Replace Roof and Install Lightning Protection, Project No. 605-20-411
Solicitation number
36C26224B0001_1
Issued by

About this file

This Invitation for Bid solicits construction services to replace an aging roof and install lightning protection at the Veterans Affairs Loma Linda Medical Center in Loma Linda, California. The contractor will furnish all labor, equipment, materials, and supervision necessary to remove the existing PVC roofing system and install a new TPO roofing system. Additional work includes preparation and performance of submittals, change orders, site visits, meetings, construction meeting minutes, staff interviews, phasing and scheduling, utility shutdowns, and infection control measures. The contractor must perform all work in accordance with the general specifications, statement of work, design, schedule, and other supporting documents provided. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 22 is the contracting agency.

View the file

Other files

File Type Posted
Award Notice_36C26224C0134.pdf PDF
Amendment 0003_Attachment M. RFI Attachment for Question 61 (Temp AC Unit).pdf PDF
Amendment 0003_Attachment AE. 100P DESIGN FOR CONSTRUCTION- 2012.05.16.pdf PDF
Amendment 0003_Attachment O. RFI Attachment for Question 62 (Cell Site 2).pdf PDF
Amendment 0003_Attachment AF. RFI Attachment for Question 58 (Abandoned Post).pdf PDF
Amendment 0003_Attachment L. RFI Attachment for Question 60 (Antenna Structure).pdf PDF
Amendment 0003_Attachment Q. RFI Attachment for Question 65 (Sat Dish 2).pdf PDF
Amendment 0003_Attachment I. RFI Responses.pdf PDF
Amendment 0003_Attachment AA. RFI Attachment for Question 113 (Retactable Skylight 1).pdf PDF
Amendment 0003_Attachment AB. RFI Attachment for Question 113 (Retractable Skylight 2).pdf PDF
Amendment 0003_Attachment S. RFI Attachment for Question 66 (Expansion Joint 2).pdf PDF
Amendment 0003_Attachment N. RFI Attachment for Question 62 (Cell Site 1).pdf PDF
Amendment 0003_Attachment V. RFI Attachment for Question 83 (PH Rooftop Equipment 1).pdf PDF
Amendment 0003_Attachment U. RFI Attachment for Question 82 (Mech Equipment 2).pdf PDF
Amendment 0003_Attachment J. RFI Attachment for Questions 49-51.pdf PDF
Amendment 0003_Attachment AC. RFI Attachment for Question 113 (Retactable Skylight 3).pdf PDF
Solicitation Amendment 0003 (SF30)_36C26224B0001 0003.pdf PDF
Amendment 0003_Attachment P. RFI Attachment for Question 64 (Sat Dishes).pdf PDF
Amendment 0003_Attachment X. RFI Attachment for Question 59 (Old Chiller Unit at Grid K3).pdf PDF
Amendment 0003_Attachment AD. 100P DESIGN FOR CONSTRUCTION- CUT SHEETS - 2012.05.10.pdf PDF
Amendment 0003_Attachment R. RFI Attachment for Question 66 (Expansion Joint 1).pdf PDF
Amendment 0003_Attachment T. RFI Attachment for Question 82 (Mech Equipment 1).pdf PDF
Amendment 0003_Attachment Z. RFI Attachment for Question 114 (CLC Lower Roof).pdf PDF
Amendment 0003_Attachment W. RFI Attachment for Question 83 (PH Rooftop Equipment 2).pdf PDF
Solicitation Amendment 0002 (SF30)_36C26224B0001 0002.pdf PDF
Amendment 0002_Attachment H. Site Visit Sign-In Sheet_02.02.2024.pdf PDF
Amendment 0001_Attachment G. Electrical Drawings.pdf PDF
Solicitation Amendment 0001 (SF30)_36C26224B0001 0001.pdf PDF
Attachment A - Statement of Work_Roof Replacement and Lightning Protection.pdf PDF
Solicitation (SF1442)_36C26224B0001.pdf PDF
Attachment E - Davis-Bacon Wage Determination - GDN CA20240026_01.12.2024.pdf PDF
Attachment C - Arch Drawings.pdf PDF
Attachment D - Gen Drawings.pdf PDF
Attachment F - Site Visit Information.pdf PDF
Attachment B - Project Specifications_Roof Replacement and Lightning Protection_Revised.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Loma Linda VAMC June 2, 2022 Roof Replacement and Lightning Protection 35% Schematic Design Loma Linda, CA 92357 Project No: 605-20-411

