About this file

This is a Statement of Work (SOW) for Design-Build services to install parking shades and reconfigure parking lots at the VA Medical Center in Las Vegas, Nevada (Project 593-26-306).

The project addresses two primary challenges at the VA Southern Nevada Healthcare System campus: unsafe pedestrian conditions with inadequate separation between vehicles and pedestrians, and extreme heat exposure in the desert climate exceeding 100°F. The Design-Build contractor must furnish all architectural and engineering (AE) design services, construction labor, materials, and supervision. The scope includes designing shade canopies with 12-foot minimum clearance, 27-foot maximum width per section, 5-degree roof slope for drainage, and cantilevered perimeter systems where feasible to minimize impacts to loop roads and utilities. The project encompasses four parking lots (A, D, E, and F) totaling 948 uncovered stalls targeted for shade coverage. Deliverables include design submittals at 35%, 65%, 95%, and 100% completion; a Basis-of-Design Report; geotechnical and utility survey reports; structural calculations; drainage analysis; and a comprehensive Parking Lot Reconfiguration Plan addressing pedestrian safety with striped walkways, speed bumps at drive inlets, LED Rectangular Rapid Flashing Beacon signage, and Loop Road crossings. Design must comply with VA Design Guides, International Building Codes, NFPA, OSHA, ADA, and ABAAS standards.

The project follows a parallel design-and-construction schedule with a total period of performance of 550 calendar days from issuance of the initial Design Notice to Proceed. Design and preconstruction to 65% must complete within 120 days, with a separate Construction NTP issued after 65% design acceptance, targeting 320-340 calendar days for construction. Final design completion is due 210 days from Design NTP, followed by 45 days for closeout including as-builts, operations and maintenance manuals, and warranties. The contractor must develop a Parking Lot Closure and Traffic Management Plan to maintain facility access throughout construction and prioritize implementation in three phases: protected pedestrian walkways and Loop Road crossings first, interior lot shade canopy coverage second, and parking stall infill third, with infill and additional lots identified as deduct alternates. Cost estimates must be broken out by individual parking lot and follow VA estimating standards. RFI responses, submittal reviews, and shop drawing reviews require 14 calendar days each from AE and VA, with expedited responses if schedule impacts occur. All work occurs during normal business hours (8:00 AM–4:30 PM, Monday–Friday, excluding federal holidays), coordinated through the Contracting Officer's Representative. Contractor personnel require Non-PIV Card clearance with a 30-45 day processing timeline, and all personnel must comply with VA Directive 0735 and HSPD-12 security requirements.

View the file

Other files

File Type Posted
RFP AMENDMENT 36C26126R0055 0003.docx DOCX document
ATTACHMENT A - PHASE 1 FACTOR 2 - EXPERIENCE-SPECIAL EXPERIENCE 10-5-2026.xlsx XLSX spreadsheet
Instruction to Offerors DESIGN BUILD 10-5-2026.docx DOCX document
Commercial Construction Clause 52.212-4 10-5-2026.docx DOCX document
RFP AMENDMENT 36C26126R0055 0002.docx DOCX document
RFP AMENDMENT 36C26126R0055 0001.docx DOCX document
Site Visit Attendee List 09-17-2026.pdf PDF
RFP Amendment_36C26126R0055 0001.docx DOCX document
Attachment Specifications 08-17-2026.pdf PDF
Attachment Assignment 21 - Draft Schematic Design and Report.pdf PDF
DB-ATTACH ATTACHMENT I - RELEASE OF CLAIMS.docx DOCX document
Attachment Assignment 44 - Parking Study.pdf PDF
Attachment ED Parking Expansion.pdf PDF
Attachment Pre-solicitation Site Visit Presentation.pptx PPTX presentation
RFP 36C26126R0055_2 FINAL.docx DOCX document
Attachment Existing Carport Design.pdf PDF
Attachment Price Breakdown Form.xlsx XLSX spreadsheet
Attachment VAAR 852.219-75 JAN 2023 DEVIATION.pdf PDF
Attachment REQUEST FOR INFORMATION FORM.docx DOCX document
ATTACHMENT A - PHASE 1 FACTOR 2 - EXPERIENCE-SPECIAL EXPERIENCE SAMPLE.xlsx XLSX spreadsheet
Attachment Assignment 44 - BOD Conceptual Design for Carports.pdf PDF
Attachment Wage Determination NV20260091 07-30-2026.pdf PDF
ATTACHMENT B - PHASE 1 FACTOR 3 - Past Performance Questionnaire.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

