0005 - Architectural Narrative - 621-24-701.pdf

PDF 189 KB Posted

Attached to
C1DZ--621-24-701 EHRM Infrastructure Upgrades Tier 3 Data Center Construction - Mountain Home VAMC
Solicitation number
36C77626B0006
Issued by

About this file

This is an Architectural Narrative for a federal construction project at the James H. Quillen VA Medical Center in Mountain Home, Tennessee.

The project (VA Project Number 621-24-701) involves relocating and upgrading the main computer room (MCR) on Floor 3 of Building 77 to achieve compliance with VA standards for a Tier 3 data center. Work spans multiple rooms (3A109, 3A112, 3A112A, 3A112D, 3A113, 3A113A, and 3A212) and includes redundant power distribution, computer room cooling, equipment replacement, grounding and bonding, cable management, fiber and copper cabling installation, a new clean agent fire suppression system with cylinder storage, and fire-rated enclosure construction. The ultimate design capacity is 100 kW, supported by two redundant 100 kW Liebert Vertiv APM2 UPS systems to handle a projected 90 kW telecommunications load. The Construction Cost Limitation is $6,248,000. Field investigations occurred in August 2024 and February 2025 to assess existing infrastructure and document the new MCR location following a contract modification.

The project is phased into four stages: demolition and preparation; new MCR construction with 1-hour fire-rated walls and sealed environment finishes; infrastructure installation including UPS systems, distribution busways, cabinets, cable management, bonding and grounding per TIA-607-D standards; and network migration, testing, and commissioning. The phased approach maintains MCR functionality during construction with minimal service interruptions. The contractor is responsible for developing and VA-approving construction phasing plans, coordinating with the VA Contracting Officer Representative, managing parking and staging, and performing site remediation throughout construction. Design compliance is required for VA design manuals, fire protection standards, seismic requirements, telecommunications infrastructure standards, and applicable national codes including NFPA, NEC, IBC, EPA, NSPC, and OSHA.

View the file

Other files

File Type Posted
36C77626B0006 0008.pdf PDF
Tech Questions Tracker - MT Home Combined - 4-9-26.pdf PDF
260408_Addendum 04.pdf PDF
Bid opening 4.16.2026 - 2pm.pdf PDF
36C77626B0006 0007.pdf PDF
36C77626B0006 0006.pdf PDF
Addendum 03.pdf PDF
Server and TR - Electrical Load Estimation.pdf PDF
Tech Questions Tracker - MT Home Combined - 3-25-26.pdf PDF
0005 - Telecommunications Narrative - 621-24-701.pdf PDF
Tech Questions Tracker - MT Home Combined - 3-24-26.pdf PDF
0005 - Environmental Narrative - 621-24-701.pdf PDF
0005 - Electrical Narrative - 621-24-701.pdf PDF
0005 - HVAC Narrative - 621-24-701.pdf PDF
36C77626B0006 0005.pdf PDF
0005 - Fire Protection Narrative - 621-24-701.pdf PDF
0005 - Structural Narrative - 621-24-701.pdf PDF
Tech Questions Tracker - MT Home Combined - 3-16-26.pdf PDF
Addendum 02.pdf PDF
36C77626B0006 0004.pdf PDF
36C77626B0006 0003.pdf PDF
36C77626B0006 0002.pdf PDF
Site Visit Sign-In Sheet - 2-12-2026.pdf PDF
36C77626B0006 0001.pdf PDF
36C77626B0006_1 - 1-29-2026 - FINAL.pdf PDF
Attachment 1 - V1_621-24-701_Specifications.pdf PDF
Attachment 8 - Site Visit Instructions - 2-12-2026.pdf PDF
Attachment 9 - Limitations on Subcontracting - Construction.pdf PDF
Attachment 3 - CONSTRUCTION DRAWINGS-COMBINED EHRM 621-24-701.pdf PDF
Attachment 6 - Pre- Construction Risk Assessment.pdf PDF
Attachment 7 - Washington Co Bldg Construction Wage Determinations 1.2.2026.pdf PDF
Attachment 2 - V2_621-24-701_Specifications.pdf PDF
Attachment 4 - Addendum 01 to Specs - 621-24-701 - 12-22-25.pdf PDF
Attachment 5 - Statement of Work - 621-24-701 EHRM - Tier 3 DC - Mtn Home.docx DOCX document
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA PROJECT NUMBER

