S06 Building 11 Brine Tank Project - Pre-Renovation Asbestos Survey Report -22 pages.pdf
PDF 3 MB Posted
- Solicitation number
- 36C26326B0007
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prepared for:
ANDERSON ENGINEERING
13605 1ST AVENUE NORTH
PLYMOUTH, MN
September 6, 2024
Asbestos Survey 636A6-22-104 Building 11 Replace Boiler Plant Brine Tank VA Central Iowa Health Care System Des Moines, Iowa
Landmark Environmental, LLC 9555 James Avenue South | Bloomington, MN 55431 | Phone: 952-295-9400 | www.landmarkenv.com
F:\PROJECTS\AND-Anderson Engineering\Des Moines Brine Tank 636A6-22-104\Asbestos Survey\Building 11 Brine Tank Project
- Pre-Renovation Asbestos Survey Report.docx
Asbestos Survey Report
636A6-22-104 Building 11 Replace Boiler Plant Brine Tank
VA Central Iowa Health Care System
Des Moines, Iowa
1.0 Executive Summary
2.0 Introduction
3.0 Sampling Methods and Analysis
4.0 Asbestos-Containing Material Assessment
5.0 Findings
6.0 Recommendations
Appendices
Appendix A Certificates
Appendix B Building Diagram with Sample Locations and Asbestos Laboratory Report
Appendix C Asbestos-Containing Materials Physical Assessment
F:\PROJECTS\AND-Anderson Engineering\Des Moines Brine Tank 636A6-22-104\Asbestos Survey\Building 11 Brine Tank Project
- Pre-Renovation Asbestos Survey Report.docx
1.0 Executive Summary
Landmark Environmental, LLC (Landmark) was retained by Anderson Engineering (Client) to conduct a pre-renovation asbestos survey (Survey) as part of a renovation project at the Veterans Affairs (VA) Central Iowa Health Care System, located in Des Moines, Iowa
(the Property). The Client intends to conduct a remodel project titled “636A6-22-104
Building 11 Replace Boiler Plant Brine Tank” (Project). Only locations and materials to be impacted during this Project were included in the Survey. The Survey was conducted on August 21, 2024.
A summary of the Survey results are as follows:
Landmark collected 13 bulk asbestos samples as part of the inspection. The contracted laboratory, EMSL Analytical, Inc. (EMSL) separated these 13 samples into 14 individual layer samples and all 14 individual layer samples were analyzed.
Based on the laboratory report, no suspect building materials were found to contain asbestos.
No building materials were assumed to contain asbestos during the Survey.
Electrical wiring and panels were not sampled. Landmark does not perform bulk sampling of electrical equipment unless it has been shut down and tagged by a licensed electrician.
Since the building and brine generation tank system was operating, a complete destructive survey could not be conducted. No attempt was made to locate materials inside walls, doors, tanks and other areas that would require destructive entry. The possibility exists that materials may be present in these locations. Materials observed, or suspected in these areas, are assumed to be ACM. The possibility exists that as these locations are opened up during renovation, suspect material will be found. If suspect materials are encountered during renovation, work should stop immediately and the materials should be sampled for asbestos content or assumed to contain asbestos and properly removed by a licensed asbestos abatement contractor.
This Survey identifies asbestos as they existed on the day of the survey at the Property.
Conditions may change over time.
This Survey should not be used as a bidding document. The ACM quantities provided are estimates and must be verified by the bidding contractors.
F:\PROJECTS\AND-Anderson Engineering\Des Moines Brine Tank 636A6-22-104\Asbestos Survey\Building 11 Brine Tank Project
- Pre-Renovation Asbestos Survey Report.docx
2.0 Introduction
Landmark completed this asbestos Survey report (Report) at the Property. The procedures used for this Survey and assessment comply with the EPA, Occupational
Safety and Health Administration (OSHA), Iowa Division of Labor (IDL), and Iowa
Department of Natural Resources (IDNR) asbestos standards.
2.1 Purpose
Landmark was retained by the Client to complete the Survey and Report for the purposes of understanding asbestos-containing material (ACM) and quantities of ACM at the Property for the upcoming Project.
2.2 Survey Approach
The Survey, consisting of identifying, sampling, assessing, and quantifying suspect ACM within the survey area, was conducted on August 21, 2024.
2.3 Assumptions, Limitations and Exceptions
The findings and recommendations in this Report are subject to the following assumptions, limitations, and/or exceptions:
• Since the building and brine generation tank system was operating, a complete destructive survey could not be conducted. No attempt was made to locate materials inside walls, doors, tanks, and other areas that would require destructive entry. The possibility exists that materials may be present in these locations. The possibility exists that as these locations are opened during renovation, suspect material will be found. If suspect materials are encountered during renovation, work should stop immediately and the materials should be sampled for asbestos content or assumed to contain asbestos and properly removed by a licensed asbestos abatement contractor.
