Tech Questions Tracker - MT Home Combined - 4-9-26.pdf

PDF 592 KB Posted

Attached to
C1DZ--621-24-701 EHRM Infrastructure Upgrades Tier 3 Data Center Construction - Mountain Home VAMC
Solicitation number
36C77626B0006
Issued by

About this file

This document is a Technical Questions and Responses Tracking Sheet for federal solicitation 36C77626B0006 concerning EHRM Infrastructure Upgrades Tier 3 Data Center Construction at Mountain Home VAMC. The project involves constructing a new data center (Master Computer Room) with relocating existing IT infrastructure while maintaining operations of an occupied medical facility. The contract is set aside as a 100% competitive Service-Disabled Veteran-Owned Small Business (SDVOSB) award, requiring all bonding through SDVOSB entities or SBA/VA-approved Mentor-Protégé partnerships. The government anticipates award 30-45 days after bid receipt, with Notice to Proceed (NTP) issuance within 90 calendar days thereafter. The period of performance is 365 calendar days after NTP.

Key scope requirements include: supplying and installing 29 network cabinets (Chatsworth ZetaFrame basis of design), structured cabling (Category 6A copper and fiber optic with pre-termination between racks), uninterruptible power supply (UPS) systems, heating/cooling infrastructure, fire suppression (NOVEC 1230 clean agent), fire alarm integration, intrusion detection systems, access control integration, and associated electrical and telecommunications work. The project requires normal work hours 7:00 AM to 4:40 PM with provision for off-hours work at contractor's cost. Prevailing wage applies per Attachment 7 (Washington County, TN). This is a firm fixed price contract with no economic price adjustment clause; all cost escalation must be included in the bid. The project is not tax-exempt; Tennessee sales taxes are the contractor's responsibility. Key personnel requirements include dedicated Superintendent, Site Safety and Health Officer (SSHO), and Contractor Quality Control (CQC) System Manager with no double- or triple-hatting allowed. All contractor personnel require VA Personal Identity Verification (PIV) cards, obtained through the VA badging process immediately after bond submission. Design team members are precluded from bidding as prime contractors, Mentor-Protégé partners, or subcontractors.

View the file

Other files

File Type Posted
36C77626B0006 0008.pdf PDF
Bid opening 4.16.2026 - 2pm.pdf PDF
260408_Addendum 04.pdf PDF
36C77626B0006 0007.pdf PDF
Server and TR - Electrical Load Estimation.pdf PDF
Tech Questions Tracker - MT Home Combined - 3-25-26.pdf PDF
36C77626B0006 0006.pdf PDF
Addendum 03.pdf PDF
0005 - Electrical Narrative - 621-24-701.pdf PDF
0005 - HVAC Narrative - 621-24-701.pdf PDF
0005 - Architectural Narrative - 621-24-701.pdf PDF
0005 - Telecommunications Narrative - 621-24-701.pdf PDF
36C77626B0006 0005.pdf PDF
0005 - Fire Protection Narrative - 621-24-701.pdf PDF
0005 - Structural Narrative - 621-24-701.pdf PDF
Tech Questions Tracker - MT Home Combined - 3-24-26.pdf PDF
0005 - Environmental Narrative - 621-24-701.pdf PDF
Tech Questions Tracker - MT Home Combined - 3-16-26.pdf PDF
36C77626B0006 0004.pdf PDF
Addendum 02.pdf PDF
36C77626B0006 0003.pdf PDF
36C77626B0006 0002.pdf PDF
Site Visit Sign-In Sheet - 2-12-2026.pdf PDF
36C77626B0006 0001.pdf PDF
Attachment 6 - Pre- Construction Risk Assessment.pdf PDF
Attachment 7 - Washington Co Bldg Construction Wage Determinations 1.2.2026.pdf PDF
36C77626B0006_1 - 1-29-2026 - FINAL.pdf PDF
Attachment 1 - V1_621-24-701_Specifications.pdf PDF
Attachment 8 - Site Visit Instructions - 2-12-2026.pdf PDF
Attachment 9 - Limitations on Subcontracting - Construction.pdf PDF
Attachment 2 - V2_621-24-701_Specifications.pdf PDF
Attachment 4 - Addendum 01 to Specs - 621-24-701 - 12-22-25.pdf PDF
Attachment 5 - Statement of Work - 621-24-701 EHRM - Tier 3 DC - Mtn Home.docx DOCX document
Attachment 3 - CONSTRUCTION DRAWINGS-COMBINED EHRM 621-24-701.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL QUESTIONS AND SOLICITATION #: 36C77626B0006

RESPONSES TRACKING SHEET PROJECT TITLE:

621-24-701 EHRM Infrastructure Upgrades Tier 3 Data Center Construction - Mountain Home

VAMC

# RECEIVED ANSWERED CONTRACTOR QUESTION VA RESPONSE

1 Will the Government provide detailed written requirements for contractor badging? Please clarify the process for obtaining PIV badges, including required documentation, background checks, and estimated processing timeframes.

Regardless of affiliation, everyone working within VA facilities or requiring access to VA information systems requires a VA PIV Card.

PIV badging requirements can be found at https://www.osp.va.gov/How_To_Get_A_VA_ID_Badge.asp

Immediately after the bonds are provided to the Government, the contractor shall immediately start working with the identified COR at the site to commence the VA PIV process for all known contractor personnel that will be working the project. All contractors must have a PIV Card in order to work on site.

2 Please confirm that any designers or consultants who provided professional services for the construction documents, including reports, are precluded from pursuing this project as a Prime contractor, Mentor- Protégé partner, or subcontractor.

Any member of the design team of this project is not permitted to be part of the construction team.

3 Please confirm that this project is a competitive SDVOSB set-aside and that any bonding provided by a contractor must be through a SDVOSB or SBA/VA APPROVED Mentor-Protégé partnership under the SBA/VA Mentor-Protégé program in which the partnership has been approved prior to the due date.

