volume I.zip ZIP file
Attachment I - Division Pricing Template.xlsx XLSX spreadsheet
Attachment D - Drawings Volume II.zip ZIP file
Attachment B - Specifications.zip ZIP file
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL QUESTIONS AND

SOLICITATION #:
36C77626R0008
RESPONSES TRACKING SHEET
PROJECT TITLE:
EHRM Infrastructure Upgrades Fayetteville, NC
#
RECEIVED
ANSWERED
CONTRACTOR QUESTION
VA RESPONSE
1.
2/9/2026
Due to the instability in our current economy such as price escalations, procurement issues, and vendors unable to reasonably hold prices for more than 30 days, please change the contract type to a fixed-price contract with economic price adjustment pursuant to FAR 16.203.
In accordance with FAR 16.202 and 52.216-1, this requirement will remain a firm-fixed-price contract.
2.
2/9/2026
Due to the instability in our current economy such as price escalations, procurement issues, and vendors unable to reasonably hold prices for more than 30 days, please reduce the price-hold period to 30 days.
The Government standard concerning price-hold period is 90 calendar days and will not be altered.
3.
2/9/2026
Will the government pay for materials stored per VAAR 852.232-70 and FAR 52.232-5? We have experienced PCAC Contracting Officers refusal to pay for materials stored on site during these periods of material shortages and the need to expedite procurement of materials when available to meet schedule obligations and prevent project delays. This is an important factor in preparing Price proposals.
In accordance with contract terms and conditions, Contractors should not submit an offer assuming the Government will approve monthly progress payments for material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site. Payment of stored materials and/or equipment is at the Contracting Officer’s discretion and will be handled on a case-by-case basis during the contract and under such terms and conditions as the Contracting Officer approves.
4.
2/9/2026
Please confirm that any designers or consultants who provided professional services for the construction documents, including reports, are precluded from pursuing this project as a Prime contractor, Mentor-Protégé partner, or subcontractor.
Any member of the design team of this project is not permitted to be part of the construction team.
5.
2/9/2026
Please confirm that this project is a competitive SDVOSB set-aside and that any bonding provided by a contractor must be through a SDVOSB or SBA/VA APPROVED Mentor-Protégé partnership under the SBA/VA Mentor-Protégé program in which the partnership has been approved prior to the due date.
This project is set aside for SDVOSBs. The bonding requirements must be met for this project per the applicable clauses, provisions, and instructions to offerors.
6.
2/9/2026
Please confirm that a large business not part of an SBA/VA APPROVED Mentor-Protégé team under the VA Mentor-Protégé program cannot provide a bid guarantee or a payment & performance bond for a SDVOSB.
This project is set aside for SDVOSBs. The bonding requirements must be met for this project per the applicable clauses, provisions, and instructions to offerors.
7.
2/9/2026
When visiting the link, I noticed the project was “set aside for Service-Disabled Veteran Owned Small Business” – does this mean that General Contractors cannot bid the project unless they meet that requirement?
Yes, this project is a 100% set-aside for SDVOSBs. The prime contractor submitting the offer must be certified as such in the SBA VetCert database.
8.
2/9/2026
Is this project tax exempt? If the project is sales tax exempt will the government/VA provide a sales tax exemption certificate?
No. See Special Note regarding FAR 52.229-3 Federal, State, and Local Taxes in the solicitation and FAR 52.229-2 NORTH CAROLINA STATE AND LOCAL SALES AND USE TAX (SEP 2025) (DEVIATION)
9.
2/9/2026
Will the Government provide detailed written requirements for contractor badging? Please clarify the process for obtaining PIV badges, including required documentation, background checks, and estimated processing timeframes.
Regardless of affiliation, everyone working within VA facilities or requiring access to VA information systems requires a VA PIV Card. PIV badging requirements can be found at https://www.osp.va.gov/How_To_Get_A_VA_ID_Badge.asp

Immediately after the bonds are provided to the Government, the contractor shall immediately start working with the identified COR at the site to commence the VA PIV process for all known contractor personnel that will be working the project. All contractors must have a PIV Card in order to work on site.

10.
2/9/2026
Are you able to confirm if there is any need for a BAS contractor as part of this project? If so, can you provide an overview?
Yes, BAS contractor is required. See Specification 23 09 23.
11.
2/9/2026
What VMS / NVR manufacturer is currently being used?
Pelco VideoXpert 3.22
12.
2/9/2026
How many licenses are available on the existing NVR?
Contractor shall provide new licenses for all new equipment provided on this project.
13.
2/9/2026

Specification 28 2300 – page 5 lists Wisenet XNP-6320 was the Basis of Design. However, in the drawings page 01T-901, Avigilon H5A PTZ camera is called out. Which camera is required for this bid?

Avigilon.

14.
2/9/2026
Is this to be bid as a full FIPS 203 or FIPS 204 environment and installation?
See Specifications for FIPS compliance requirements, including but not limited to, FIPS-200 and FIPS-201.
15.
2/9/2026
What is the existing CCURE system serial number?
Security Related – VA will not provide this information.
16.
2/9/2026
How many online readers are on the existing CCURE server?
Security Related – VA will not provide this information.
17.
2/9/2026
How many reader licenses total does the existing CCURE server have?
Security Related – VA will not provide this information.
18.
2/9/2026
What series is the existing CCURE server currently on?
The existing system is Software House C-CURE 9000, ver 2.70. Currently there isn’t an integration between the PACS and CCTV systems.
19.
2/9/2026
Is the existing CCURE server using CCURE high assurance for PIV card validation?
See RFI 18.
20.
2/9/2026
Is the existing CCURE server using HID pivClass and pivCheck soware?
See RFI 18.
21.
2/9/2026
Are PIV certificate validations done at the door or at the panel?
At the door.
22.
2/9/2026

Is there an existing intrusion detection system that we are adding on to and should be included in the scope of work?