For Design-Build Services

Install Parking Shades & Parking Lot Reconfiguration

Project 593-26-306

VA Southern Nevada Healthcare System (VASNHS) VA Medical Center (VAMC) Las Vegas, NV

6900 Pecos Road, N. Las Vegas, NV 89086

1.0. PROJECT SUMMARY & INTENT

1.1. The VA Southern Nevada Healthcare System (VASNHS) campus in North Las

Vegas experiences two critical challenges impacting patient/staff safety and comfort:

1.1.1. Unsafe Pedestrian Conditions: Existing parking lots require pedestrians to navigate active drive aisles and cross the Loop Road without adequate protection. Current layouts lack sufficient dedicated walking paths, traffic-calming measures, and high-visibility crossings, creating conflict points between vehicles and pedestrians. These conditions increase the risk of accidents and impede ADA accessibility for Veterans and visitors with mobility limitations.

1.1.2. Exposure to Extreme Heat: The campus is located in a desert climate where summer temperatures routinely exceed 100°F. Veterans and staff walking from vehicles to the facility face prolonged sun exposure, elevating the risk of heat exhaustion and heat stroke, particularly for elderly and medically vulnerable populations.

1.2. This Design-Build (DB) project will deliver a comprehensive solution by using parking lot improvement documents (see Section 10.0 Reference Material) as basis of design to reduce vehicle-pedestrian conflicts, enhance accessibility, and protect Veterans and staff from extreme heat, supporting VA’s mission to provide a safe, accessible, and comfortable healthcare environment.

1.2.1. The Design Build (DB) contractor shall furnish:

1.2.1.1. Design: All design Architect and Engineering (AE) services, materials, supplies, equipment, investigations and project supervision, and construction period services associated with this contract. Design shall meet Veteran’s Affair (VA) Design

Guides and Design Criteria and VA Master Specifications at the Technical Information Library (TIL) (www.cfm.va.gov/TIL), including providing parking that meets VA parking requirements, physical security design-guide requirements, and access requirements per VA Design guide. Design shall follow all current applicable codes, including, but not limited to, International Building Codes (IBC), National Fire Protection

Association (NFPA), and Occupational Safety and Health

Administration (OSHA).

1.2.2. Construction: All labor, materials, supervision, and administration for the complete construction of the project.

1.2.3. The Design Build Contractor shall consider the site in its entirety and develop designs for parking shade canopies and reconfiguration of lots to include pedestrian walkways that fit within the site constraints.

2.0. SCOPE

The AE/DB team shall design and construct shade canopies and associated parking lot improvements as follows, in accordance with VA Design Guides, Design Criteria, and VA Master

Specifications found in the TIL:

2.1. General Basis-Of-Design

The following information shall be verified by DB AE via provided as-builts and site investigation. Intent of information will be to provide canopy appearance, proportions, and detailing that is compatible with the existing campus canopy aesthetic as described in Assignment 44 – Conceptual Design for Carports and

593-14R-200 – Existing Carport Design. New canopies shall be engineered for shade-only (wind/gravity) loading; structural members shall be optimized accordingly and shall not replicate the heavier member sizing associated with photovoltaic loading in the reference documents. Exact replication of the existing canopy system is not required; designs that achieve visual compatibility while meeting shade-only structural and VA aesthetic requirements are acceptable.

2.1.1. Minimum clearance: 12 ft under all canopies.

www.cfm.va.gov/TIL

2.1.2. Max canopy width: 27 ft per section; interior modules approx. 40 ft long;

perimeter stalls, see 2.1.7

2.1.3. Roof slope: 5° toward south for drainage.

2.1.4. Stall dimensions: 18 ft × 9 ft typical; maintain VA standard geometry and

24 ft two-way aisles.

2.1.5. Lightning Protection: Ensure new shade canopies have lightning protection designed for implementation in construction.

2.1.6. Perimeter stalls: Use cantilevered systems with footings on one side (as opposed to centered like existing carports) to minimize impacts to loop roads and utilities; Where the DB AE determines that a cantilevered system is not achievable due to site, utility, or structural constraints, the

AE shall document the basis for that determination in the applicable design submittal and propose an alternative for VA review and approval prior to proceeding.

2.1.7. Parking Lot Reconfiguration – Infill & Pedestrian Safety:

Use Assignment 21 – Draft Schematic Design and Report, Assignment 44

– Parking Study, and ED Parking Expansion for basis-of-design. For lots that do not have detailed drawings associated, apply the same basis-of-design details for implementation into those lots.