This project is set aside for SDVOSBs. The bonding requirements must be met for this project per the applicable clauses, provisions, and instructions to offerors.

https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.osp.va.gov%2FHow_To_Get_A_VA_ID_Badge.asp&data=05%7C02%7C%7C02d066cae89d4a9d6b3008de627d340b%7Ce95f1b23abaf45ee821db7ab251ab3bf%7C0%7C0%7C639056487045311207%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=dqbsmZbRft%2BkBDeSt2Q5Tf2K5e6EtTUwK0%2BETGjzJo8%3D&reserved=0

4 1) Should we include the 29 network cabinets in our bid or will be VA be providing those?

a. If we provide, do you have a cabinet brand you prefer?

b. Document “Attachment 2 - V2_621-24- 701_Specifications“ page 374 says “cabinets and related equipment should be white in color” Is black an acceptable color substitute?

c. Same document, page 358 says “provide six keys to COR for each cabinet”. Page 374 contradicts that and says “provide two per cabinet”.

Which is correct?

d. Same document says, the cabinets need to be “Compliant with facility’s SMS card access system”. What is your card access system brand and model?

e. Same document, page 374 says provide a “Vertical Exhaust Duct” for each server cabinet where it calls for this optional item. Should we assume ALL cabinets get the VED or just some? Please clarify.

2) Same document, Page 374 says we “Must supply 45U of 1RU blanking panels for each cabinet”. Page 377 contradicts that and says “provide enough to fill 75% of all RUs in each server and network cabinet”. Which is correct?

1) Yes, the network cabinets are CFCI.

a. Basis of design: Chatsworth ZetaFrame Cabinet (PN:ZB14-

A222Ae1) or equivalent.

b. VA to confirm.

c. VA to confirm preference.

d. VA to confirm.

e. Provide VED for all cabinets.

2) Refer to 377 for blanking panels.

5 What color do the phenolic nameplates and associated text on them need to be?

Refer to specification 26 05 11 Requirements for Electrical Installations §1.11

6 1) Several places in same document says “All cabling used shall be pre-terminated and procured to the specific length required by the design (horizontal and vertical paths) with no more than 1 meter of excess length on each end”. Is that statement accurate or can we fusion splice all fiber cable on this project like we normally do? Quoting and ordering per-terminated fiber cable to exact lengths will be extremely hard, if not impossible to do.

2) Same document, page 359 says, “Provide minimum one cabinet with blank rack space, for additional system expansion equipment” Is that accurate? If so, should that cabinet be installed in the MCR or just warehoused at your location somewhere?

3) Same document, page 361 says, “Provide each cabinet with an internal UPS”. Do you have a preferred make/model/part # or additional specification requirements that we should quote?

1) All interconnections within the MCR rack lineup, from one rack to another, needs to be pre-terminated. Cabling leaving the racks, exiting the room shall not be pre-terminated.

2) Disregard providing one additional blank cabinet. Cabinets shall be provided as shown on the construction documents drawings.

3) Centralized UPS in use within MCR. No rack mounted UPS.

7 Please provide the sign schedule and spec section. Refer to specification 10 14 00 & 01 28 26 per Addendum 2.

8 The VA’s Master Specification 01 32 16.15, 'Project Schedules' (Small Projects – Design/Bid/Build), was revised effective December 1, 2025. The updated version is now available on the Technical Information Library (TIL). Will the VA be updating the 01 32 16.15 spec for this project to include this spec instead of the older one?

This has already been updated. See Addendum 1 dated 12/22/25 posted in the original solicitation.

9 Also will the VA still keep in VAAR 852.232-71 or will VAAR 852.232-70 replace this Clause?

VAAR 852.232-71 is to be replaced by VAAR 852.232-70. This project will now adhere to VAAR 852.232-70.

10 Drawing EP102 shows mechanical units 77-ERU-1 feeding from MCR EQ B and 77-ERU-2 feeding from MCR EQ A, both located in room 3A212. However, the E-601 One-Line Diagram for Panels MCR EQ A and MCR EQ B does not show the feeders or breakers for these units. Could you please provide the feeder and breaker sizes for 77-ERU-1 and 77-ERU- 2?

These outdoor units are powered via indoor units. Coordinate with mechanical contractor for more information.

11 Regarding the basket tray shown on drawing TN402, what are the required dimensions? Additionally, does the drawing represent a single tray or multiple trays?

Cable tray shall be sized to hold the maximum expected cable load at not more than 40% fill and not more than 6” maximum cable depth. 270536 2.1, C. Refer to Telecommunications and Architectural Floor Plans.

12 Does the VA utilize a specific vendor to service the existing fire alarm system? If so, please provide their contact information.

Johnson Controls Simplex office number: 423-467-3547

13 Does the VA utilize a specific vendor to service the existing clean agent system? If so, please provide their contact information.

Johnson Controls Simplex office number: 423-467-3547

14 Where will the designated contractor lay-down area and office trailer yard be located?

Refer to sheet AS001. Coordinate with the VA on lay-down location.

15 Will onsite parking be available for contractors and crew? If so, will there be a designated area, and what is its proximity to the project site?

Contractor parking shall be co-located with the Contractor laydown site identified on Drawing AS001.

16 Will the owner accept Procore Project Management software as the primary submittal and data tracking tool for this project?

Procore – No Substitute

17 How many calendar days should be included in the critical-path method schedule for owner and A/E submittal review?

See POP for overall calendar days. Refer to documents for period of performance.

18 How long after award will the Government provide the submittal register?

General contractor shall generate their own submittal register in Procore.

19 Please clarify whether QC Manager candidates with directly relevant QC experience on comparable Federal construction projects may be considered acceptable if their formal education differs from the degree described in the solicitation/specification/01 45 00, provided their qualifications are documented in the proposal/QC Plan submittal.