A complete, fully functional system shall be provided.

23.
2/9/2026

Are all the motion detectors being installed in each TR monitored from the CCure or IDS monitoring.

CCure

24.
2/9/2026

Is this project tax-exempt, if so, will a certificate be provided?

See RFI 8.

25.
2/9/2026

ET series drawings for CCTV camera. Bid spec documents do not specified what system are currently in place for this project, please answer the following questions:

a. What is the manufacturer of the current video management system?

b. What version/existing is the current video management system operating?

c. Are we expected to support version upgrades as part of this contract?

d. Are there sufficient existing licenses to support the new cameras?

e. Are the cameras to be 2MP pan/tilt/zoom or fixed dome?

f. Is there a current vendor/installer of this system that we can contact Please provide contact information

Pelco VideoXpert 3.22

Not proprietary – currently for exterior cameras, our standards are the Pelco IMD15127 and IMD12136 cameras and the interior cameras are the Pelco IMF82-1ERS and SRXP4-5V10-IMD-IR cameras. The preferred models are IMD12136 and Pelco IMF82-1ERS.

26.
2/9/2026

ET series drawings for card reader/pin pad. Bid spec documents do not specified what system are currently in place for this project, please answer the following questions:

a. What is the manufacturer of the current access control system.

b. What version/existing software is the access control system operating.

c. Are we expected to support the version?

updates as part of the contract?

d. Are the sufficient licenses to support the new doors?

e. Is there any existing integration between the access control and CCTV systems?

f. Is there a current vendor/installer of this system that we can contact.

The existing system is Software House C-CURE 9000, ver 2.70. Currently there isn’t an integration between the PACS and CCTV systems.

27.
2/9/2026

Is there an allowance of Cat 6A cables & 1 ¼” data rough-in that should be carried within the Div.26&27 pricing? Some previous requirements on other projects requested 5-10% additional Cat 6A cables & 1 ¼” data rough-in to cover what may have missed during design.

Yes, there is a 10% allowance. See cover sheet, G-000 General Note #2 and T-700 series drawings.

28.
2/9/2026

Existing Fire Alarm System.

a. Q- Is there a current maintenance vendor/installer of this system that we can contact?

The system to be installed is Siemens Desigo Compact FV2025 panel.

29.
2/9/2026

Existing Nurse Call System.

a. Q- Is there a current maintenance vendor/installer of this system that we can contact?

Nurse call is not in scope.

30.
2/9/2026

Is conduit required for grounding conductors running/installed ceiling & risers?

Yes, 1" minimum.

31.
2/9/2026

Is there a requirement for x-ray scanning of concrete floor slabs prior to core drilling for floor-to-floor sleeves/conduits?

Yes.

32.
2/9/2026

Is there a location where site asphalt and concrete can be stored/separated? Can this material be removed from the site once per week?

Contractor must coordinate with COR for possible locations. Contractor must submit a written request for consideration.

33.
2/9/2026

Will soil testing be performed prior to construction, to determine if any soils are contaminated?

No.

34.
2/9/2026

Is there a location where spoil dirt can be stored?

See RFI 32

35.
2/9/2026

Is there a specific location that will be used as a laydown yard during construction?

See RFI 268.

36.
2/9/2026

Will erosion control plans be provided?

No. Contractor is responsible for developing and submitting Erosion Control Plans per Specification 01 57 19.

37.
2/9/2026

Has there been any boring samples/test made for duct bank pathway/trench to determine subsurface condition?

See Geotech report #70215256 by Terracon, dated 1/4/2023.

38.
2/9/2026
WAO-There are no prints that indicate Demo locations. Is this a 1 for 1 replacement for existing cables?
Provided in the documents. See General Note 1 on each building’s cover sheet.
39.
2/9/2026
Is there required a full survey of every room/above ceiling? If so, who dictates the outlet location and quantity of cables per location?
Yes, full surveys are required for all areas. WAO will be replaced in the existing locations. See T-700 series sheets for cable quantities plus the required 10% allowance. Cable length indicated is estimated and shall be independently verified by all Bidders. Deviations in the actual installed cable length will not be treated as an unforeseen condition.
40.
2/9/2026
Can the government provide a quantity of CAT6 A cables that need to be installed by TR? Please provide a Drop Count Matrix that needs to be provided.
See T-700 series sheets for cable quantities plus the required 10% allowance. Cable length indicated is estimated and shall be independently verified by all Bidders. Deviations in the actual installed cable length will not be treated as an unforeseen condition.
41.
2/9/2026
What is the drop count of each coverage zone? If it is a 1 for 1 swap, how many existing drops are located in each coverage zone?
A Drop count list was provided by the A&E. See T-700 series sheets for cable quantities plus the required 10% allowance. Cable length indicated is estimated and shall be independently verified by all Bidders. Deviations in the actual installed cable length will not be treated as an unforeseen condition.
42.
2/9/2026
Are there a count and length for Cat6A patch cords?
Patch cords shall be provided and installed by the contractor at each End User Device (EUD) and in each respective TR for all ports. Patch cords at the EUD shall match existing length for each location. Contractor will be required to field verify, procure, test, and install each cable. Patch cables installed in each TR rack shall be sized per EHRM standard rack elevations with a clean installation.
43.
2/9/2026
Are there a count and length for Fiber Patch cords?
Patch cords shall be provided and installed by the contractor at both ends of all Fiber Optic Cable provided and installed on this project. The contractor shall provide a fully-functional, fully-patched system for all cable on this project.
44.
2/9/2026
Is armored fiber acceptable or is Maxcell or innerduct required for ISP fiber?
Innerduct, Maxcell or equal is required for all ISP fiber.
45.
2/9/2026
Are there specific lengths for the CAT6A patch Cords?
Patch cords shall be provided and installed by the contractor at the End User Device (EUD) and in each respective TR for all ports. Patch cords at the EUD shall match existing length for each location. Contractor will be required to field verify, procure, test, and install each cable. Patch cables installed in each TR rack shall be sized per EHRM standard rack elevations with a clean installation.
46.
2/9/2026
Are we to provide one patch cord each end for every new CAT6A cable installed? Or will the VA specify a quantity for the Technology contractor to provide?
Patch cords shall be provided and installed by the contractor at each End User Device (EUD) and in each respective TR for all ports. Patch cords at the EUD shall match existing length for each location. Contractor will be required to field verify, procure, test, and install each cable. Patch cables installed in each TR rack shall be sized per EHRM standard rack elevations with a clean installation.
47.
2/9/2026
Are we to provide patch cables for each pair of strands at each end?
Patch cords shall be provided and installed by the contractor at both ends of all Fiber Optic Cable provided and installed on this project. The contractor shall provide a fully functional, fully patched system for all cable on this project.
48.
2/9/2026
Is there any copper backbone (25-pair or larger) needed?
The existing copper backbone is being retained and reused.
49.
2/9/2026