2.1.7.1. Incorporate protected pedestrian paths, speed tables, and/or crosswalks where canopy installation affects walkways.

VA Request: In lieu of speed tables in parking lots, implement striped pedestrian paths with speed bumps at drive inlets in all lots. Where site geometry, drainage, or utility conflicts preclude implementation at a specific location, the DB AE shall document the basis for the exception in the applicable design submittal and propose an alternative treatment for VA review and approval prior to proceeding. See figure below for example:

Figure 1: (Left) Shown in Assignment 21 Report; (Right) Design Intent Described in 2.1.8.2.

2.1.7.2. Implement targeted infill in landscape islands, between-lot areas, and the ED parking lot, preserving stall/aisle standards, slopes, and positive drainage. Where a specific island or area cannot accommodate infill due to drainage, utility, structural, or geometric constraints, the DB AE shall document the basis for the exception in the applicable design submittal and identify the area as a deduct alternate or note it as infeasible with VA approval prior to proceeding.

2.1.7.3. Infill and parking stall additions should include shaded canopies.

2.1.7.4. Assess the flagpole roundabout on the northeast side of campus

(between Lots A and B) for pedestrian and vehicular conflict points. Based on assessment findings, provide design recommendations and construction documents to: (1) discourage uncontrolled pedestrian passage through the roundabout via signage, delineators, or hardscape measures; and (2) improve vehicular circulation and traffic flow clarity through striping, signage, or minor geometric adjustments. Major reconstruction of the roundabout is not anticipated. The DB AE shall present findings and proposed improvements at the 35% design workshop for VA review and approval prior to advancing the design.

2.1.7.5. Ensure compliance with PG-18-10, ADA, ABAAS, and FHWA

RRFB signage standards.

2.2. Parking Lots and Coverage Targets

AE shall verify counts and layout during design survey(s):

2.2.1. Lot A: 127 uncovered stalls (84 perimeter, 43 interior).

2.2.2. Lot D: 466 uncovered stalls (117 perimeter, 349 interior).

2.2.3. Lot E: 177 uncovered stalls (101 perimeter, 76 interior).

2.2.4. Lot F: 178 uncovered stalls (63 perimeter, 115 interior).

2.3. Structural and Site Considerations

2.3.1. Design foundations and structural systems per local wind/seismic codes and VA standards; consider geotechnical recommendations for pier embedment and uplift resistance.

2.3.2. Preserve existing drainage patterns; maintain positive flow and avoid ponding per VA TIL Parking Design Manual & Demand Model; integrate gutter/downspout systems as needed.

2.3.3. Perform utility conflict analysis (i.e. ground-penetrating radar, SUE Level

A/B + potholing, etc.) before footing design.

2.3.4. Use corrosion-resistant finishes and match campus color palette.

2.3.5. Accessibility and Pedestrian Safety

2.3.5.1. Provide 6 ft minimum width for secondary walkways.

2.3.5.2. Install striped crosswalks, speed tables, and LED RRFB signage at crossings per FHWA and VA guidelines.

2.3.5.3. Ensure lighting for nighttime pedestrian activity along new paths.

2.3.5.4. Include striped crossings with speed bump protection across

Loop Road on west side of campus, connecting the outer parking lots A & F to the outer loop ring (see Assignment 21 – Draft

Schematic Design and Report, pg. 12-16 for more information)

2.3.5.4.1. Apply lighting requirements for pedestrian

crossings as established in Assignment 21 – Draft

Schematic Design and Report (General Note 4) to all new crossings across the Loop Road.

2.4. Deliverables and AE Responsibilities

2.4.1. Design Submittals: 35%, 65%, 95%, 100% drawings/specifications.

2.4.2. Basis-of-Design Report: Document canopy system selection and deviations from existing details.

2.4.3. Technical Reports: Geotechnical, structural calculations, drainage analysis, utility survey, parking lot reconfiguration plan.