05-01-22

00 01 10-6

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 12 FURNISHINGS

12 22 16 Drapery Track and Accessories 01-21 12 24 00 Window Shades 08-17 12 24 21 Lightproof Shades 01-21 12 31 00 Manufactured Metal Casework 01-21 12 32 00 Manufactured Wood Casework 01-21 12 34 00 Manufactured Plastic Casework 01-21 12 35 70.21 Medication Cabinet 01-21 12 36 00 Countertops 12-18 12 56 70.11 Suspended Table 01-21

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural

Components 01-21

13 17 23 Therapeutic Pools 01-21 13 17 23.11 Therapeutic Pool Accessories 01-21 13 19 13 Kennel Enclosures and Gates 01-21 13 21 29 Constant Temperature Rooms 01-21 13 21 49 Audiology Booth 01-21 13 34 19 Metal Building Systems 01-21 13 49 00 Radiation Protection 01-21

DIVISION 14 CONVEYING EQUIPEMENT

14 12 11 Traction and Winding Drum Dumbwaiter 11-20 14 21 00 New Traction Elevator 08-20 14 21 10 Modernization of Traction Elevator 08-20 14 21 11 Traction Cartlift 03-20 14 24 00 New Hydraulic Elevator 08-20 14 24 10 Modernization of Hydraulic Elevator 08-20 14 24 11 Hydraulic Cartlift 03-20 14 24 24 Renovation Hydraulic Elevator (Custom Written by VACO) 14 26 26 Renovation Traction Elevator (Custom Written by VACO) 14 91 33 Gravity Soiled Linen Chutes 08-20 14 91 82 Gravity Trash Chutes 03-20

DIVISION 21- FIRE SUPPRESSION N/A

21 08 00 Commissioning of Fire Suppression System 11-16 21 08 00.01 DVA/USACE Projects Commissioning of Fire Suppression

Systems 08-19

21 12 00 Manual Dry Standpipe Systems 06-15 21 13 13 Wet-Pipe Sprinkler Systems 06-15 21 13 16 Dry-Pipe Sprinkler Systems 01-15 21-22-00 Clean Agent Fire Suppression Systems 05-15 21-30-13 Electric-Driven, Fire Pumps 05-15 21-30-16 Diesel-Driven, Fire Pumps 05-15

Loma Linda, CA 92357 Project No: 605-20-411

05-01-22

00 01 10-7

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 22 PLUMBING

22 05 11 Common Work Results for Plumbing 09-20 22 05 12 General Motor Requirements for Plumbing Equipment 09-20 22 05 19 Meters and Gages for Plumbing Piping 09-20 22 05 23 General-Duty Valves for Plumbing Piping 09-20 22 05 33 Heat Tracing for Plumbing Piping 09-20 22 07 11 Plumbing Insulation 09-19 22 08 00 Commissioning of Plumbing Systems 11-16 22 08 00.01 DVA/USACE Projects Commissioning of Plumbing Systems 08-19 22 11 00 Facility Water Distribution 05-21 22 11 23 Domestic Water Pumps 09-15 22 12 16 Facility Elevated, Potable-Water Storage Tanks 09-15 22 13 00 Facility Sanitary and Vent Piping 09-20 22 13 23 Sanitary Waste Interceptors 09-20 22 13 29 Sanitary Sewerage Pumps 09-20 22 13 29.13 Wet-Pit Mounted, Vertical Sewerage Pumps 09-20 22 13 33 Packaged, Submersible Sewerage Pump Units 09-20 22 14 00 Facility Storm Drainage 09-15 22 14 29 Sump Pumps 09-15 22 14 33 Packaged, Pedestal Drainage Pump Units 09-15 22 14 36 Packaged, Submersible, Drainage Pump Units 09-15 22 15 00 General Service Compressed-Air Systems 09-20 22 31 11 Water Softeners 09-15 22 33 00 Electric Domestic Water Heaters 09-20 22 34 00 Fuel-Fired Domestic Water Heaters 09-20 22 35 00 Domestic Water Heat Exchangers 09-20 22 40 00 Plumbing Fixtures 09-15 22 42 26 Commercial Disposers 09-15 22 61 13.74 Dental Compressed-Air Piping 09-20 22 61 19.74 Dental Compressed-Air Equipment 09-20 22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15 22 62 19.74 Dental Vacuum and Evacuation Equipment 09-15 22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15 22 66 00 Chemical-Waste Systems for Laboratory and Healthcare

