Attachment A - Spec 01 31 00.01 Project Management and Coordination.pdf

PDF 18 KB Posted

Attached to
Y1DA--580-324 | Replace/Construct Bldg 121 | Houston, TX Federal contract opportunity
Solicitation number
36C77625R0030_1
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This document is a specification section for Project Management and Coordination (Section 01 31 00.01) that outlines digital project management procedures for a construction project. The specification requires a web-based project management software package with comprehensive features, including compilation of project data, access control, document workflow planning, and tracking of various project communications such as RFIs, submittals, change orders, and meeting minutes. The software must support mobile devices, provide user licenses for the Owner, Architect, and consultants, and include eight hours of software training. At project completion, a digital archive must be provided in a readable format with locked data to prevent further changes. Recommended software platforms include Procore, Oracle Primavera Submittal Exchange, or equivalent web-based project management systems.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--580-324 | Replace/Construct Bldg 121 | Houston, TX, newest first.
File Type Posted
Amendment 0006 - Att.pdf PDF
Amendment 0006 - Att.pdf PDF
Amendment 0006 - Att 4 - Updated RFI Log 6-20-25.docx DOCX document
Amendment 0006 - Att. 1 - Mechanical Addendum.pdf PDF
Amendment 0006.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004 - Att. 6 - RFI 43 Bldg. 121 Floor Plan.pdf PDF
Amendment 0004 - Att. 4 - RFI 55 Contractor Map.png PNG image
Amendment 0004 - Att. 3 - RFI 53 Construction Fence Limit 121.png PNG image
Amendment 0004 - Att. 5 - RFI 48 11 41 00 Food Storage Equipment.docx DOCX document
Amendment 0004 - Att. 2 - Bldg. 121 Geotech Report.pdf PDF
Amendment 0004 - Att. 1 RFI Log.docx DOCX document
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
Amendment 0002.pdf PDF
Bldg. 121 Floor plan.pdf PDF
Site Visit Sign-in-sheet..pdf PDF
Site Visit Agenda.pdf PDF
Amendment 0001.pdf PDF
Attachment 13 - Drawings Technology.pdf PDF
Attachment 4 - Drawings Civil.pdf PDF
Attachment 11 - Drawings Mechanical.pdf PDF
Attachment 1 - Houston Bldg 121 - Specs - Vol 1.pdf PDF
Attachment 5 - Drawings Landscape.pdf PDF
Attachment 3 - Drawings General.pdf PDF
36C77625R0030_1.pdf PDF
Attachment 8 - Drawings Interior.pdf PDF
Attachment 7 - Drawings Architectural.pdf PDF
Attachment 2 - Houston Bldg 121 - Specs - Vol 2.pdf PDF
Attachment 15 - Wage Determination Harris County.pdf PDF
Attachment 6 - Drawings Structural.pdf PDF
Attachment 9 - Drawings Fire Suppression.pdf PDF
Attachment 16 - PPQ.docx DOCX document
Attachment 12 - Drawings Electrical.pdf PDF
Attachment 10 - Drawings Plumbing.pdf PDF
Attachment 14 - Limitations on Subcontracting - Construction.docx DOCX document
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number

Project Name Project Location

PROJECT MANAGEMENT AND COORDINATION

05-01-24

01 31 00.01 - 1

SECTION 01 31 00.01

PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative provision for coordinating construction operations on Project, including, but not limited to, the following:

1. Web-based Project management software package.

B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.

1.3 DEFINITIONS

A. BIM: Building Information Modeling.

B. RFI: Request for Information. Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.

1.4 DIGITAL PROJECT MANAGEMENT PROCEDURES

A. Web-Based Project Management Software Package: Provide, administer, and use web-based

Project management software package for purposes of hosting and managing Project communication and documentation until Final Completion.

1. Basis of Specification: Procore, Oracle Primavera Submittal Exchange or other equivalent web-based project management software.

2. Web-based Project management software includes, at a minimum, the following features:

a. Compilation of Project data, including Contractor, subcontractors, Architect, Architect's consultants, Owner, and other entities involved in Project. Include names of individuals and contact information.

b. Access control for each entity for each workflow process, to determine entity's digital rights to create, modify, view, and print documents.

c. Document workflow planning, allowing customization of workflow between project entities.

d. Creation, logging, tracking, and notification for Project communications required in other Specification Sections, including, but not limited to, RFIs, submittals, Minor

Changes in the Work, Construction Change Directives, and Change Orders.

e. Track status of each Project communication in real time, and log time and date when responses are provided.

Project Number

Project Name Project Location

PROJECT MANAGEMENT AND COORDINATION

05-01-24

01 31 00.01 - 2

f. Procedures for handling PDFs or similar file formats, allowing markups by each entity. Provide security features to lock markups against changes once submitted.

g. Processing and tracking of payment applications.

h. Processing and tracking of contract modifications.

i. Creating and distributing meeting minutes.

j. Document management for Drawings, Specifications, and coordination drawings, including revision control.

k. Management of construction progress photographs.

l. Mobile device compatibility, including smartphones and tablets.

3. Provide Project management software user licenses for use of Owner, Architect, and

Architect's consultants. Provide eight hours of software training for web-based Project software users.

4. At completion of Project, provide digital archive in format that is readable by common desktop software applications in format acceptable to Architect. Provide data in locked format to prevent further changes.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

- - - END - - -