Please confirm if we will be allowed to keep a locked storage container or Conex box within the grounds.

Contractor will be required to provide the VA detailed written requests for lay down yard accommodations.

50.
2/9/2026

Please clarify note #43 on plan 01T-001 with your intent. Also, what does CPCI stand for/meaning.

43. J-HOOK ROUTING IS AN "IN-THE-FIELD" INSTALLATION CHOICE AND SHALL BE REQUIRED TO BE DOCUMENTED ON ALL AS-BUILT PACKAGES. SLEEVES REQUIRED TO COMPLETE THESE J- HOOK ROUTINGS SHALL BE CONSIDERED AND INCLUDED IN THE J-HOOK ROUTE EQUIPMENT PACKAGE FROM THE CONTRACTOR AS CPCI PATHWAY EQUIPMENT. J-HOOK SLEEVES THROUGH RATED AND NON-RATED ASSEMBLIES SHALL NOT BE A REQUIREMENT OF THIS DRAWING PACKAGE AS THEY ARE FIELD DEFINED LOCATIONS AND QUANTITIES.

The contractor shall bid 100% cable tray as indicated on the contract drawings and specifications. All routes shall be field verified and submitted as “Coordination Drawings” as defined by the specifications. If coordination drawings indicate that above ceiling space constraints dictate the limited use of J-hooks, these locations will be reviewed on a case-by-case basis. Any location requiring limited J-hooks shall NOT result in additional costs or time to the Government.

CPCI = Contractor Provided Contractor Installed.

51.
2/9/2026

Please clarify note #31 on plan 01T-001 with your intent.

31.STANDARD WORKSTATION OUTLET (AKA WORK AREA OUTLETS OR WAO) SHALL CONSIST OF A 5S X 2-7/8 ” DEEP METAL BOX, FED WITH A CONDUIT. BACK BOX TO BE FITTED WITH SINGLE-GANG FINISH RING FOR 4-PORT FACEPLATE.ALL CONDUITS FOR TELECOMMUNICATIONS OUTLETS SHALL BE STEEL THIN WALL ELECTRICAL METALLIC TUBING (TYPE EMT) UNLESS OTHERWISE. UNDER NO CIRCUMSTANCES SHALL FLEXIBLE CONDUIT BE USED FOR PATHWAYS INDICATED ON THIS DRAWING. ALL CONDUITS FOR TELECOMMUNICATIONS OUTLETS ARE TO BE STUBBED TO NEAREST CABLE TRAY. CONTRACTOR IS TO ENSURE THAT NO CONDUIT EXCEEDS 40% FILL. IF EXISTING CONDUIT IS NOT LARGE ENOUGH TO SUPPORT NEW CAT 6A CABLE, CONTRACTOR SHALL PROVIDE THE MAXIMUM ALLOWABLE NEW CAT 6A CIRCUITS TO REPLACE EXISTING, PROVIDED AT THE NEAREST AVAILABLE DROP WITH EXISTING CONDUIT CAPACITY.

Q-Do you have quantities of WAO’s that do not meet the above note/requirement?

Q-If you do not have quantities, please give directions for bidding this scope.

Should we assume that all WAO’s do not meet the above requirements?

Contractor shall not exceed 40% fill using existing in-wall conduit. This requirement does not reduce the cable quantity required to be provided on this contract.

52.
2/9/2026

On “T” series Plan (Technology plans) shows the cable tray layout/routing in hallway & corridors with the A&B Fiber backbone installation in the same cable tray as the WAO CAT6 cable. Is this the intent to install fiber & CAT6 cable in the same cable tray? Please advise.

Drawings are schematic in nature. See Specification 27 05 36 for cable tray and fiber optic raceway requirements.

53.
2/9/2026

To confirm that the existing analog phone cable/system to remain & re-terminated/tested on new WAO plate, as per “T” series Plan key notes#13

Confirmed.

54.
2/9/2026
55.
2/9/2026
Is this project tax-exempt, if so, will a certificate be provided?
See RFI 8.
56.
2/9/2026

Referring to ET series for CCTV camera, the bid spec documents do not specify what systems are currently in place for this project. What is the manufacturer of the current video management system?

Pelco VideoXpert

57.
2/9/2026

Referring to ET series for CCTV camera, the bid spec documents do not specify what systems are currently in place for this project. What version/existing is the current video management system operating?

See RFI 56.

58.
2/9/2026

Referring to ET series for CCTV camera, the bid spec documents do not specify what systems are currently in place for this project. Are we expected to support version upgrades as part of this contract?

59.
2/9/2026
Referring to ET series for CCTV camera, the bid spec documents do not specify what systems are currently in place for this project. Are there sufficient existing licenses to support the new cameras?
See answer number 56. No – licenses for the system should be included with the cameras or at least carry the cost to add them for a working system.
60.
2/9/2026

Referring to ET series for CCTV camera, the bid spec documents do not specify what systems are currently in place for this project. Are the cameras to be 2MP pan/tilt/zoom or fixed dome?