Contract documents provide qualification requirements for QC/QA Managers. Qualifications may not be substituted.

20 Confirm the required number of submittal copies/digital format and turnaround time expectations per VA electronic submittal procedures (new section in addendum).

Digital format for product information submittals is acceptable to Spur. Actual physical material samples need to be provided per the specifications and catalogued digitally.

Review durations to be determined post bid award. Digital submittals are required to be submitted through Procore per specifications.

21 If double- or triple-hatting is not permitted, please confirm acceptable alternatives, such as designating a qualified alternate SSHO or QC representative under the superintendent's oversight, and any documentation/submittal requirements to demonstrate independence and competency.

No role shall be double- or triple-hatted. SSHO and QA/QC personnel shall meet qualifications stated in the contract.

22 Will the VA permit the use of Procore or an equivalent construction management software platform for submittals and project communications?

Procore – No Substitute

23 Will the owner accept the “Primavera P6” for schedule submission and monthly updates?

MS Project shall be used for scheduling - No Substitute.

PDF copies shall be shared with the project team.

24 Is this project tax-exempt, and will the CO/COR provide the necessary tax-exempt certificates?

No

25 Because of COVID-19 throughout the U.S. and the resulting Federal, State and local governments’ responses/requirements, are there any new work requirements or mandates that will be required by the VA on this project?

VA to confirm any such requirements specific to their station.

26 Many VA campuses are beginning to address tuberculosis protocols on VA campus projects, including the 90-day screening before assignment to the worksite. This requirement will limit the amount of personnel who can immediately perform work right after the award. Will this project be required to follow 01 35 26 1.13 for TB-required protocols and a requirement to follow the 90-day screening before beginning work on the project?

Per specification 01 35 26 1.16, tuberculosis protocols are included with this contract.

27 What is the approximate duration between issuing the award and issuing the NTP?

The Government anticipates issuance within 90 calendar days after award.

28 For planning the preliminary project schedule, please provide an anticipated award date.

Award is anticipate to be around 30-45 days after bids are received.

29 How many calendar days should be included in the critical-path method schedule for the owner and A/E to review and respond to RFIs?

Reference question #17

30 Will the Government provide the 3-D REVIT Design model in native file format for the creation of coordination drawings and use by contractor?

VA can provide 2D CAD files upon request.

31 1.Please confirm that the project scope will be completed during normal working hours, not nights and weekends.

Per specification 01 10 11 3.G, normal work hours will be from 7:00am to 4:40pm (local time). Nights and weekend work to be coordinated with the COR and performed as required. Bids shall include an allowance for off-hours work requirement.

32 2.What are the station’s normal work hours? Will work be restricted to normal business hours, or will the VA require night/weekend work due to the Tier 3 Data Center environment?

Per specification 01 10 11 3.G, normal work hours will be from 7:00am to 4:40pm (local time). Nights and weekend work to be coordinated with the COR and performed as required. Bids shall include an allowance for off-hours work requirement.

33 3.Given that this is an operational medical facility with high traffic and specific ICRA requirements, is it permissible to perform work in common areas, such as corridors, after normal business hours?

Per specification 01 10 11 3.G, normal work hours will be from 7:00am to 4:40pm (local time). Nights and weekend work to be coordinated with the COR and performed as required. Bids shall include an allowance for off-hours work requirement.

34 Where will the designated laydown area be for the

GC?

Refer to AS001. Coordinate with the VA on lay-down location.

35 Can you confirm that the owner will be contracting directly with a third-party commissioning agent for commissioning the project and that the Contractor is only to include participation/coordination with the Commissioning Agent?

Refer spec section 01 91 00.

VA has contracted with 3rd party Cx agent.

36 Are there specific testing/certification standards (e.g., TIA-568, BICSI) and documentation formats required for fiber and copper cabling commissioning?

The Contract Documents incorporate by reference the following standards and design manuals, including but not limited to:

VA Office of Information & Technology Infrastructure Standard for Telecommunications Spaces (ISTS) v4.0

VA PG-18-10 Telecommunications and Special Telecommunications Systems Design Manual

BICSI standards

ANSI/TIA-942-B

Applicable Telecommunications Industry Association (TIA) standards as defined in VA PG-18-10

Contractor shall test, certify, and document all copper and fiber optic cabling installations in accordance with the above referenced standards and their latest adopted editions as of the date of the Contract Documents.

Test documentation shall demonstrate compliance with the performance category specified and be submitted in manufacturer-native electronic format from the field test instrument, including complete parameter results. As-built documentation, cable schedules, labeling records, and warranty certification shall be included in the closeout submittal.

37 Clarify the level of commissioning required (e.g., Level 4 or 5 per VA specs) for power, cooling, fire suppression, and communications systems, including who provides the Commissioning Authority.

Refer spec section 01 91 00 for general requirements. Items/ scopes/ divisions that require commissioning are listed in each specification section. Contractors are responsible for all commissioning requirements in accordance with the specifications.

38 Has the facility Operation & Maintenance team reviewed the Contract Documents for operability to avoid change orders?

Contractor is responsible to review contract documents for operability.

39 Can the contractor use an existing office inside the building for a temporary construction office during construction instead of setting up a temporary trailer?

Temporary office space inside the VA facility will not be provided.

40 Can the contractor use the existing restroom facilities in the work area or adjacent ones nearby?

Public restroom facilities within the VA may be used but shall be left in good condition by the contractor.

41 Can the contractor use the existing on-site utilities for temporary electrical and water free of charge?

Contractor must provide physical connections to VA utilities if available. VA will supply power and water free of charge after contractor physically connects to service. Bids shall include an allowance for generators to provide temporary power to laydown site if access to VA utilities is not possible.

42 Will the owner provide the fire watch during the period that the fire suppression and/or fire alarm system is not in service?

All firewatch must be provided by the contractor.

