This document is an additional response to late questions/RFI/clarifications for Solicitation Number 36C26326B0007, Project Number 636A6-22-104 to Replace Boiler Plant Brine Tank. The document addresses two key contractor questions regarding the project's technical specifications.

The first question concerns fire sprinkler system installation, with the government providing detailed guidance on phasing, system connections, and installation requirements. Specifically, the new fire suppression system must be installed, tested, and activated in Phase 3, with the existing system remaining active throughout Phases 1-3, with a brief impairment during the cutover. The second question clarifies that no blast doors are required for the project, despite an initial suggestion in the statement of work. The response emphasizes that contractors must develop their own drawings and calculations based on the project specifications.

View the file

Other files

File Type Posted
S06 Additional Late Questions and Responses - 2 pages.pdf PDF
36C26326B0007 0007.docx DOCX document
36C26326B0007 0006.docx DOCX document
S06 Additional Late Question and Response -1 page.pdf PDF
36C26326B0007 0005.docx DOCX document
36C26326B0007 0004.docx DOCX document
S06 Atch F Wage Determination IA20260071 01.02.26 -6 pages.pdf PDF
S06 Additional Late Questions and Responses -3 pages.pdf PDF
36C26326B0007 0003.docx DOCX document
36C26326B0007 0002.docx DOCX document
36C26326B0007 0001.docx DOCX document
S06 Building 11 Brine Tank Project - Pre-Renovation Asbestos Survey Report -22 pages.pdf PDF
S06 Building 11 Brine Tank Project - Lead Survey Report - 7 pages.pdf PDF
S06 Questions and Responses - Solicitation 36C26326B0007 -3 pages.pdf PDF
S06 Pre-Bid Sign In Sheet 12.8.25 -1 page.pdf PDF
S06 Atch F Wage Determination IA20240071 12.12.25 -7 pages.pdf PDF
S06 Late Questions and Responses - Solicitation 36C26326B0007 -1 page.pdf PDF
S06 Pre-Bid Site Visit Agenda -2 pages.pdf PDF
S02 Atch A SOW - 4 pages.pdf PDF
S02 Atch D VAAR 852.219-75 Limitations on Subcontracting Certificate of Compliance - 2 pages.pdf PDF
S02 Atch B Drawings - 31 pages.pdf PDF
S02 Atch F Wage Determination IA20240071 11.21.25 -7 pages.pdf PDF
S02 Atch E Safety or Environmental Violations and EMR Information - 2 pages.pdf PDF
S02 Atch C Specifications - 608 pages.pdf PDF
36C26326B0007_1.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number: 36C26326B0007 Project Number: 636A6-22-104 Replace Boiler Plant Brine Tank

Additional Responses to Late Questions/RFI/Clarifications

Question: There is no way to isolate the existing fire sprinkler main and pipe in the areas of construction as it feeds other parts of the plants fire protection. It also states to run new piping next to the existing pipe but there is no room to do that with everything packed tight. I would recommend the pipe is replaced piece per piece in its current location so the systems can be drained and filled every day. How would you like me to proceed with quoting this work?

Answer: Please proceed following the requirements of paragraph 1.17.L of Specification 01 35 26 and Construction Phasing General Notes notes 5 and 6 on Sheet GC111 and Phasing note 3 on Sheet GC111, the fire suppression system within the limits of construction must be installed, tested, and activated prior to removing the existing system, all in Phase 3. As the new work is reliant upon connections to existing piping, it is anticipated the new work will be installed adjacent to the existing fire suppression system, the existing system will remain active throughout Phases 1, 2, and 3 with the exception of a brief impairment during Phase 3 to cut over the existing water supply piping to the new fire suppression system, and then the fire suppression system will remain active during Phase 4, 5, and 6. Do not consider “adjacent to” to mean “next to” and know that the new fire sprinkler system layout in the limits of construction is not limited to the layout indicated in detail 2 on sheet FX101. The contractor’s drawings and calculations, items 1.4.A.2 and 1.4.A.4 of Specification 21 13 13, must be developed based on the contractor’s design in accordance with paragraphs 1.1.A and 1.3.A of Specification 21 13 13.

Question: Could you clarify if the door needs to be a blast door? The specification doesn’t mention anything about the door to be blast door but the statement of work on page 1 suggests being.

Answer: No blast doors are required.