• Electrical wiring and panels were not sampled. Landmark does not perform bulk sampling of electrical equipment unless it has been shut down and tagged by a licensed electrician.
• This Survey identifies materials as they existed on the day of the survey. Conditions may change over time.
F:\PROJECTS\AND-Anderson Engineering\Des Moines Brine Tank 636A6-22-104\Asbestos Survey\Building 11 Brine Tank Project
- Pre-Renovation Asbestos Survey Report.docx
2.4 Qualifications
The Survey was conducted by Mark Meier, an accredited asbestos building inspector with Landmark. A photocopy of the inspector’s IDL certification is included in Appendix A.
Asbestos sample analysis for this project was conducted by EMSL. EMSL is accredited by the National Voluntary Accreditation Program (NVLAP lab code 200019-0).
F:\PROJECTS\AND-Anderson Engineering\Des Moines Brine Tank 636A6-22-104\Asbestos Survey\Building 11 Brine Tank Project
- Pre-Renovation Asbestos Survey Report.docx
3.0 Sampling Methods and Analysis
3.1 Bulk Asbestos Sampling
Building diagrams were utilized to divide the Property building into functional spaces for the purposes of describing sampling locations. The building diagram with sample locations has been included in Appendix B.
Similar systems and materials were grouped into “homogeneous areas of building materials” (homogeneous materials). Homogeneous materials often exist in more than one functional space within the Property building. Each homogeneous material was assigned a discrete number; the homogeneous material number is indicated in the first number of the sample name. Multiple samples of each homogeneous material were taken in accordance with the EPA-Asbestos Hazard Emergency Response Act (AHERA) guidelines using a random sampling procedure. These multiple samples were designated “A, B, C,” etc. for each homogenous material, as indicated in the sample name. The sample locations and sample descriptions are shown on the building diagram and the asbestos laboratory report in Appendix B.
Samples were collected by carefully removing a small representative sample of the suspect material and sealing it in a plastic bag.
3.2 Bulk Asbestos Analysis
Landmark collected 13 bulk asbestos samples as part of the inspection. The contracted laboratory, EMSL separated these 13 samples into 14 individual layer samples and all 14 individual layer samples were analyzed. The results are presented in the attached laboratory report in Appendix B.
The bulk samples were analyzed by polarized light microscopy (PLM) with dispersion staining, EPA method 600/R-93/116 and EPA method 600/M4-82-020. Quantity determinations are made by visual estimation. For each homogeneous material, once a positive sample was identified, the remaining samples were not analyzed.
EPA National Emission Standards for Hazardous Air Pollutants (NESHAP)-Rule 40 CFR
Part 61 states that samples found to contain less than 10% asbestos by visual estimation may be further quantified by point count analysis.
The Asbestos rule states that all multi-layer systems, except for wall systems where joint compound was used only at the joints and nail holes, must be analyzed as separate materials. If any layer contains greater than one percent asbestos, that layer must be treated as asbestos-containing. This requires all layers in a multi-layered system to be
F:\PROJECTS\AND-Anderson Engineering\Des Moines Brine Tank 636A6-22-104\Asbestos Survey\Building 11 Brine Tank Project
- Pre-Renovation Asbestos Survey Report.docx treated as asbestos-containing if the layers cannot be separated without disturbing the asbestos-containing layer.
Asbestos samples will be held for 30 days after the date of this report.
3.3 Chain of Custody Procedures
To ensure that samples collected in the field are neither lost nor their identity mis-identified, all samples, from the point of collection to receipt in the laboratory, proceeds as follows. Each sample is first assigned a unique and distinct sampling number. After a sample is placed into a plastic bag, that unique number is assigned to that bag. This same number is documented on the laboratory’s chain of custody. The inspector signs each chain of custody before delivering to the lab. Upon receipt of the samples, the lab analyst verifies that each sample matches the corresponding chain of custody number and signs and dates the chain of custody. After analysis, the analyst generates a report that includes the sample results and the project chain of custody forms.
F:\PROJECTS\AND-Anderson Engineering\Des Moines Brine Tank 636A6-22-104\Asbestos Survey\Building 11 Brine Tank Project
- Pre-Renovation Asbestos Survey Report.docx
4.0 Asbestos-Containing Material Assessment
In each functional space, each homogeneous material was quantified and assessed for friability (i.e. material can be crumbled, pulverized, or reduced to powder by hand pressure when dry). Suspect ACM was then assessed as to their condition and potential for disturbance. This information was recorded on the asbestos physical assessment shown in Appendix C. The model for this system is described in the EPA Draft
Curriculum for Training Building Inspectors.