43 Please provide detailed guidance for noise and vibration operations, including acceptable levels/duration, hours of operations for acceptable levels, and acceptable noise levels after hours.

Refer to specification 01 00 00 1.6.G

44 1.Can the QA/QC dual hat as the Superintendent?

2.Spec 01 45 00 3.4 B. (pg. 6&7) calls specifically for the superintendent to hold QC role: “The CQC System Manger is assigned as CQC System Manager but has duties as project superintendent in addition to quality control.”

3.Can the government please confirm that the response provide to numerous questions that does not allow the QC role to be dual hatted is going to over ride the specification that requires the superintendent and QC to be held by 1 person?

See Addendum 3: CQC System Manager: Identify as CQC System Manager an individual within the onsite work organization that is responsible for overall management of CQC and has the authority to act in all CQC matters for the Contractor. The CQC system Manager is required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of 10 years construction experience on construction similar to the scope of this Contract. This CQC System manager is on the site at all times during construction and is employed by the General Contractor. Identify in the plan an alternate to serve in the event of the CDQC System Manager’s absence. The requirements for the alternate are the same as the CQC System Manager.

45 Can the SSHO dual hat as a Superintendent? No role shall be double- or triple-hatted. SSHO and QA/QC

46 Has the owner entered into an agreement with the owner-furnished equipment vendor?

Contractor shall furnish all labor, materials, and equipment required to complete this project IAW the design and specifications.

47 In the RFP it states there is an asbestos report.

Please provide report.

Hazardous material survey report provided within Environmental Design Narrative; . For the narrative, see Amendment 0005, 0005 - Environmental Narrative - 621-24-701.

48 Can the owner confirm that the General Contractor is to not include any Asbestos or Lead Removal?

All abatement shall be provided by the contractor. Known environmental hazards identified in contract documents.

49 Has the work area been checked for asbestos, lead-based materials, and/or other hazardous materials? Is there a report available?

See response to questions 47 & 48.

50 What is the Government's policy if asbestos products are encountered during construction which is not quantified in the construction documents?

All abatement shall be provided by the contractor. Known environmental hazards identified in contract documents. For the narrative, see Amendment 0005, 0005 - Environmental Narrative - 621-24-701.

51 Keynote A2 on HA101, says to "remove window assembly with underlying presumed asbestos framing/plug caulks and seals within a negative air pressure enclosure, 3 window assemblies. Install fire-treated plywood cover adequately secured over window opening, 1 window cover." AE102, Keynote

8.94 appears to be showing a window film on the existing windows. Please clarify what is correct.

Only remove window gasketing as required to apply blackout film as per AE Keynote 8.94. Window frames are to remain intact and should not be disturbed. Note that asbestos containing caulking/sealants associated with original window systems are presumed present and concealed/hidden behind exposed frames.

Any work requiring window frame removal must be performed by a licensed abatement contractor.

52 Drawing HA101 shows 4 windows on East side to be within the work area. The 2 windows in 3A113 and 1 window in 3A112 are identified to contain asbestos but not the window in 3A112A. does the window in 3A112A contain asbestos?

Room 3A112A window frames are to remain intact and should not be disturbed. Note that asbestos containing caulking/sealants associated with original window systems are presumed present and concealed/hidden behind exposed frames. Any work requiring window frame removal must be performed by a licensed abatement contractor.

53 Drawing HA101 note A2: The window in 3A112 is identified to contain asbestos and is scheduled to be removed and replaced with fire rated wood. Drawing AE101 note 8.94 calls for the window to be disassembled completely film applied and reinstalled.

Can the VA please clarify if the existing window is to be abated and reinstall or is being replaced?

Only remove window gasketing as required to apply blackout film as per AE101 Keynote 8.94. Window frames are to remain intact and should not be disturbed. Note that asbestos containing caulking/sealants associated with original window systems are presumed present and concealed/hidden behind exposed frames.

Any work requiring window frame removal must be performed by a licensed abatement contractor.

54 Drawing HA101 note A6: The windows in 3A113 are identified to contain asbestos and are scheduled to be protected only no removal or abatement. Drawing AE101 note 8.94 calls for the window to be disassembled completely film applied and reinstalled.

Can the VA please clarify if abatement of these 2 windows is within the scope of this project?

Only remove window gasketing as required to apply blackout film as per AE101 Keynote 8.94. Window frames are to remain intact and should not be disturbed. Note that asbestos containing caulking/sealants associated with original window systems are presumed present and concealed/hidden behind exposed frames.

Any work requiring window frame removal must be performed by a licensed abatement contractor.

55 Will the windows be removed or will they just receive a blackout film.

Only remove window gasketing as required to apply blackout film.

56 Are there any known asbestos-containing materials (ACM) or other hazardous materials in rooms 3A112, 3A112A, etc., and if so, can the VA provide survey reports or abatement requirements?

Yes. Please refer to Drawing HA101 and contract specifications for details. Hazardous material survey report provided within Environmental Design Narrative. For the narrative, see Amendment 0005, 0005 - Environmental Narrative - 621-24-701.

57 Are there any known asbestos-containing materials (ACM) or other hazardous materials in rooms 3A112, 3A112A, etc., and if so, can the VA provide survey reports or abatement requirements?

Yes. Please refer to Drawing HA101 and contract specifications for details. Hazardous material survey report provided within Environmental Design Narrative. For the narrative, see Amendment 0005, 0005 - Environmental Narrative - 621-24-701.

58 Please confirm if any hazardous material abatement required in this project. If so, Will the VA provide recent asbestos and lead survey reports?

Yes. Please refer to Drawing HA101 and contract specifications for details. Hazardous material survey report provided within Environmental Design Narrative. For the narrative, see Amendment 0005, 0005 - Environmental Narrative - 621-24-701.

59 Can the existing service and/or public elevators be used for construction activities? Are there any restrictions or time constraints?