See answer number 56. Not proprietary – currently for exterior cameras, our standards are the Pelco IMD15127 and IMD12136 cameras and the interior cameras are the Pelco IMF82-1ERS and SRXP4-5V10-IMD-IR cameras. The preferred models are IMD12136 and Pelco IMF82-1ERS.

61.
2/9/2026

Referring to ET series for CCTV camera, the bid spec documents do not specify what systems are currently in place for this project. Is there a current vendor/installer of this system that we can contact? Please provide contact information.

See RFI 56 & 60.

62.
2/9/2026

Referring to the ET series drawings for card reader/pin pad, the bid spec documents do not specify what system is currently in place for this project. What is the manufacturer of the current access control system?

63.
2/9/2026

Referring to the ET series drawings for card reader/pin pad, the bid spec documents do not specify what system is currently in place for this project. What version/existing software is the access control system operating?

64.
2/9/2026

Referring to the ET series drawings for card reader/pin pad, the bid spec documents do not specify what system are currently in place for this project. Are we expected to support the version updates as part of the contract?

65.
2/9/2026

Referring to the ET series drawings for card reader/pin pad, the bid spec documents do not specify what system are currently in place for this project. Are the licenses sufficient to support the new doors?

66.
2/9/2026
Referring to the ET series drawings for card reader/pin pad, the bid spec documents do not specify what system are currently in place for this project. Is there any existing integration between the access control and CCTV systems?
The existing system is Software House C-CURE 9000, ver 2.70. Currently there isn’t an integration between the PACS and CCTV systems.
67.
2/9/2026

Referring to the ET series drawings for card reader/pin pad, the bid spec documents do not specify what system are currently in place for this project. Is there a current vendor/installer of this system that we can contact? Please provide contact information.

See RFI 66.

68.
2/9/2026
Is there an allowance of Cat 6A cables & 1 ¼” data rough-in that should be carried within the Div.26&27 pricing? Some previous requirements on other projects requested 5-10% additional Cat 6A cables & 1 ¼” data rough-in to cover what may have been missed during design.
Yes, 10% allowance is required. See G-000 General Note 2 and T-700 series sheets. Cable length indicated is estimated and shall be independently verified by all Bidders. Deviations in the actual installed cable length will not be treated as an unforeseen condition.
69.
2/9/2026
Referring to the Existing Fire Alarm System, is there a current maintenance vendor/installer of this system that we can contact? Please provide contact information.
The existing Edwards EST system is monitored and service by Everon. It is to remain in place and active until the entire Siemens system is installed.
70.
2/9/2026

Referring to the Existing Nurse Call System. Is there a current maintenance vendor/installer of this system that we can contact? Please provide contact information.

Nurse call is not in scope.

71.
2/9/2026

Is conduit required for grounding conductors running/installed ceiling & risers?

See RFI 30

72.
2/9/2026

Is there a requirement for x-ray scanning of concrete floor slabs prior to core drilling for floor-to-floor sleeves/conduits?

Yes

73.
2/9/2026

Is there a location where site asphalt and concrete can be stored/separated? Can this material be removed from the site once per week?

74.
2/9/2026

Will soil testing be performed prior to construction, to determine if any soils are contaminated?

No

75.
2/9/2026

Is there a location where spoil dirt can be stored?

76.
2/9/2026

Is there a specific location that will be used as a laydown yard during construction?

See RFI 268.

77.
2/9/2026

Will erosion control plans be provided?

No. Contractor is responsible for developing and submitting Erosion Control Plans per Specification 01 57 19.

78.
2/9/2026

Has there been any boring samples/test made for duct bank pathway/trench to determine subsurface condition?

See Geotech report #70215256 by Terracon, dated 1/4/2023.

79.
2/9/2026

WAO-There are no prints that indicate Demo locations. Is this a 1 for 1 replacement for existing cables?

See General Note #1 on each cover sheet G-000. See T-700 series sheets for cable quantities plus the required 10% allowance.

80.
2/9/2026

Is there required a full survey of every room/above ceiling? If so, who dictates the outlet location and quantity of cables per location?

Yes, full surveys are required for all areas. WAO will be replaced in the existing locations. See T-700 series sheets for cable quantities plus the required 10% allowance.

81.
2/9/2026

Can the government provide a quantity of CAT6 A cables that need to be installed by TR? Please provide a Drop Count Matrix that needs to be provided.

See T-700 series sheets for cable quantities plus the required 10% allowance. Cable length indicated is estimated and shall be independently verified by all Bidders. Deviations in the actual installed cable length will not be treated as an unforeseen condition.

82.
2/9/2026

What is the drop count of each coverage zone? If it is a 1 for 1 swap, how many existing drops are located in each coverage zone?

See T-700 series sheets for cable quantities plus the required 10% allowance. Cable length indicated is estimated and shall be independently verified by all Bidders. Deviations in the actual installed cable length will not be treated as an unforeseen condition.

83.
2/9/2026

Is there a count and length for Cat6A patch cords?

Patch cords shall be provided and installed by the contractor at the End User Device (EUD) and in each respective TR for all ports. Patch cords at the EUD shall match existing length for each location. Contractor will be required to field verify, procure, test, and install each cable. Patch cables installed in each TR rack shall be sized per EHRM standard rack elevations with a clean installation.

84.
2/9/2026

Is there a count and length for Fiber Patch cords?

Patch cords shall be provided and installed by the contractor at the End User Device (EUD) and in each respective TR for all ports. Patch cords at the EUD shall match existing length for each location. Contractor will be required to field verify, procure, test, and install each cable. Patch cables installed in each TR rack shall be sized per EHRM standard rack elevations with a clean installation.

85.
2/9/2026
Is armored fiber acceptable or is Maxcell or innerduct required for ISP fiber?
Innerduct, maxcell, or equal is required per OIT ISTS.
86.
2/9/2026

Are there specific lengths for the CAT6A patch Cords?

