0005 - Structural Narrative - 621-24-701.pdf

PDF 87 KB Posted

Attached to
C1DZ--621-24-701 EHRM Infrastructure Upgrades Tier 3 Data Center Construction - Mountain Home VAMC
Solicitation number
36C77626B0006
Issued by

About this file

This is a Structural Narrative document for a federal construction project (641-24-701) focused on EHRM Infrastructure Upgrades at a Tier 3 Data Center in Mountain Home, Tennessee. The project involves updating the main computer room in Building 77, with the computer room relocating southward within the building, and adding electrical equipment to Building 204.

Building 77 features lightweight concrete slab flooring over 3-inch metal deck supported by steel beams, girders, and columns, with Level 3 containing an additional 3-inch lightweight concrete topping slab. The roof system consists of 1½-inch metal deck on steel framing. Building 204 utilizes two-way concrete slab construction supported on concrete columns. The structural narrative confirms that renovations are primarily non-structural with no major changes to vertical or lateral load paths, and no new construction is required. The existing floor and roof structures have been reviewed and confirmed adequate to support new mechanical, electrical, and telecommunications equipment without structural modifications. Design standards referenced include PG-18-10 Structural Design Manual, the 2024 International Building Code (IBC), and the 2024 International Existing Building Code (IEBC). The contractor is required to verify all existing conditions in the field prior to construction.

View the file

Other files

File Type Posted
36C77626B0006 0008.pdf PDF
Tech Questions Tracker - MT Home Combined - 4-9-26.pdf PDF
260408_Addendum 04.pdf PDF
Bid opening 4.16.2026 - 2pm.pdf PDF
36C77626B0006 0007.pdf PDF
36C77626B0006 0006.pdf PDF
Server and TR - Electrical Load Estimation.pdf PDF
Tech Questions Tracker - MT Home Combined - 3-25-26.pdf PDF
Addendum 03.pdf PDF
0005 - Architectural Narrative - 621-24-701.pdf PDF
0005 - Telecommunications Narrative - 621-24-701.pdf PDF
0005 - Electrical Narrative - 621-24-701.pdf PDF
0005 - HVAC Narrative - 621-24-701.pdf PDF
Tech Questions Tracker - MT Home Combined - 3-24-26.pdf PDF
0005 - Environmental Narrative - 621-24-701.pdf PDF
36C77626B0006 0005.pdf PDF
0005 - Fire Protection Narrative - 621-24-701.pdf PDF
Tech Questions Tracker - MT Home Combined - 3-16-26.pdf PDF
Addendum 02.pdf PDF
36C77626B0006 0004.pdf PDF
36C77626B0006 0003.pdf PDF
36C77626B0006 0002.pdf PDF
Site Visit Sign-In Sheet - 2-12-2026.pdf PDF
36C77626B0006 0001.pdf PDF
36C77626B0006_1 - 1-29-2026 - FINAL.pdf PDF
Attachment 1 - V1_621-24-701_Specifications.pdf PDF
Attachment 8 - Site Visit Instructions - 2-12-2026.pdf PDF
Attachment 9 - Limitations on Subcontracting - Construction.pdf PDF
Attachment 6 - Pre- Construction Risk Assessment.pdf PDF
Attachment 7 - Washington Co Bldg Construction Wage Determinations 1.2.2026.pdf PDF
Attachment 3 - CONSTRUCTION DRAWINGS-COMBINED EHRM 621-24-701.pdf PDF
Attachment 2 - V2_621-24-701_Specifications.pdf PDF
Attachment 4 - Addendum 01 to Specs - 621-24-701 - 12-22-25.pdf PDF
Attachment 5 - Statement of Work - 621-24-701 EHRM - Tier 3 DC - Mtn Home.docx DOCX document
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT NUMBER 641-24-701 (2409)

PROJECT NAME EHRM Infrastructure Upgrades - Tier 3 DC

Mountain Home,TN SUBMITTAL Final Bid Documents

SUBJECT Structural Narrative

Structural - 1

Project Overview

The project includes updating the main computer room in building 77. The computer room will be moving south in building 77. Additional electrical equipment is being added to Building 204.

Existing Structure

The building 77 floor framing consists of lightweight concrete slab over 3” metal deck spanning between steel beams and girders supported on steel columns. Level 3 floor has an additional

3” lightweight concrete topping slab atop the floor structure. The roof framing is 1 ½” metal roof deck supported on steel beams and girders.

The existing structure of building 204 consists of two-way concrete slab supported on concrete columns.

All existing conditions shown on plan shall be verified in the field by the contractor.

Design Criteria

Design Manuals - PG-18-10 – Structural

IBC – International Building Code – 2024 Edition

IEBC – International Existing Building Code – 2024 Edition

Proposed Structural Changes

The renovations and upgrades of all rooms are primarily non-structural and currently do not cause any major changes to the vertical or lateral load path. There are no new buildings being constructed to support the EHRM project.

Stand has reviewed the existing floor and roof structures to confirm the adequacy for new mechanical electrical and telecom equipment as indicated on the structural design documents.

The floor and roof systems are adequate to support the equipment as indicated on the structural design documents without structural modifications to the buildings.

File details come from the government source that posted it. Updated .