Facilities 09-20

22 67 19.16 Reverse-Osmosis Water Equipment 09-15 22 67 21 Water Dealkalizing System 09-15

DIVISION 23 HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 10 Common Work Results for Boiler Plant and Steam

Generation 04-20

23 05 11 Common Work Results for HVAC 04-22 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 02-20

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment

02-20

23 05 51 Noise and Vibration Control for Boiler Plant 03-22 23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20

Loma Linda, CA 92357 Project No: 605-20-411

05-01-22

00 01 10-8

SECTION NO. DIVISION AND SECTION TITLES DATE

23 05 93.01 DVA/USACE Projects Testing, Adjusting, and Balancing for HVAC

11-21

23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 04-22 23 08 00.01 DVA/USACE Projects Commissioning of HVAC Systems 08-19 23 08 11 Demonstrations and Tests for Boiler Plant 04-20 23 09 11 Instrumentation and Control for Boiler Plant 03-22 23 09 23 Direct-Digital Control System for HVAC 09-11 23 10 00 Facility Fuel Systems 04-20 23 11 23 Facility Natural-Gas Piping 04-20 23 21 11 Boiler Plant Piping Systems 09-21 23 21 13 Hydronic Piping 02-20 23 21 23 Hydronic Pumps 02-20 23 22 13 Steam and Condensate Heating Piping 02-20 23 22 23 Steam Condensate Pumps 04-20 23 23 00 Refrigerant Piping 02-20 23 25 00 HVAC Water Treatment 02-20 23 31 00 HVAC Ducts and Casings 02-20 23 34 00 HVAC Fans 02-20 23 36 00 Air Terminal Units 02-20 23 37 00 Air Outlets and Inlets 02-20 23 38 13 Commercial-Kitchen Hoods 02-20 23 40 00 HVAC Air Cleaning Devices 03-20 23 50 11 Boiler Plant Mechanical Equipment 03-22 23 51 00 Breechings, Chimneys, and Stacks 04-20 23 52 25 Low-Pressure Water Heating Boilers 11-21 23 52 28 Low-Pressure Steam Boilers 11-21 23 52 33 Water Tube Boilers 03-22 23 52 39 Fire Tube Boilers 03-22 23 56 00 Solar Energy Heating System 03-20 23 57 33 Geothermal Energy Direct Use (Heating Applications) 03-20 23 64 00 Packaged Water Chillers 03-20 23 65 00 Cooling Towers 03-20 23 72 00 Air-to-Air Energy Recovery Equipment 03-20 23 73 00 Indoor Central-Station Air-Handling Units 03-20 23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 03-20 23 81 00 Decentralized Unitary HVAC Equipment 03-20 23 81 23 Computer-Room Air-Conditioners 03-20 23 81 43 Air-Source Unitary Heat Pumps 03-20 23 81 46 Water-Source Unitary Heat Pumps 03-20 23 81 49 Ground-Source Heat Pump 03-20 23 82 00 Convection Heating and Cooling Units 03-20 23 82 16 Air Coils 03-20 23 84 00 Humidity Control Equipment 03-20

DIVISION 25 INTEGRATED AUTOMATION

25 10 10 Advanced Utility Metering System 02-10

Loma Linda, CA 92357 Project No: 605-20-411

05-01-22

00 01 10-9

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 26 ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 13 Medium-Voltage Cables 01-17 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 36 Wireways for Radiology Equipment 01-18 26 05 39 Underfloor Raceways for Electrical Systems 01-18 26 05 41 Underground Electrical Construction 01-17 26 05 73 Overcurrent Protective Device Coordination Study 01-18 26 08 00 Commissioning of Electrical Systems 11-16 26 08 00.01 DVA/USACE Projects Commissioning of Electrical Systems 08-19 26 09 23 Lighting Controls 01-18 26 11 16 Secondary Unit Substations 01-18 26 12 19 Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers 01-18 26 13 13 Medium-Voltage Circuit Breaker Switchgear 01-17 26 13 16 Medium-Voltage Fusible Interrupter Switches 01-17 26 20 11 Isolated Power Systems 01-18 26 22 00 Low-Voltage Transformers 01-18 26 23 00 Low-Voltage Switchgear 01-17 26 23 13 Generator Paralleling Controls 01-17 26 24 13 Distribution Switchboards 01-18 26 24 16 Panelboards 01-18 26 24 19 Motor Control Centers 01-18 26 25 11 Busways 01-17 26 26 00 Power Distribution Units for Static Uninterruptible