Service elevator may be used for construction related tasks.

60 Will the Government consider candidates with extensive relevant experience and CQM-C certification as meeting the qualification requirements in lieu of a formal degree, consistent with FAR and VA guidelines that allow for equivalent experience for technical roles?

Contract documents provide qualification requirements for QC/QA Managers. Qualifications may not be substituted.

61 Please confirm if the Government will consider a QA/QC organization in which the named QC Manager provides overall program management and decision-making authority, while on-site inspections and documentation are carried out by project-dedicated QC personnel reporting to that individual.

Contract documents provide qualification requirements for QC/QA Managers. Qualifications may not be substituted.

62 May CQM discipline-specific staff (HVAC, plumbing, electrical, low voltage, civil, etc.) be provided by trade subcontractors performing the work, rather than directly by the CM, provided they meet the minimum experience requirements?

Reference specification 01 45 00 3.4.C

63 Who is the current fire alarm vendor on site? Johnson Controls Simplex office number: 423-467-3547

64 Who is the current fire sprinkler subcontractor on site? Contractor to subcontract fire sprinkler related work.

65 Who is the CCTV vendor/system on site? Avigilon

66 Who is the access control vendor on site? Hirsh Velocity: PACS System

67 Please confirm if the sprinkler heads will need to be turned up while the acoustical ceiling tile is out.

Confirmed, the VA requires interim protection during construction.

Construction area shall have either a 1 hour fire rated barrier around the construction site, or sprinkler head shall be turned up when the acoustical ceiling tiles are removed.

68 Please confirm if existing floors will need to be covered with a self-leveling material?

Refer to 09 05 16 Subsurface Preparation for Floor Finishes

69 Can the loading dock area be used for dumpsters? if not, provide the location.

Dumpster shall be located at the contractor's laydown site.

70 Provide the path for the removal of debris. Debris removal path shall be coordinated with the COR, path shall minimize disruptions to the operation of the hospital.

71 Will the project require power system studies such as Protective Device Coordination and Arc Flash?

A coordination study, arc flash calculations, and short circuit calculations are required for this project. Specification section 26 05 73 Overcurrent Protective Device Coordination Study is included in Addendum 02, issued as part of Amendment 0004.

72 Can the VA provide as-built drawings or surveys of the existing MCR (room 3A109) showing current equipment layout, power distribution, cooling infrastructure, and cable routing to facilitate accurate relocation planning?

Existing MCR layout represented in contract drawings. No existing as built drawing exists.

73 What is the exact VA Tier 3 data center standards (e.g., specific references from VA OIT Infrastructure Standards, PG-18-10 Electrical Design Manual, or OEHRM requirements) that the new MCR must meet, particularly for redundancy (N+1 or 2N) in power and cooling? Please confirm if the required redundancy is concurrently maintainable (Tier 3) level, and provide details on the existing normal, emergency, and UPS sources serving Floor 3 of Building 77.

The design is informed by the referenced standards and others within the PG-18-10 series, including the HVAC Design Manual, taken as a whole rather than specific cited sections.

Information on the existing normal, emergency, and UPS sources serving Floor 3 of Building 77 is shown on the one-line diagram on sheet E-601.

74 Are there any restrictions on shutdown durations or required phasing for existing MCR power/cooling systems during relocation to avoid impacting hospital operations?

Yes. Refer to phasing information in contract documents specifically the narratives and drawings. Refer to RFI 116 below. Refer to Amendment 0005, and all the attached 0005 - Architectural Narrative - 621-24-701.

75 Please provide the current load calculations (kVA/kW) for the existing MCR equipment and projected loads for the relocated Tier 3 setup to confirm UPS and power infrastructure sizing.

Total MCR load calculated for new equipment is in bid documents under the file name ‘Server & TR - Electrical Load Estimation.pdf’.

No existing load calculations were performed. Provided in Amendment 0006

76 For the clean-agent fire suppression system: Which specific agent (e.g., FM-200, Novec 1230) is preferred or approved by VA for occupied spaces, and are there cylinder storage location preferences beyond room 3A112A?

Basis of design calculations for the renovation is NOVEC 1230. See FG101 general note 4.

77 Confirm whether the new fire-rated assembly in the MCR requires a specific fire-resistance rating (e.g., 2-hour) and if UL-listed assemblies or equivalent are acceptable.

Refer to partition tags on AE101 and Partition Types on AE001.

78 Please clarify acceptable firestop systems (e.g., specific manufacturers/products listed in VA master specs) for walls/floors in the new MCR spaces.

Refer to Specification Section 07 84 00 for performance requirements. Contractor to submit product for review to ensure that it meets performance requirements.

79 For HVAC upgrades and Johnson Controls DDC:

Provide the current DDC protocol/version and integration requirements for tying new controls into the existing VA building management system (BMS).

Can you also give us the current Local JCI reps contact information.

Coordinate current local BMS contractor information with VA medical staff.

Johnson Controls Rep: Mike Scarbrough - Michael.Scarbrough@jci.com

80 Please confirm acceptable testing/adjusting/balancing (TAB) procedures and certification requirements for the new computer room cooling systems per VA specs.

Refer to Specification section 23 05 93 for further information.

81 For structured cabling (DIV 27): Confirm required fiber types (e.g., OM4 multi-mode, OS2 single mode) and redundancy configurations (A/B diverse paths) for backbone cabling to the new MCR.

All information regarding fiber types and redundancy can be found within the contract documents. Specifically, the Telecommunications Drawings, Narrative, and specs. For the narrative, see Amendment 0005, 0005 - Telecommunications Narrative - 621-24-701.

82 Clarify if the new MCR requires a dedicated telecommunications grounding busbar (TGB) and if it must connect to the building main grounding electrode system per VA and NEC requirements.

Yes. Refer to Telecommunications Drawings for more information.