PROJECT NAME

621-24-701 (2409) EHRM Infrastructure Upgrades – Tier 3 DC Mountain Home, TN

SUBMITTAL Final Bid Documents SUBJECT Architectural Narrative

Architecture 1

Project Overview and Background

The purpose of this project is to coordinate all design efforts to relocate the main computer room (MCR) on Floor 3 of Building 77 located at James H. Quillen VA Medical Center

(JHQVAMC) and make it compliant with VA standards for a Tier 3 data center. The area of work for this project will occur within rooms 3A109 (existing MCR), 3A112, 3A112A, 3A112D, 3A113, 3A113A, and 3A212. Work will include providing redundant power distribution, computer room cooling and distribution, replacement of aged equipment, grounding and bonding, cable management, and new fiber and copper to the new MCR. A new clean agent system will be provided, as well as a new fire rated assembly within the new MCR, ensuring that all penetrations are sealed appropriately. A new space will be provided in room 3A112A to host cylinder storage for the clean agent system. The clean agent releasing panel, which is not typically allowed to be located within the MCR, will be located in in room 3A212. The project will be designed so as not to exceed a Construction Cost Limitation of $6,248,000 without the consent of the VA.

A kickoff meeting was held virtually with the VA on August 21st, 2024 and field investigation occurred August 22nd-23rd, 2024, performed by the electrical and telecommunications teams.

The purpose of the visit was to conduct a preliminary investigation of the existing MCR, located in room 3A109, and its supporting infrastructure. During the visit, architectural measurements were taken and our electrical team surveyed lighting and power distribution for the MCR and supporting spaces. Existing computer room units (CRU), fire protection equipment, fire riser, clean agent tanks, and releasing panel were also identified and documented. Rooms surveyed included MCR 3A109, Telecom 3A110, Electrical Closet 3A115, Storage 3A107 (Electrical

Distribution Panel), UPS Room (Liebert) 3A108, and Telecom 3A221 in Building 77. Room

A006 (Demarc Room) was also investigated in Building 200 as well as the Switchgear L169

(Electrical Distribution Switchgear Room) in Building 204.

Due to Mod 1 of the contract, which changed the location of the new MCR, the Architectural team visited the facility on February 3rd, 2025 along with Telecom, Electrical, and Mechanical.

A visit by Physical Security and Fire Protection later occurred on February 6th, 2025. During

621-24-701 (2409) EHRM Infrastructure Upgrades – Tier 3 DC Mountain Home, TN

Architecture 2 this visit, field measurements and photographic documentation for the following spaces: Office

3A112, Storage 3A112A, Restroom 3A112D, Storage 3A113, and Kitchen 3A113A. These spaces will be altered to host the new MCR space.

Ultimate Design Capacity

Following the completion of the equipment layout and selection of design criteria–driven basis-of-design equipment, calculations identified a projected telecommunications load of 90 kW. To adequately support this load, the basis of design includes a 100 kW UPS system. The overall design has been coordinated across all disciplines around two 100 kW UPS systems to provide redundancy and ensure capacity for the 90 kW telecommunications load. The ultimate design capacity of the MCR will be 100 kW.

Occupancy & Classifications

No change in occupancy or classification is anticipated during this project. Life Safety sheets provided to show travel distances.

Construction Phasing

Project to be phased so that the existing MCR remains functional during construction and interruptions are kept at a minimum while services are switched over. Plans are to be developed by the Contractor and approved by the VA to eliminate interruptions or kept to an absolute minimum. Emergency egress shall not be compromised during construction.

Contractor parking and staging areas have not been identified. Staging for construction materials will be available as close as possible to affected buildings, if necessary, during construction. Contractor is responsible for building construction/demolition remediation throughout construction process until the work is accepted by the VA. Contractor to coordinate with VA COR prior to all construction phasing and staging while on station.

621-24-701 (2409) EHRM Infrastructure Upgrades – Tier 3 DC Mountain Home, TN

Architecture 3

Phasing shall be done in the following order:

PHASE 1 – DEMOLITION & PREPARATION

• Vacate rooms as indicated in demolition drawings.

• Demolish existing walls, ceiling systems, plumbing, HVAC, electrical, and telecommunications infrastructure.

• Cut new door openings and infill existing openings as required. Apply fire/smoke sealants to penetrations.

• Maintain existing cabling pathways where needed until replacement systems are

• installed.

PHASE 2 – NEW MCR CONSTRUCTION

• Construct new 1-hour fire-rated walls for the Main Computer Room (MCR).

• Perform mechanical, electrical, telecom, and fire protection rough-ins.

• Finish MCR interior surfaces to create sealed, clean-agent-compatible environment.