Patch cords shall be provided and installed by the contractor at the End User Device (EUD) and in each respective TR for all ports. Patch cords at the EUD shall match existing length for each location. Contractor will be required to field verify, procure, test, and install each cable. Patch cables installed in each TR rack shall be sized per EHRM standard rack elevations with a clean installation.

87.
2/9/2026

Are we to provide one patch cord each end for every new CAT6A cable installed? Or will the VA specify a quantity for the Technology contractor to provide?

The VA will not provide direction on patch cable quantity. Patch cords shall be provided and installed by the contractor at the End User Device (EUD) and in each respective TR for all ports. Patch cords at the EUD shall match existing length for each location. Contractor will be required to field verify, procure, test, and install each cable. Patch cables installed in each TR rack shall be sized per EHRM standard rack elevations with a clean installation.

88.
2/9/2026

Are we to provide patch cables for each pair of strands at each end?

Patch cords shall be provided and installed by the contractor at both ends of all Fiber Optic Cable provided and installed on this project. The contractor shall provide a fully-functional, fully-patched system for all cable on this project.

89.
2/9/2026

Is there any copper backbone (25-pair or larger) needed?

The existing copper backbone is being retained and reused.

90.
2/9/2026

Please confirm if we will be allowed to keep a locked storage container or Conex box within the grounds.

Contractor to provide a detailed written request for lay down area. COR will coordinate with the facility as needed.

91.
2/9/2026

Please clarify note #43 on plan 01T-001 with your intent. Also, what does CPCI stand for/meaning.

“43. J-HOOK ROUTING IS AN "IN-THE-FIELD" INSTALLATION CHOICE AND SHALL BE REQUIRED TO BE DOCUMENTED ON ALL AS-BUILT PACKAGES. SLEEVES REQUIRED TO COMPLETE THESE J- HOOK ROUTINGS SHALL BE CONSIDERED AND INCLUDED IN THE J-HOOK ROUTE EQUIPMENT PACKAGE FROM THE CONTRACTOR AS CPCI PATHWAY EQUIPMENT. J-HOOK SLEEVES THROUGH RATED AND NON-RATED ASSEMBLIES SHALL NOT BE A REQUIREMENT OF THIS DRAWING PACKAGE AS THEY ARE FIELD DEFINED LOCATIONS AND QUANTITIES.”

The contractor shall bid 100% cable tray as indicated on the contract drawings and specifications. All routes shall be field verified and submitted as “Coordination Drawings” as defined by the specifications. If coordination drawings indicate that above ceiling space constraints dictate the limited use of J-hooks, these will be reviewed on a case-by-case basis. Any location requiring limited J-hooks shall NOT result in additional costs or time to the Government.

CPCI = Contractor Provided Contractor Installed.

92.
2/9/2026

Please clarify note #31 on plan 01T-001 with your intent.

31.STANDARD WORKSTATION OUTLET (AKA WORK AREA OUTLETS OR WAO) SHALL CONSIST OF A 5S X 2-7/8 ” DEEP METAL BOX, FED WITH A CONDUIT. BACK BOX TO BE FITTED WITH SINGLE-GANG FINISH RING FOR 4-PORT FACEPLATE.ALL CONDUITS FOR TELECOMMUNICATIONS OUTLETS SHALL BE STEEL THIN WALL ELECTRICAL METALLIC TUBING (TYPE EMT) UNLESS OTHERWISE. UNDER NO CIRCUMSTANCES SHALL FLEXIBLE CONDUIT BE USED FOR PATHWAYS INDICATED ON THIS DRAWING. ALL CONDUITS FOR TELECOMMUNICATIONS OUTLETS ARE TO BE STUBBED TO NEAREST CABLE TRAY. CONTRACTOR IS TO ENSURE THAT NO CONDUIT EXCEEDS 40% FILL. IF EXISTING CONDUIT IS NOT LARGE ENOUGH TO SUPPORT NEW CAT 6A CABLE, CONTRACTOR SHALL PROVIDE THE MAXIMUM ALLOWABLE NEW CAT 6A CIRCUITS TO REPLACE EXISTING, PROVIDED AT THE NEAREST AVAILABLE DROP WITH EXISTING CONDUIT CAPACITY.

Contractor shall not exceed 40% fill using existing in-wall conduit. This requirement does not reduce the cable quantity required to be provided on this contract.

93.
2/9/2026

Referring to note #31 on plan 01T-001, do you have quantities of WAO’s that do not meet the note/requirement?

94.
2/9/2026
Referring to note #31 on plan 01T-001, If you do not have quantities, please give directions for bidding this scope.
Bid the replacement of all cables and WAO on the project. In-wall conduit will be retained and reused.
95.
2/9/2026

Referring to note #31 on plan 01T-001, Should we assume that all WAO’s do not meet the above requirements?

96.
2/9/2026
On “T” series Plan (Technology plans) shows the cable tray layout/routing in hallway & corridors with the A&B Fiber backbone installation in the same cable tray as the WAO CAT6 cable. Is this the intent to install fiber & CAT6 cable in the same cable tray? Please advise.
Drawings are schematic in nature. See specifications for cable tray and fiber optic raceway requirements. All routes shall be field verified and submitted as “Coordination Drawings” as defined by the specifications.
97.
2/9/2026

Please confirm that the existing analog phone cable/system is to remain & re-terminated/tested on new WAO plate, as per “T” series Plan key notes#13 “ALL EXISTING ANALOG PHONE CABLE DEVIES AND TERMINATIONS ETC. SHALL REMINA OPERATION AT ALL TIMES AND SHELL BE RETAINED AND REUSED. PROTECT IN PLACE.”