See Amendment 0005, 0005 - Telecommunications Narrative - 621- 24-701.

83 Are there preferred rack/enclosure manufacturers or VA-approved products for the new MCR (e.g., specific ladder rack, tray, or cabinet types)?

Refer to contract documents (specifically the Telecommunications Drawings, Narrative, and specs), and OIT Design Guide Templates found on the TIL for VA-approved products. For the narrative, see Amendment 0005, 0005 - Telecommunications Narrative - 621-24- 701.

84 Please provide access protocols, badging requirements, and escort procedures for contractor personnel working in occupied Floor 3 areas during construction.

Refer to Question 1 response.

85 Interim Life Safety Measures (ILSM): Confirm specific ILSM requirements for work near patient care areas, including fire watch, temporary barriers, and notification procedures.

Refer to sheet GI002 and Spec Section 01 35 26 Safety Requirements.

86 In the addendum to the specs (Attachment 4)- The addendum revised contractor work hours—please clarify if overtime or off-hours work is permitted/required for critical tie-ins or shutdowns, and any associated costs.

Per specification 01 10 11 3.G, normal work hours will be from 7:00am to 4:40pm (local time). Nights and weekend work to be coordinated with the COR and performed as required. Bids shall include an allowance for off-hours work requirement.

87 Provide preferred or required sequence for demolition of existing MCR equipment vs. build-out of new spaces to minimize downtime.

Existing MCR shall not be demolished under this project. For phasing requirements refer to contract documents.

88 For selective demolition: Confirm if existing equipment in room 3A109 is to be removed by contractor, turned over to VA, or disposed of, and any salvage credits.

None of the above. Existing MCR shall not be demolished under this project.

89 Structural modifications: Are engineer-stamped calculations or shop drawings required for any minor wall/ceiling penetrations or reconfigurations in the affected rooms?

Penetrations through non-structural walls/ceilings are generally acceptable without review. No penetrations, holes or other modifications shall be made through new or existing structural members without first contacting the EOR for approval, unless such penetrations are already shown and detailed on the structural drawings.

90 Confirm acceptable flooring types (e.g., anti-static raised floor or sealed concrete) and painting specifications for the new MCR to meet Tier 3 environmental controls.

Refer to sheet AE601. No raised flooring in this project.

91 Infection Control Risk Assessment (ICRA): Provide the required ICRA class for this project and any specific barriers, negative pressure, or HEPA filtration needs.

Refer to sheet GI002. It was determined during the design of this project that Category D, Low Patient Risk is attributed to this project per the VA provided ICRA sheet. This results in a Level III level of precautions. Contractor is to verify and coordinate ICRA requirements with the VA. Refer to specification section 01 35 26 Safety Requirements for additional information.

92 Can the VA locate and mark existing utilities (power, fiber, HVAC lines) in rooms 3A112 series prior to demolition/start of work.

Contractor to field verify all existing conditions prior to demolition/start of work.

93 Clarify if independent third-party testing is required for specific items (e.g., firestopping, cable certification, TAB) and approved labs.

Not Mechanical & not required

94 With the revised period of performance in addendum, confirm if the 365-day completion includes phased substantial completion for partial MCR activation.

The period of performance for project completion is 365 days after issuance of the Notice to Proceed.

95 Confirm if any wage determination updates apply beyond Attachment 7 (Washington County, TN), and if certified payroll is required weekly or bi-weekly.

Attachment 7 is to be followed.

Also, per FAR 52.222-8 (DEV NOV 2025) Payrolls and Basic Records in the solicitation/contract. Payrolls are required to be submitted weekly.

96 Can the VA schedule a follow-up walkthrough of the affected rooms (3A109, 3A112 series) for bidders/contractors to verify field conditions and measurements?

No additional site visit will be scheduled.

97 Is the use of Johnson Controls Direct Digital Controls (DDC) a mandatory/brand-name-only requirement with no substitutions permitted or is it specified as a basis of design/preferred system where products of equal performance and compatibility from other manufacturers acceptable?

No, coordinate current local BMS contractor information with VA medical staff. Open protocol BMS system required, provide integration.

98 If DDC substitutions are permitted, please confirm the specific performance, protocol, and integration requirements that an alternate DDC system must meet, including: Compatibility and full interoperability, Supported communication protocol, Cybersecurity compliance, Any required licensing, programming tools, training, or maintenance contract implications, demonstration of seamless integration without additional cost.

Please refer to Specification Section 23 09 23.

99 If Johnson Controls is required due to existing system compatibility or standardization at this facility, please provide: Confirmation of the current BMS platform and version in use, Any VA-approved justification for brand-name specification, details on whether the contractor would be required to coordinate directly with Johnson Controls or an authorized representative for programming/integration and the email and contact info who the current representative is.

Controls contractor shall be responsible for verifying all existing BMS systems compatibility with VA and manufacturer. Coordinate current local BMS contractor information with VA medical staff.

100 In Section 01 35 26 (Safety Requirements) or equivalent, the SSHO must often be a separate qualified individual from the Prime Contractor's Superintendent and/or Quality Control Manager, with duties only as the SSHO. Please confirm if the Project Superintendent can serve concurrently as the SSHO (double-hatting) for this project, or if a dedicated, separate SSHO is required at all times when work is performed.

No role shall be double- or triple-hatted. SSHO and QA/QC personnel shall meet qualifications stated in the contract.

101 Per Division 01 Quality Control requirements (e.g., Section 01 45 00 or similar), is the Project Superintendent permitted to also serve as the Contractor Quality Control (CQC) Manager (double-hatting), or must these be separate personnel to ensure independent quality oversight and documentation?

102 For smaller or less complex projects, some VA contracts allow limited combining of key roles. Please clarify if triple-hatting (one individual serving as Project Superintendent, SSHO, and CQC Manager simultaneously) is acceptable on this Tier 3 Data Center relocation project, or if dedicated separate personnel are required for each role to meet safety, quality, and supervision mandates in an occupied VA medical facility.