• Verify enclosure continuity floor-to-deck above.

• Apply dust mitigation materials (gasketed tiles, caulking, epoxy coatings, etc.).

PHASE 3 – INFRASTRUCTURE INSTALLATION

Install

• Redundant UPS systems (Liebert Vertiv APM2 or approved equal), dual A/B feed

• Overhead distribution busways with L21-20 tap boxes

• MDA and HDA cabinets (partial)

• Cable tray and raceway systems

• Bonding and grounding (TIA-607-D compliant)

• Security, lighting, CRU units on raised stands

• All systems sized per ultimate design capacity.

WAN Demarcation & Carrier Cutover

621-24-701 (2409) EHRM Infrastructure Upgrades – Tier 3 DC Mountain Home, TN

Architecture 4

• Install single-mode fiber from the existing Demarc Room (Telecom A006) to new MCR.

• This link shall become the new WAN demarcation point.

• If new cabinets have not been installed prior to fiber optic cabling from Demarc is

• installed, provide service loop and enclosure for fiber optic cabling to keep safe during construction until which time the fiber optic cabling can be terminated.

• Coordinate with the Local Exchange Carrier (LEC) for service handoff, splicing, and termination requirements.

• Label fiber type, termination points, and routing on final telecom drawings.

PHASE 4 – NETWORK MIGRATION, TESTING & COMMISSIONING

Core Switch Migration

• Phase 1: Deploy Core A in new MCR. Create a temporary interconnect (“umbilical”) to

Core B in the existing MCR to maintain network redundancy.

• Phase 2: Migrate Core B to new MCR. Complete permanent dual-core configuration.

Backbone Fiber Migration

• Extend backbone fiber from existing MCR to new MCR.

o To be done while backbone for respective Core switches which feed the backbone is being deployed to new MCR.

• Use existing pathways where possible.

• Re-terminate or fusion splice existing fibers to meet TIA-568 and HEFP standards.

• When necessary, deploy temporary parallel backbone routes to avoid service disruption.

• All fiber cabling to be labeled on both ends per VA OIT standards.

Equipment Migration

• Coordinate migration of network/server equipment cabinet mounted equipment (e.g., Cerner FDSS, IaaMS, Biomed).

• Prior to move:

621-24-701 (2409) EHRM Infrastructure Upgrades – Tier 3 DC Mountain Home, TN

Architecture 5 o Inventory cabinet contents.

o Validate destination cabinet locations and power (dual L21-20 feeds).

o Ensure UPS, CRU, bonding, and grounding are operational.

• Migrate equipment during low-usage windows to reduce impact.

• Maintain service redundancy through temporary cross-patching and umbilical links.

• Post-move: verify connectivity and operability before decommissioning legacy connections.

Applicable Codes, Standards, and Guidelines

The following codes, standards, and guidelines will be followed throughout the design of this project:

• Design Manuals (By discipline) PG-18-10

• Design and Construction Procedures PG-18-3

• A/E Submission Instructions, PG-18-15, Minor and NRM Projects Vol. C

• Standard Details and CAD Standards PG-18-4

• Equipment Guide List PG-18-5

• Equipment Guide List Index

• Architectural Barrier Act (ABA) Standards

• VA Barrier Free Design Standard (A Supplement to the ABA) PG-18-13

• VA Signage and Wayfinding Design Manual PG-18-10

• Master Construction Specifications PG-18-1

• Space Planning Criteria PG-18-9

• Design Guides (graphical, by function) PG-18-12

• Room Finishes, Door, and Hardware Schedule PG-18-14

• NEPA Interim Guidance for Projects PG-18-17

• VA Design Alerts

• VHA Fire Protection Design Manual

• VHA National BIM/CAD Standards

• VHA Required Division 01 Specification Sections List

621-24-701 (2409) EHRM Infrastructure Upgrades – Tier 3 DC Mountain Home, TN

Architecture 6

• Physical Security and Resiliency Design Manual, June 2025 Revision

• Whole Building Commissioning Process Manual

• VA Sustainable Design Manuals

• VHA Directive 1061 – Prevention of Healthcare-Associated Legionella Disease and

Scald Injury from Potable Water Distribution Systems

• Seismic Design Requirements H-18-8

• VA Cultural Resource Management Procedures H-7545

• OIT Infrastructure Standard for Telecommunications Spaces v4.0 (01 July 2023)

• National Codes and Standards: (Most recent Editions) o NFPA o IBC o NEC o EPA o NSPC o OSHA