F:\PROJECTS\AND-Anderson Engineering\Des Moines Brine Tank 636A6-22-104\Asbestos Survey\Building 11 Brine Tank Project
- Pre-Renovation Asbestos Survey Report.docx
5.0 Findings
5.1 Summary of Asbestos-Containing Materials
Suspect homogeneous material found to contain asbestos and their sample numbers include:
Thermal Insulation – None Observed
Surfacing Material – None Observed
Miscellaneous Materials – None Observed
Assumed Materials – None Observed
5.2 Summary of Non-Asbestos-Containing Materials
Suspect ACM is considered negative for asbestos when all samples of the material are found to contain one percent or less asbestos. Suspect homogeneous material found to be negative includes:
1. Hard pipe fitting insulation on hard pipe insulation - small line (Sample 1).
2. Hard pipe insulation - small line (Sample 2).
3. Hard pipe insulation - large line (Sample 3).
4. Clay block mortar (Sample 4).
5. Black tar on wall (Sample 5).
6. White caulk (Sample 6).
F:\PROJECTS\AND-Anderson Engineering\Des Moines Brine Tank 636A6-22-104\Asbestos Survey\Building 11 Brine Tank Project
- Pre-Renovation Asbestos Survey Report.docx
6.0 Recommendations
Based on the Survey and assessment results, as well as the proposed future use of the
Property building, the following recommendations for each ACM are summarized below.
Description Total Estimated Recommendation
Thermal System Insulation None observed
Surfacing Material None observed
Miscellaneous Materials None observed
Assumed Materials None observed
Electrical wiring and panels were not sampled and were assumed to contain asbestos.
Landmark does not perform bulk sampling of electrical equipment unless it has been shut down and tagged by a licensed electrician.
Since the building and brine generation tank system was operating, a complete destructive survey could not be conducted. No attempt was made to locate materials inside walls, doors, tanks and other areas that would require destructive entry. The possibility exists that materials may be present in these locations. Materials observed, or suspected in these areas, are assumed to be ACM. The possibility exists that as these locations are opened up during renovation, suspect material will be found. If suspect materials are encountered during renovation, work should stop immediately and the materials should be sampled for asbestos content or assumed to contain asbestos and properly removed by a licensed asbestos abatement contractor.
F:\PROJECTS\AND-Anderson Engineering\Des Moines Brine Tank 636A6-22-104\Asbestos Survey\Building 11 Brine Tank Project
- Pre-Renovation Asbestos Survey Report.docx
7.0 Signatures of Environmental Professional(s)
We declare that, to the best of our professional knowledge and belief, the Survey referenced by this report, and the report itself, were conducted in accordance with intent of the EPA, IDNR, IDL, AHERA regulations to the best of my ability and knowledge.
Mark Meier
Asbestos Building Inspector (24-12078)
Eric Gabrielson
Vice President
Appendices
Appendix A
Appendix B
EMSL Analytical, Inc.
3410 Winnetka Avenue North New Hope, MN 55427
Tel/Fax: (763) 449-4922 / (763) 449-4924 http://www.EMSL.com / minneapolislab@emsl.com
352407997EMSL Order:
Customer ID: LMEN42
Customer PO:
Project ID:
Attention: Phone:Mark Meier (952) 666-2422
Fax:Landmark Environmental, LLC (952) 887-9605
Received Date:9555 James Avenue South – Suite 262 08/22/2024 3:40 PM
Analysis Date:Bloomington, MN 55431 08/28/2024 - 08/29/2024
Collected Date: 08/21/2024
Project: 23128.02/ DMVA Brine Tank
Test Report: Asbestos Analysis of Bulk Materials via AHERA Method 40CFR 763 Subpart E
Appendix E supplemented with EPA 600/R-93/116 using Polarized Light Microscopy
Sample Description Appearance % Fibrous % Non-Fibrous
Non-Asbestos Asbestos
% Type
1A
352407997-0001
None DetectedNon-fibrous (Other)80%Synthetic
Glass
10%
10%
Gray/Blue
Fibrous
Homogeneous
Hard fitting on Small
Line/ Rm 002
1B
352407997-0002
None DetectedNon-fibrous (Other)80%Synthetic
Glass
10%
10%
Gray/Blue
Fibrous
Homogeneous
Hard fitting on Small
Line/ Rm 002
1C
352407997-0003
None DetectedNon-fibrous (Other)80%Synthetic
Glass
10%
10%