103 Confirm the minimum qualifications for the SSHO (e.g., OSHA 30-hour certification, EM 385-1-1 experience, etc.) and whether the SSHO must be full-time dedicated on-site with no other duties (no double- or triple-hatting allowed), especially during high-hazard activities like electrical work, HVAC modifications, or demolition in the MCR areas.

No role shall be double- or triple-hatted. SSHO and QA/QC personnel shall meet qualifications stated in the contract.

104 The solicitation requires the contractor to provide supervision, with the superintendent typically required to be physically present on-site at all times when work is being performed. Please confirm if this full-time on-site requirement applies strictly to the superintendent, and if any double hatting with SSHO or QC roles would violate this presence mandate.

105 Given the project's focus on relocating the MCR with minimal disruption (including potential phased shutdowns/tie-ins), clarify if combining roles (e.g., superintendent doubling as SSHO) is allowable during low-activity phases or if separate personnel are required throughout the 365- day performance period to maintain continuous safety and quality oversight.

No role shall be double- or triple-hatted. SSHO and QA/QC personnel shall meet qualifications stated in the contract.

106 In other VA EHRM infrastructure upgrade projects (e.g., similar Tier 3 data center or critical IT room relocations), VA has often required separate SSHO and QC personnel from the superintendent to ensure impartiality. Please provide any project-specific guidance or references from the specs/addenda on whether role combining (double/triple-hatting) is prohibited or restricted for this Mountain Home project.

107 Drawing TN405. Is there a difference between the Equipment Distributor Cabinet and the Server Cabinet?

In terms of functionality? Yes. In terms of cabinet? No.

108 Drawing TN405. Do we need to provide and install the Equipment Distributor Cabinets and Server Cabinets?

If yes, please provide the specified manufacturer and part number.

Cabinets are CFCI. Refer to question 4 for basis of design.

109 Drawing TN405. Please provide more information on the 6” Cable Management sidecars to/for Network Cabinet

Basis of design: OR-MM20VMD706.

110 Drawing TN501 Do we need to provide and install the “fiber pathway channel” referenced in Detail #6? If yes, please provide additional information and installation location(s).

Yes. These are for intra-mcr rack lineup cabling. To be installed as needed. Refer to 255 below.

111 Drawing TN602 Please clarify which cabling description needs to be followed for the cable groups 60 & 61, per table or per schematic. 60 - RK104 to RK204 / RK104 to RK215 -or 61 - RK215 to RK114 / RK204 to RK114

60 = RK104 to RK215

61 = RK204 to RK114

112 The specifications call for polyiso SIPs. Would expanded polystyrene SIPs be considered and allowed?

Expanded polystyrene is an acceptable substitution.

113 Will the project require power system studies such as Protective Device Coordination and Arc Flash?

Duplicate response. Refer to question / response #71

114 Can the VA provide as-built drawings or surveys of the existing MCR (room 3A109) showing current equipment layout, power distribution, cooling infrastructure, and cable routing to facilitate accurate relocation planning?

No, as-built drawing is not available. Contractor shall verify all existing field conditions prior to bid.

115 What is the exact VA Tier 3 data center standards (e.g., specific references from VA OIT Infrastructure Standards, PG-18-10 Electrical Design Manual, or OEHRM requirements) that the new MCR must meet, particularly for redundancy (N+1 or 2N) in power and cooling? Please confirm if the required redundancy is concurrently maintainable (Tier 3) level, and provide details on the existing normal, emergency, and UPS sources serving Floor 3 of Building 77.

Duplicate question. Refer to answer #73.

116 Are there any restrictions on shutdown durations or required phasing for existing MCR power/cooling systems during relocation to avoid impacting hospital operations?

Yes. Refer to phasing information in contract documents specifically the narratives and drawings. Refer to RFI 74 above.

117 Please provide the current load calculations (kVA/kW) for the existing MCR equipment and projected loads for the relocated Tier 3 setup to confirm UPS and power infrastructure sizing.

Duplicate response. Refer to question / response #75.

118 For the clean-agent fire suppression system: Which specific agent (e.g., FM-200, Novec 1230) is preferred or approved by VA for occupied spaces, and are there cylinder storage location preferences beyond room 3A112A?

Basis of design calculations for the renovation is NOVEC 1230. See FG101 general note 4. If required cylinder storage may be coordinated with equipment in the MCR space. If possible locate all cylidner storage in room 3A112A.

119 Confirm whether the new fire-rated assembly in the MCR requires a specific fire-resistance rating (e.g., 2-hour) and if UL-listed assemblies or equivalent are acceptable.

Refer to partition tags on AE101 and Partition Types on AE001.

120 The solicitation references “Supplemental Insurance Requirements.” Can the VA confirm required limits (General Liability, Auto, Umbrella, Professional Liability, Pollution, Builder’s Risk), and whether cyber/data liability coverage is required due to EHRM scope?

See Section 4.5 of the solicitation for the requirements.

VA does not pay for Builders risk.

121 Please clarify acceptable firestop systems (e.g., specific manufacturers/products listed in VA master specs) for walls/floors in the new MCR spaces.

Refer to Specification Section 07 84 00 for performance requirements. Contractor to submit product for review to ensure that it meets performance requirements.

122 For HVAC upgrades and Johnson Controls DDC:

Provide the current DDC protocol/version and integration requirements for tying new controls into the existing VA building management system (BMS).

Can you also give us the current Local JCI reps contact information.

Coordinate current local BMS contractor information with VA medical staff.

DDC controls must be compatible with the existing building automation system.

Johnson Controls Rep: Mike Scarbrough - Michael.Scarbrough@jci.com

123 Please confirm acceptable testing/adjusting/balancing (TAB) procedures and certification requirements for the new computer room cooling systems per VA specs.