98.
2/9/2026
BLD 1 NO Drawings provided for WARD STORAGE 397 per the finish schedule.
Ward Storage 397 has been removed from the finish schedule. See addendum 1 for revised schedule.
99.
2/9/2026
Please provide the survey by Terracon as mentioned in 01H-100 and sim.
See attached updated Specifications with Addendum 1.
100.
2/9/2026

Per Sheet 21A-201, there are three locations of coded note 3 existing door and wall to be demolished to accomadate new 8' door; however, at corridor 5 the middle coded note 3 location does not show the wall length that needs to be removed. Please provide length of wall to be remove.

See addendum 1 for revised Keynotes.

101.
2/9/2026

NO WALL AND DOOR PROTECTION FOUND IN DRAWINGS, PLEASE PROVIDE LOCATIONS REQUIRED.

See attached addendum 1 drawings.

102.
2/9/2026

PerF6/ES401 note 2 there are cable runs from building 21 to building 1; however, the scale on the detail is not measurable and the existing site is grayed out, there is no clear detail of what the trenching will be going through, ie. Asphalt, concrete sidewalk, curbs, lawns, landscape, etc. Please provide a measurable plan that indicates what is existing so quantities can be measured, and provide details and requirements of items to be replaced from trenching operation. Also please provide a trench profile for these cable runs.

103.
2/9/2026
For the site infrastructure of electric and telecom will horizontal boring be acceptable in lieu of trenching with concrete encasement under paved areas. If yes, please provide any sleeve requirements.
Horizontal boring is not allowed, trenching and concrete duct bank shall be provided for all locations. See Specification 26 05 41.
104.
2/9/2026

Sheet TS201 is marked "Not for construction" in the drawing area, but marked for construction in the past box. Please indicate if these plans are or are not for construction.

Disregard “NOT FOR CONSTRUCTION” label on TS2** sheets. See updated plans.

105.
2/9/2026

Per the TS labelled site plans, many of the hardscape, paving, and landscape areas are shown in light grey and not clearly marked; Please mark up the plans and indicate what will need replaced from trenching operations, provide details and requirements, ie. profiles, thickness, reinforcing, etc.

106.
2/9/2026

Per TS101, coded note 21 indicates a sidewalk with handrail, see detail E3/T-501; this detail only shows a concrete sidewalk profile, please provide drawings, details and requirements for the handrail.

Sidewalk Plan-CG101. See attached addendum 1 drawings.

107.
2/9/2026

Per 21A-101 coded note 14 indicates to add sidewalk with a detail cut F5/21A-301; however, that detail does not have any sidewalk shown, please provide details and requirements.

Sidewalk Plan-CG101. See attached addendum 1 drawings.

108.
2/9/2026

Per 21A-501 Architectural roof plan & details shows details for HVAC equipment pad framing and support; however, no roof plan is provided. Please provide a roof plan of the existing roof and provide location of new equipment curb. The roof on this buildling appears to be a pitched roof but the detail cuts seem to show it as a flat roof with membraone roofing.

There is no new HVAC equipment on the roof of B21 with this project.

109.
2/9/2026

Per 21M-101 coded note 13 indicates to provide an new equipment pad. 21M-501 has detail D1 concrete equipment base detail, this detail seems to be for interior equipment bases, not exterior. Please provide details and requirements for the CRAC unit equipment pad .

110.
2/9/2026

Ref: 28 13 00 Physical Access Control System. We know the manufacture of the door hardware, however, can we get a picture of the locking hardware on one of the doors and/or the name of the locking hardware we need to quote?

Coordinate with VA for station standards and see Specification 08 71 00.

111.
2/9/2026

In the Specs it states build a schedule based on 540 days, but the contract is for 731 days. Which is true?

The period of performance is 731 calendar days from issuance of notice to proceed.

112.
2/9/2026

In the specs, it states that the work will require working in multiple buildings at once. Will multiple superintendents be required?

113.
2/9/2026

Will we be able to work in areas with sensitive information, if so when will access be available?

Coordinate with VA for access. Contractor must submit detailed written requests for VA review and approval, including coordination with all appropriate VA staffs.

114.
2/9/2026

What are the hours of operation? Will some of this work have to be done after-hours?

Yes, all cable replacements, shutdowns and above ceiling work shall be performed after-hours.

115.
2/9/2026

Duct Bank Installation Responsibility Please clarify who is responsible for the installation of the duct bank inside the building.

Is the site contractor expected to stub up just outside the building, or is it our responsibility to run conduit inside the building footprint?

Contractor shall run duct bank into the building per PSRDM requirements.

116.
2/9/2026

Plan Discrepancy – VF101 vs. TS101 There appears to be a conflict between Sheet VF101, which shows only two new lines being installed to the building, and Sheet TS101, which shows multiple lines extending throughout the site.

We were told the scope includes only two runs at 9,000 LF total (x2 conduits), but TS101 appears to show a significantly larger amount of duct bank.

Please clarify which sheet reflects the correct duct bank layout and quantity.

VF101 is a site survey plan only to indicate existing conditions. TS series sheets show all the new work. Provide duct bank per TS series sheets and all associated contract requirements.

117.
2/9/2026

Number of Main Lines It was also stated that there are four main lines coming from Ramsey, but the plans (including Detail T-501) only show two lines.

Please confirm how many duct bank lines are intended to be installed from the Ramsey tie-in point.

VF101 is a site survey plan only to indicate existing conditions. TS series sheets show all the new work. Provide duct bank per TS series sheets and all associated contract requirements.

118.
2/9/2026

Erosion Control There is no erosion control plan provided in the current drawing set.

Given the scope and disturbance area, it is expected that erosion control measures will be required.

Please confirm whether a separate erosion control plan will be issued, or if the site contractor is expected to include erosion control as part of this scope.

Contractor is responsible for developing and submitting Erosion Control Plans per Specification 01 57 19.

119.
2/9/2026

Tie-in Manhole Locations There is no clear detail or plan showing where the tie-in manholes for the main duct bank runs are to be installed.