Gray/Blue
Fibrous
Homogeneous
Hard fitting on Small
Line/ Rm 002
2A
352407997-0004
None DetectedNon-fibrous (Other)80%Synthetic
Glass
10%
10%
Blue
Fibrous
Homogeneous
Hard Pipe insulation on Small Line/002
2B
352407997-0005
None DetectedNon-fibrous (Other)80%Synthetic
Glass
10%
10%
Blue
Fibrous
Homogeneous
Hard Pipe insulation on Small Line/002
2C
352407997-0006
None DetectedNon-fibrous (Other)80%Synthetic
Glass
10%
10%
Blue
Fibrous
Homogeneous
Hard Pipe insulation on Small Line/002
3A
352407997-0007
None DetectedNon-fibrous (Other)80%Synthetic
Glass
10%
10%
Blue
Fibrous
Homogeneous
Hard pipe insulation on Larger Line/ 002
3B
352407997-0008
None DetectedNon-fibrous (Other)80%Synthetic
Glass
10%
10%
Blue
Fibrous
Homogeneous
Hard pipe insulation on Larger Line/ 002
3C
352407997-0009
None DetectedNon-fibrous (Other)80%Synthetic
Glass
10%
10%
Blue
Fibrous
Homogeneous
Hard pipe insulation on Larger Line/ 002
3D
352407997-0010
None DetectedNon-fibrous (Other)80%Synthetic
Glass
10%
10%
Blue
Fibrous
Homogeneous
Hard pipe insulation on Larger Line/ 002
4 Mortar
352407997-0011
None DetectedNon-fibrous (Other)100%Gray/Various/Black
Non-Fibrous
Homogeneous
Clay Block
Mortar/Rump Rm
4 Brown Material
352407997-0011A
None DetectedNon-fibrous (Other)100%Brown
Non-Fibrous
Homogeneous
Clay Block
Mortar/Rump Rm
352407997-0012
None DetectedNon-fibrous (Other)100%Black
Non-Fibrous
Homogeneous
Black Tar
Coating/Pump Rm
352407997-0013
None DetectedNon-fibrous (Other)100%Gray
Non-Fibrous
Homogeneous
White Caulk/ Exterior
Initial report from: 08/29/2024 10:44:10
Page 1 of 2ASB_PLM_0008_0002 - 2.31 Printed: 8/29/2024 9:44 AM
EMSL Analytical, Inc.
3410 Winnetka Avenue North New Hope, MN 55427
Tel/Fax: (763) 449-4922 / (763) 449-4924 http://www.EMSL.com / minneapolislab@emsl.com
352407997EMSL Order:
Customer ID: LMEN42
Customer PO:
Project ID:
Analyst(s)
Michael Craigmile (14) Rachel Travis, Laboratory Manager or Other Approved Signatory
EMSL maintains liability limited to cost of analysis . Interpretation and use of test results are the responsibility of the client. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations . The report reflects the samples as received.
Results are generated from the field sampling data (sampling volumes and areas, locations, etc.) provided by the client on the Chain of Custody. Samples are within quality control criteria and met method specifications unless otherwise noted. The above analyses were performed in general compliance with Appendix E to Subpart E of 40 CFR (previously EPA 600/M4-82-020 “Interim Method”) but augmented with procedures outlined in the 1993 (”final”) version of the method. This report must not be used by the client to claim product certification, approval, or endorsement by NVLAP, NIST or any agency of the federal government. Non- friable organically bound materials present a problem matrix and therefore EMSL recommends gravimetric reduction prior to analysis . Unless requested by the client, building materials manufactured with multiple layers (i.e. linoleum, wallboard, etc.) are reported as a single sample. Estimation of uncertainty is available on request.
Samples analyzed by EMSL Analytical, Inc. New Hope, MN NVLAP Lab Code 200019-0; Colorado AL-24478
Initial report from: 08/29/2024 10:44:10
Page 2 of 2ASB_PLM_0008_0002 - 2.31 Printed: 8/29/2024 9:44 AM
OrderID: 352407997
OrderID: 352407997
KEY
- Asbestos Sample LocationXX
3C
3B 3A2C 2B 2A1C 1B 1A
6 - exterior
Appendix C
9/6/2024 BUILDING 11 REPLACE BOILER PLANT BRINE TANK
VA CENTRAL IOWA HEALTH CARE SYSTEM, DES MOINES, IOWA
ASBESTOS-CONTAINING MATERIAL ASSESSMENT DATABASE
Floor Location Type Description Quantity
Height
(Feet) Condition
Disturbance
Potential
Homog.
Material
Bsmt Natural Gas Room No ACM Observed
Bsmt Pump Room No ACM Observed
Bsmt Room 002 No ACM Observed
Bsmt Brine Tanks No ACM Observed
Exterior Top of Brine
Tanks No ACM Observed
Type: TSI=Thermal System Insulation SURF=Surfacing Materials MISC=Misc.
Quantity: CF=Cubic Ft LF=Linear Ft SF=Square Ft Condition: G=Good F=Fair P=Poor Dist. Pot.: L=Low M=Medium H=High
File details come from the government source that posted it. Updated .