Refer to Specification section 23 05 93 for further information.

124 For structured cabling (DIV 27): Confirm required fiber types (e.g., OM4 multi-mode, OS2 single mode) and redundancy configurations (A/B diverse paths) for backbone cabling to the new MCR.

Duplicate. Refer to question / response #81.

125 Is this project exempt from sales tax? If so, will the VA provide a tax exemption certificate for material purchases?

No. See Special Note regarding FAR 52.229-3 Federal, State, and Local Taxes and Special Notes regarding FAR 52.229-3, in the solicitation. It is solely the responsibility of the offeror to include all state and local sales or use taxes for construction materials, and all other applicable taxes, in their bid or proposal price. Tennessee is NOT tax exempt.

126 Will payment applications be accepted for materials stored on-site or in a bonded off-site warehouse?

In accordance with contract terms and conditions, Contractors should not submit an offer assuming the Government will approve monthly progress payments for material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site. Payment of stored materials and/or equipment is at the Contracting Officer’s discretion and will be handled on a case-by-case basis during the contract and under such terms and conditions as the Contracting Officer approves.

127 Will the Government consider including an Economic Price Adjustment (EPA) clause to address significant fluctuations in material pricing?

This will be awarded as a Firm Fixed Price (FFP) contract and all escalation should be factored in your FFP. Additionally, FAR 52.216-4 “Economic Price Adjustment – Labor and Material” is not included in the solicitation and will not be added.

128 If tariffs are imposed on materials (e.g., steel, wood) after bid submission but before award, will the Government allow a price escalation even if the materials remain Buy American–compliant?

This will be awarded as a Firm Fixed Price (FFP) contract and all escalation should be factored in your FFP. Additionally, FAR 52.216-4 “Economic Price Adjustment – Labor and Material” is not included in the solicitation and will not be added.

129 Will the Government provide detailed requirements for contractor badging? Please clarify the PIV process, including documentation, background checks, and estimated processing time.

See response to #1.

130 How soon after contract award does the Government anticipate issuing the official Notice to Proceed?

The Government anticipates issuance within 90 calendar days after award.

131 Will the Government consider reducing the required bid validity period (e.g., to 60 days) to account for inflation and contractor pricing risk?

No

132 Can the Government confirm the stated contract duration is accurate, considering phased access and execution requirements?

The period of performance for project completion is 365 days calendar days after NTP.

133 The solicitation references “Supplemental Insurance Requirements.” Can the VA confirm required limits (General Liability, Auto, Umbrella, Professional Liability, Pollution, Builder’s Risk), and whether cyber/data liability coverage is required due to EHRM scope?

See response to #120.

134 May one individual serve in dual or multiple roles (SSHO, QCM, Superintendent) if fully qualified?

No role shall be double- or triple-hatted. SSHO and QA/QC personnel shall meet qualifications stated in the contract.

135 If not, may the Superintendent also serve as SSHO? No role shall be double- or triple-hatted. SSHO and QA/QC personnel shall meet qualifications stated in the contract.

136 Can the VA confirm the expected level of background investigations for contractor personnel and approximate processing timelines for clearance approvals?

Refer to Question 1 Response.

137 Will the contractor be required to provide a site office/trailer, or will space within the facility be made available?

Temporary office space inside the VA facility will not be provided.

138 Will the VA allow temporary connection to existing utility infrastructure, with the contractor responsible for metered usage?

Contractor must provide physical connections to VA utilities if available. VA will supply power and water free of charge after contractor physically connects to service. Bids shall include an allowance for generators to provide temporary power to laydown site if access to VA utilities is not possible.

139 Will designated parking and staging areas be provided for contractor personnel and deliveries? Will the VA provide laydown space or containers, or must these be arranged off-site?

Contractor laydown area identified on Drawing AS001. Dumpster shall be located at the contractor's laydown site.

140 Is there a freight or construction elevator that contractors will be required to use for material deliveries and equipment transport?

Service elevator may be used for construction related tasks.

141 What ICRA level is required for the project? It was determined during the design of this project that Category D, Low Patient Risk is attributed to this project per the VA provided ICRA sheet. This results in a Level III level of precautions.

Contractor is to verify and coordinate ICRA requirements with the VA. Refer to specification section 01 35 26 Safety Requirements for additional information.

142 If abatement is required, will the VA identify known ACM/LCM locations?

Refer to sheet HA101 in the drawings. VA to provide report.

143 If ACM remediation is required, can remediation activities be performed during normal working hours, or will after-hours work be required?

See response to questions 47 & 48.

144 Does the existing roof have an active warranty? If so, what company holds the warranty?

No warranty exists on the roof.

145 Does the VA have an existing fire alarm/security service provider? If so, please provide contact information for required coordination.

Johnson Controls Simplex office number: 423-467-3547

146 Will the facility remain occupied during construction, or will temporary relocation of staff/equipment be required?

Facility will remain occupied outside of scope areas. Contractor to coordinate schedule with VA to determine when temporary relocation of staff/equipment is required.

147 Will demolition of major systems (e.g., AHUs, utilities) require after-hours or phased work to minimize disruption?

Yes. For phasing requirements, refer to contract documents. For after hours work, coordinate with VA staff on station.

148 Will the VA provide temporary cooling/heating during system cutovers? If not, should the contractor include them?

Per specification 01 10 11.6 Use of Government-owned material and equipment is prohibited. If required the contractor will provide.

149 Are existing primary and secondary cable pathways intended to be reused?

Existing pathways will remain and be reused where feasible.

150 Will the Government provide a formal shutdown/outage approval process and outage window schedule for data center cutovers? If yes, what is the typical lead time required for outage approval?

Utility outages to be coordinated through COR.

151 During electrical cutovers, should the contractor include temporary generators/load banks to maintain Tier 3 operational continuity, or will the VA provide backup power continuity during…