This document summarizes an amendment to a federal solicitation for construction services. The amendment extends the closing date of solicitation 36C77623R0050 from August 1, 2023 to August 2, 2023 at 2:00 PM Eastern time. It provides additional project specifications and drawings. It also responds to several contractor questions regarding casework, medical equipment, light boxes, blast-resistant windows, contaminated soils, and disposal requirements. The solicitation is for the construction of a new Women's Health Clinic project located at the Manchester VA Medical Center. The Department of Veterans Affairs Technology Acquisition Center in Austin is the contracting agency.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C77623R0050 amendment 0005
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numb ers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE
ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF
AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF
SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, et c.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO
AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 608-317 36C776 Department of Veterans Affairs Program Contracting Activity Central 6100 Oak Tree Blvd, Suite 490 Independence OH 44131 36C776 Department of Veterans Affairs Program Contracting Activity Central 6100 Oak Tree Blvd, Suite 490 Independence OH 44131 To all Offerors/Bidders
36C77623R0050 06-14-2023
X x x August 8, 2023 at 2:00 PM ET See continuation page for details of amendment 0005
William Henkel Contracting Officer
CONTINUATION PAGE
The purpose of amendment 0005 to solicitation 36C77623R0050 is the following:
To extend the closing date of the solicitation from August 1, 2023 to August 8, 2023 at 2:00 PM Easter time.
To provide the following attachments to the existing drawings and specifications.
· Spec 1-13 Combined
· 6670-AQ201 EQUPMENT SCHEDULE -6670-AQ201 EQUPMENT SCHEDULE
· 6670-AS301 EXTERIOR ELEVATIONS-EXTERIOR ELEVATIONS
· 6670AS801 DOOR& WINDOW SCHEDULES mca-DOOR &WINDOW SCHEDULES
To provide the following responses to requests for information:
7/11/2023
Please specify if there are any fire smoke dampers that need to be controlled by the fire alarm system. Currently there is none shown on the drawings.
Yes, see the schedule on the mechanical drawings
7/11/2023
A specification for misc metals appears to be missing.
Spec section 05 50 00 Metal Fabrication has been added.
Please provide specification section 10 73 16.13 for post supported Canopy.
Spec section 10 73 16.13 Metal Canopies has been added.
A specification for spandrel panel.
Basis of Design added to drawing AS301.
Please provide Div 7 for Metal Panels.
Basis of Design added to drawing AS301.
Please provide Div 6 for Fiber-Cement Panels.
Basis of Design added to drawing AS301.
7/17/2023 Div 10 / 11:
1. Please clarify the abbreviations “VC”, “VV” & “CC” used to identify who is installing each piece of equipment in the equipment schedule on Drawing AQ201. We can’t find any reference in the docs for definition of the abbreviations. These designations are under a column labeled “Installed By”. In addition to understanding these abbreviations, please clarify if the intent of this column is to designate the responsibility for both furnishing and installing.
Drawing AQ201 has been revised to show VA Acquisition Codes (V= VA, C= GC) for provider and installer where “installed By” was labelled.
2. Please confirm the intent for Medical Equipment on this project. Will the contractor be responsible for the furnish and/or install (if supplied by owner) of the medical equipment scheduled on Drawing AQ201. If so, please also provide a Specification for the medical equipment.
See above.
3. Please provide an updated specification section for the Division 10 28 00 – Toilet Accessories, which reflects the scope scheduled on Drawing AQ201. The specification and the schedule on AQ201 do not align, in that there are items in the schedule that are not listed in the specification.
Revised AQ201 indicates VA provides all toilet accessories with GC to install.
Site/Civil:
Specification 31 20 00 1.6.B states that “No separate payment shall be made for rock excavation quantities shown.” Please indicate where the rock quantities to be included are shown.
In the Allowance Section (01 21 00), 3.3, it calls out “include quantity of 15 cubic yards of rock removal.”
7/19/2023
Casework CB011:
Casework assemblies for the Exam, Consultation and Procedure Rooms on drawing AS602 (1/AS602, 2/AS602 & 7/AS602) and AQ201 are labeled as “CB011”. There are two sections 12 32 00 “Manufactured Wood Casework” and 12 31 00 “Manufactured Metal Casework”. We can not find any further drawing notes or specification that indicates which of these two specification sections apply to the CB011 casework, i.e., is it metal or wood, or possibly another specification other than a Div 12 spec should apply. Please clarify which specification section should be used for casework CB011.