Please provide a plan and details identifying all tie-in structures, including their elevations and locations.

See TS series sheets.

120.
2/9/2026

We see the note 2 under general notes on the G-000 sheets regarding the allowance we are to include for 10% new data drops and understand these new ones are to be surface mounted. Are the new conduits to be painted to match the walls. If so, will the entire wall, corner to corner to be painted? If either of these are the case, please provide an allowance in square footages to include for new wall painting. Or are all of the additional to be assumed to be added in existing data boxes to where no additional finishes will be required?

The 10% allowance refers to total cable/WAO/port quantities.

121.
2/9/2026

Note 4 on G-000 implies 50% of the existing data lines in outlets are not in conduit. If this is the case, confirm we are to provide pricing for 50% of the existing to be in new surface mounted conduit?

Confirmed.

122.
2/9/2026

If we are to include 50% of the existing to be new conduit, will they need to be painted as well? Please provide SF of wall to be painted as well.

Confirmed.

123.
2/9/2026
Dwg 45M-101, keynote 6 states to secure condensate piping to the wall. Confirm this piping is to be inside the staff toilet or the corridor?
Route condensate drain line outside, coordinate location with Owner.
124.
2/9/2026
The detail on 45M-501 shows the sink to be a floor sink. Confirm there is a floor sink in the staff toilet room. If not a floor sink, is the line to drain into the wall sink?
Route condensate drain line outside, coordinate location with Owner.
125.
2/9/2026
Dwg 45M-201 shows the outdoor unit on the roof, while 45M-101, note 12, calls for 4” housekeeping pad, please clarify if the unit is on the roof or on the ground.
Drawing 45M-201 does not exist. Outdoor unit shall be on a pad at grade. Coordinate final location with Owner.
126.
2/9/2026

Dwg 45E-501, note 3, states existing doors shall be recertified as required, please clarify what and how these existing doors are to be recertified.

See Division 8 specifications.

127.
2/9/2026

Section 01 00 00 – 22 K states 7’ construction fence to be placed around the construction area where indicated on the drawings. Please confirm no temporary construction fence is required, if so, please provide drawings.

Fence is required for all site work as indicated on the drawings.

128.
2/9/2026
Have borings been done to show the potential water table around the campus? If so, please provide or confirm we should not anticipate the need for dewatering.
See Geotech report #70215256 by Terracon, dated 1/4/2023. – “No free water observed” within 30’ of surface.
129.
2/9/2026
Section 01 00 00 E, Appendix E, ACM Inspection and Lead Paint Screening Report, is not included in the specifications where noted on page 00 01 10-1. Should we have access to this report?
See attached updated Specifications in addendum 1.
130.
2/9/2026
Spec section 02 21 13, Site Surveys, this spec section appears to be for a design build type project and not a utility project. We understand the need for providing as-builts but do not see where a site surveyor would be needed. Please clarify the scope for the Site Surveyor
Comprehensive site surveys and deliverables sealed by a PLS are required as indicated in Specification 02 21 13.
131.
2/9/2026

Will ACAD drawings be provided for the as-builts or a complete site plan PDF?

ACAD files that are available will be provided for reference. The contractor shall provide professional survey services and develop a comprehensive site plan showing existing conditions coordinated with new work.

132.
2/9/2026
Dwg 45E-701, the existing breaker panel that is to be replaced appears to be recessed in the wall. Can the new panel be surface mounted in its place, or does it need to be recessed within the existing wall, likely requiring the opening to be wider. If to be recessed, confirm the existing wall is metal stud/ gyp and deep enough to encase the new panel.
Surface mounting is acceptable provided all clearances are maintained and the existing recess is finished to match adjacent.
133.
2/9/2026

Dwg 45T-101 note 8, the three green dots at each end, are all three conduits to extend under the floor and out the foundation wall?

These dots indicate proposed conduit entrance locations. Contractor is responsible for developing coordination drawings indicating the final route and fiber entry locations with required pull boxes.

134.
2/9/2026
Dwg 45T-101 shows fiber coming into the building opposite the comm room, with no exit of the building 45, while fiber B appears to be coming into the building at the comm room and no being brought in through the slab. Please clarify.
See Site plan for additional context. Fiber paths enter from opposite sides of the Building. Contractor shall coordinate final routing.
135.
2/9/2026
Dwg 71H-100, Please clarify if we are to assume the walls in the comm room H128 contain lead paint and is to be abated. The legend states NA but shows confirmed.
Lead paint has not been confirmed in this location.
136.
2/9/2026
Dwg 71A-400 keynote 9 states telecom room walls to become 1 hr rated. With the removal of the ceilings system, do the exiting walls, both below and above the existing ceiling require new drywall? What is the approximate height of the area above the existing ceiling?
Yes, above and below existing ceiling to be upgraded to 1-hr rated. Refer to partition Type B legend on 71A-400. Height of area above ceiling is approximately 3 feet, but needs to be verified in field.
137.
2/9/2026

Dwg 71A-400 – the new telecom door is shown to be 8’ tall, please confirm the is correct and the existing door is also 8’. If existing door is not 8’, but only 7’, anyway to confirm no electrical is in the wall or the area to be removed?

Existing door is 7’ and new door will match existing.

138.
2/9/2026
Please confirm the utilities will be marked by others prior to excavation of the duct bank.
Contractor is responsible for a comprehensive site survey and utility locates.
139.
2/9/2026
The paths for the duct banks are stated as suggested. How do we account for any additional asphalt and/or concrete if the DBs are rerouted to where additional costs are incurred? Confirm this will be a changed site condition.
Contractor shall submit final routes based on approved site surveys and utility coordination. Coordinated routes are NOT a changed site condition.
140.
2/9/2026
Will temp fencing be required along the duct bank and be moved as progresses?
Yes.
141.
2/9/2026
There is not a plan showing where silt fence is to be placed, please provide.
See specifications for temporary fencing requirements.
142.
2/9/2026
What is the cure time of the concrete placed for the duct bank before backfilling?
See Specification 03 30 00 Part 3.10.
143.
2/9/2026
Site VF 101 shows 2 duct bank lines from Ramsey while TS 101 only shows one, please clarify the difference between these sheets of plans.
VF101 is a site survey plan only to indicate existing service provider fiber to remain. TS series sheets show all the new work. Provide duct bank per TS series sheets and all associated contract requirements.
144.
2/9/2026

Please provide a detail showing how the duct banks are to be tied into the manholes. Are the sweeps to be encased as well?