Power Systems 01-18

26 27 26 Wiring Devices 01-18 26 29 11 Motor Controllers 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 32 13 Engine Generators 01-18 26 33 53 Static Uninterruptible Power Supply 01-17 26 35 26 Harmonic Filters 01-18 26 36 23 Automatic Transfer Switches 01-17 26 41 00 Facility Lightning Protection 01-17 26 42 00 Cathodic Protection 01-17 26 43 13 Surge Protective Devices 01-17 26 51 00 Interior Lighting 01-18 26 55 71 Medical and Surgical Lighting Fixtures 01-18 26 56 00 Exterior Lighting 01-18

DIVISION 27 COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19 27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Raceways and Boxes for Communications Systems 10-18 27 05 61 Leased Space, Communication Equipment and Systems 06-15 27 08 00 Commissioning of Communications Systems 11-16

Loma Linda, CA 92357 Project No: 605-20-411

05-01-22

00 01 10-10

SECTION NO. DIVISION AND SECTION TITLES DATE

27 08 00.01 DVA/USACE Projects Commissioning of Communications Systems

08-19

27 10 00 Control, Communication and Signal Wiring 06-15 27 11 00 Communications Equipment Room Fittings 06-15 27 15 00 Communications Structured Cabling 01-16 27 31 00 Voice Communications Switching and Routing Equipment 06-15 27 31 31 Voice Communications Switching and Routing Equipment -

Extension 06-15

27 32 41 Two-Way Radio Equipment and Systems 10-18 27 41 31 Master Antenna Television Equipment and Systems 06-15 27 51 16 Public Address and Mass Notification Systems 10-18 27 51 23 Intercommunications and Program Systems 06-15 27 52 23 Nurse Call and Code Blue Systems 10-18 27 52 41 Miscellaneous Medical Systems 06-15 27 53 19 Distributed Radio Antenna (Within Building) Equipment and System 10-18

DIVISION 28 ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and

Security 10-18

28 05 26 Grounding and Bonding for Electronic Safety and Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16 28 08 00.01 DVA/USACE Projects Commissioning of Electronic Safety and Security Systems 08-19

28 13 00 Physical Access Control System 10-11 28 13 16 Physical Access Control System and Database Management 09-11 28 13 53 Security Access Detection 09-11 28 16 00 Intrusion Detection System 10-11 28 23 00 Video Surveillance 09-11 28 26 00 Electronic Personal Protection System 09-11 28 31 00 Fire Detection and Alarm 10-11 28 52 31 Emergency Call System 06-15

DIVISION 31 EARTHWORK

31 20 00 Earthwork 07-16 31 20 11 Earthwork (Short Form) 10-12 31 23 19 Dewatering 10-12 31 23 23.33 Flowable Fill 10-12 31 32 23 Pressure Grouting Soil Stabilization 10-12 31 62 00 Driven Piles 10-12 31 63 16 Auger Cast Grout Piles 10-12 31 63 26 Drilled Caissons 10-12

Loma Linda, CA 92357 Project No: 605-20-411

05-01-22

00 01 10-11

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 32 EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16 32 12 16 Asphalt Paving 09-15 32 14 16 Brick Unit Paving 08-16 32 17 23 Pavement Markings 08-16 32 31 13 Chain Link Fences and Gates 06-18 32 31 40 High Security Fences and Gates 08-16 32 84 00 Planting Irrigation 08-16 32 90 00 Planting 08-16

DIVISION 33 UTILITIES

33 08 00 Commissioning of Site Utility Systems 11-16 33 08 00.01 DVA/USACE Projects Commissioning of Site Utility

Systems 08-19

33 10 00 Water Utilities 03-17 33 30 00 Sanitary Sewer Utilities 06-13 33 40 00 Storm Sewer Utilities 12-17 33 46 13 Foundation Drainage 10-11 33 51 00 Natural-Gas Distribution 10-11 33 63 00 Steam Energy Distribution 09-17

DIVISION 34 TRANSPORTATION

34 71 13 Passive Vehicle Barriers 04-18 34 75 13.13 Active Vehicle Barriers 08-16

DIVISION 48 Electrical Power Generation

48 14 00 Solar Energy Electrical Power Generation System 10-17 48 15 00 Wind Energy Electrical Power Generation System 10-17 48 16 23 Geothermal Energy Electrical Power Generation System 10-17

---END---

Loma Linda, CA 92357 Project No: 605-20-411

05-01-22

00 01 10-12

-INTENTIONALLY BLANK-

Appendix E

Roof Analysis Report