CB011 is the VA code for wood casework. (Section 12 31 00 Metal Casework has been removed from the specs.
The schedule on drawing AQ201 lists “CB012”. We can’t find any reference to casework CB012. Please clarify where casework CB012 is located.
See above.
Consistent with our previous questions on the abbreviations on the schedule on AQ201, please clarify if “CC” indicates the bidding CM is furnishing and/or installing the CB011/CB012 casework.
Drawing AQ201 has been revised to show VA Acquisition Codes (V= VA, C= GC) for provider and installer where “installed By” was labelled.
Light Box Assembly:
Please reference detail 11/AS701 Light Box detail. This entire assembly is labeled as “Deduct 2B”. Please clarify if all, or specific portions of this detail should be considered as part of Deduct 2B.
Please only fill in deductive alternatives that are in the cost schedule of the solicitation.
c. See drawing AQ201, Item #A0701 “Back-Lit Window Infill”. Please advise if this item is intended to represent the Light Box detail on drawing AS701.
Yes.
1. From several glass subcontractors:
0. Please provide Blast (PSI) number, and GSA TS01 Blast rating for the blast-resistant windows. There is no information to be found in the drawings or specifications. See Kawneer Selection Guide attached for the full blast-resistant window collection.
Per Physical Security Engineer: I am not allowed to provide those parameters. Although the VA allowed me to do that until a few years ago, a communication went out from the VA requiring that the contractor/vendor is to follow the requirements in the VA specifications and the PSRDM. Both of those documents require that the contractor/vendor apply to the VA to gain direct access to the FOUO blast parameters.
Spec section 08 56 53, paragraph 1.5.F.
PSRDM 2020, paragraph 6.1.2.
It is my recommendation that the window vendor or the vendor’s design agent apply for the information.
0. Do the blast-resistant windows require a large missile impact test? See above
1. From sitework subcontractor:
1. Please clarify the scope of work included under specification 31 20 00 Earthwork regarding disposal of unsuitable and excess soils.
“use disposal facility that can accept the materials in accordance with state and federal regulations”
1. The requirements of specification 31 20 00 Earthwork include:
0. Section 1.2.R that states the definition of contaminated soils: ”Soil that contains contaminates as defined and determined by the Resident Engineer or the Government’s testing agency.”
0. Section 3.5.C that states in part: “Segregate all excavated contaminated soil designated by the Resident Engineer”
0. Section 3.5.C that states in part: “Dispose of excavated contaminated material in accordance with State and Local requirements.”
1. The requirements of specification 01 74 19 include:
0. Section 1.4.A that defines a class III landfill as a “A landfill that accepts non-hazardous resources such as household, commercial and industrial waste resulting from construction, remodeling, repair and demolition operations.”
0. Section 1.4.E that defines disposal as “Acceptance of solid wastes at a legally operating facility for the purpose of land filling (includes Class III landfills and inert fills).”
0. Section 1.4.H that defines inert solids/waste to include “soil and concrete that does not contain hazardous waste or soluble pollutants at concentrations in excess of water-quality objectives established by a regional water board, and does not contain significant quantities of decomposable solid resources.”
1. Has the Resident Engineer or the Government’s testing agency defined and determined any contaminated soils? No contaminated soils have been identified
0. If the answer is yes, please provide the definition and determination developed by the Resident Engineer or the Government’s testing agency. This is necessary for the contractor to know the quantity and type of contaminated soil that must be included for disposal (in accordance with “State and Local requirements.”) in the proposal.
Please confirm that Specification 01 74 19 requires that all soil disposal must be at a Class III landfill. The definition of Class III landfill was provided however specification require a “disposal facility that can accept the materials in accordance with state and federal”. Disposal reports are required for project documentation
1. There was an Amendment posted today (July 13, 2023), with attachments 13 and 14, the SF-30 is identified as Amendment 0004. We also received Amendment 0004 on July 10, 2023 (Incorporating FAR 52.204-27.) Should the Amendment sent today be considered Amendment 0005?
All amendments are labeled properly on Sam.gov
End of Document See attached document: Specs 01-13 Combined.
See attached document: 6670-AQ201 EQUIPMENT SCHEDULE-6670-AQ201 EQUIPMENT SCHEDULE.
See attached document: 6670-AS301 EXTERIOR ELEVATIONS-EXTERIOR ELEVATIONS.
See attached document: 6670-AS801 DOOR _ WINDOW SCHEDULES mca-DOOR _ WINDOW SCHEDULES.