Follow specification 26 05 41.

145.
2/9/2026

Was told at the walk-through new ceilings are being replaced in the hospital corridors under a current project. Any chance these ceilings can be lowered in that project to minimize issues for installing the duct bank at tight conditions?

No. This project may not be dependent on another future project.

146.
2/9/2026
The specs call for a firm to be contracted by the GC for special inspections. Is this required for this project, if so, please clarify their role.
Yes, special inspections are required as indicated in Specification 01 45 35.
147.
2/9/2026
All the doors shown to be replaced are implied to be in metal stud/gyp walls with none showing to be in CMU walls. Demo and installation of the frames take a lot more work if the walls are of CMU. Please confirm none of the doors are in CMU walls that are to be replaced.
Doors within CMU walls have been noted on plans.
148.
2/9/2026
Where the conduits enter the building, likely brick could be damaged. Any chance the faculty has left over brick in case brick are damaged?
Contractor shall be responsible for repairing masonry to match existing.
149.
2/9/2026
Of the walls that are to be removed, please confirm they are of metal stud/ gyp as implied. Removal of CMU walls cost more than removal of gyp walls.
CMU walls have been noted on plans.
150.
2/9/2026

Are all exterior walls of every building brick on CMU? Boring through CMU cost more than through metal/stud gyp. Most of the buildings imply the duct bank conduit are to enter the building through the slab requiring removal and replacement of concrete and floor coving at those locations, along with building a chase to cover the conduits at the interior. It would be less expensive, bring the conduit up the exterior of the walls and entering above the ceilings, even if the exterior walls are of brick and CMU.

Conduit must enter as shown, under the building, through the floor per VA Physical security requirements.

151.
2/9/2026

Are the disturbed areas to be replaced with sod or hydroseed?

Yes, as applicable. All areas shall be returned to existing conditions.

152.
2/9/2026
Dwg TS-101 - The path of the duct bank plan west of the parking area 4, may require the removal of a few bushes behind the two small buildings. Is it necessary for these bushes to be replaced?
Contractor shall coordinate final route and return landscaping to existing conditions.
153.
2/9/2026
Dwg TS-101, plan north of THH#2B, shows the duct bank will be in the woods, trees will need to be removed. Please confirm additional trees will not be required to be planted to replace the removed trees.
See addendum 1 for updated site plan. This route has been adjusted.
154.
2/9/2026
Dwg 03H-100, detail C5 shows to provide a construction fence around two dumpsters. This area appears to at an active construction fenced in area. Confirm this project will likely be completed by the time this project starts.
Coordinate with VA for temporary construction provisions. Location is subject to change based on current construction activities.
155.
2/9/2026
Dwg 01H-100 shows only 887sf of lead paint to be abated. Confirm this does include both rooms indicated on this sheet. Since the heights of the walls are not shown, one would think the lead paint qtys would be greater than the amount shown. Please confirm.
Estimated quantity is provided for reference only. LBP shall be assumed on all surfaces for the rooms indicated and abated completely.
156.
2/9/2026

Regarding CCTV Storage requirements:

Please confirm the required video retention architecture.

Is CCTV video required to be stored on-site, off-site, or in a hybrid configuration?

If off-site or hybrid storage is required, must it be in a VA-approved cloud or enterprise environment?

What is the required retention duration for recorded video?

On-site only, 30 days.

157.
2/9/2026

Regarding Environmental sensors scope:

The documents refer to environmental monitoring. Please clarify What environmental conditions are required to be monitored (temperature, humidity, leak detection, smoke, door status, etc.)?

Are sensors required in all telecom rooms/MDF/IDFs or additional spaces?

Is integration with an existing VA monitoring platform required?

New monitoring platform(s) are required. Specifically, for the MCR reference Mechanical drawings for Building 21 and Division 23 & 25 specifications.

For TRs, split systems shall have thermostat and humidity monitoring and control. Humidity shall be controlled by operating the indoor units in “dry mode”.

See Specification 23 09 23 for integration.

158.
2/9/2026

Third-Party Inspection Requirements:

Please confirm inspection and testing requirements.

Must third-party inspections be performed by an independent firm separate from the installation contractor?

If required, will the Prime/Government provide the inspector, or should subcontractors include this cost in their bid?

Third-party inspections shall be provided by an independent firm separate from the installation contractor or prime contractor. See Specifications 01 00 00 and 01 45 00 for additional requirements.

159.
2/9/2026

Labor Rates for Third-Party Personnel Please clarify pricing responsibility for third-party labor.

Are labor rates pre-established by the VA/Prime, or should subcontractors include market-rate pricing?

If established, please provide the applicable labor categories and rate schedule.

Please follow solicitation guidance.

160.
2/9/2026

Subcontractor Qualification Requirements:

Please confirm subcontractor’s credential and experience requirements.

Are Division 27/28 subcontractors required to meet the same minimum qualifications, certifications, and past-performance requirements as the Prime contractor? If so, please provide the specific credentialing and experience thresholds required for subcontractors performing this scope

Please follow solicitation guidance.

161.
2/9/2026

Pricing Responsibility When Work Is Subcontracted Please clarify pricing expectations when portions of the work are subcontracted.

If portions of the Division 27/28 scope must be…

This is the start of the file's text. The full file is on GovTribe.