2.4.3.1. Parking Lot Reconfiguration Plan: The DB contractor shall develop a Parking Lot Reconfiguration Plan as part of the 35% design submittal, updated at each subsequent design milestone, and substantially complete and approved by VA no later than

65% design acceptance. The plan shall be approved by VA prior to issuance of the early Construction Notice to Proceed (NTP) and shall, at minimum, detail the following:

• Targeted infill feasibility and implementation plans/drawings for landscape islands, between-lot areas, and the ED parking lot, preserving stall/aisle standards, slopes, and positive drainage;

• Integration of protected pedestrian paths, striped crossings with speed bump protection at drive inlets, Loop

Road crossings, and LED RRFB signage at conflict points per FHWA, MUTCD, and VA guidelines;

• Assessment findings and proposed improvements for the flagpole roundabout between Lots A and B, per Section

2.1;

• Verification of no conflicts with structural, utility, or drainage systems; for lots deferred due to unresolved conditions, a phasing narrative identifying the resolution path and projected construction start in lieu of completed plans at 65%, with full plans provided at 95%/100%;

• A proposed phasing plan and construction schedule identifying the sequence of lot closures and early-phase construction areas, coordinated with Section 3.2;

• A Parking Lot Closure and Traffic Management Plan detailing coordinated, phased lot shutdowns that maintain facility access for VA staff and patients throughout construction; identification of VA patient transportation service drop-off and pick-up zones, as provided by the

COR, with approved temporary alternatives established and operational prior to each associated closure; and temporary wayfinding and traffic control signage designed, fabricated, installed, and maintained by the DB contractor per VA TIL and MUTCD standards.

• Where any element above is determined to be infeasible at a specific location, the DB AE shall document the basis and propose an alternative for VA review and approval prior to proceeding. The COR will identify VA patient transportation service providers and designated drop-off areas at or following the Kick-Off Meeting to inform the contractor's planning efforts.

2.4.4. Cost Estimates: Use VA estimating standards. Break out costs by individual parking lot and provide a prioritized list for implementing shade structures and pedestrian-safety reconfiguration. The priority sequence for design and construction shall be: (1) protected pedestrian walkways and Loop Road crossings; (2) shade canopy coverage for interior lots;

and (3) parking stall infill, including the ED Parking Expansion. Identify parking stall infill and/or additional lots as deduct alternates to maintain the established construction limit.

2.4.5. Schedule: Phased construction schedule to maintain parking operations and facility access, coordinated with the Parking Lot Closure and Traffic

Management Plan per Section 2.4.3.1.

3.0. Period of Performance (PoP) & Separate Construction NTP

3.1. Overall PoP (Parallel Design & Construction)

3.1.1. Design & Preconstruction (to 65%): Target 120 calendar days from issuance of Design NTP, including BOD/SUE/Geotech, QCP, and

35%/65% workshops.

3.1.2. Construction (separate NTP; parallel start): Target ~320–340 calendar days from Construction NTP (issued after VA acceptance of 65%).

3.1.3. Final Design (95%/100% IFC): Complete by Design NTP + 210 days, supporting early fabrication/field work.

3.1.4. Closeout: 45 calendar days for as-builts, O&M, warranties, etc.

3.1.5. Total project PoP (Design Phase, Construction Phase, and → Final

Acceptance): 550 calendar days from issuance of the initial design NTP. This range represents the contractual ceiling for project duration.

The DB contractor shall refine and confirm the project schedule at the

35% design milestone based on AE findings, utility conditions, and hospital operations; schedule refinements shall fall within the established ceiling and shall not extend the contract period of performance without a formal contract modification.

3.2. Separate Construction NTP Provision

3.2.1. VA may issue a separate Notice to Proceed (NTP) for construction upon acceptance of the 65% design and associated investigative reports —

BOD, SUE Level A/B with potholing, and Geotechnical Report. The intent of the early Construction NTP is to permit the DB contractor to commence surface-level work — including pedestrian walkway construction, striping, signage, speed bump installation, and parking lot reconfiguration — in areas where shade canopy installation is not yet underway, thereby advancing the project schedule in parallel with long-lead canopy fabrication and submittal review.

The DB contractor shall identify, within the 65% Parking Lot

Reconfiguration Plan, which lots and work elements are proposed for early-phase construction and confirm feasibility of phased lot closures given hospital operations and parking availability.

Early Construction NTP is contingent on validated investigative reports and VA acceptance of the 65% design. If utility conflicts, geotechnical findings, or ADA/drainage constraints in the proposed early-phase areas remain unresolved at the time of 65% acceptance, the Construction NTP for those areas shall be deferred until conflicts are resolved, to avoid utility strikes, foundation redesigns, ADA nonconformance, or cost and schedule impacts.

DESIGN BUILD & CONSTRUCTION MILESTONES

ACTION CALENDAR

DAYS

Kick-Off Meeting and Preliminary Site Review 20 Notice to Proceed

35% Design Submittal & Meeting NTP + 60 Kickoff Meeting

35% Veteran Affairs Comments NTP + 74 35% Design Submittal & Meeting

65% Design Submittal and Meeting NTP + 120 35% VA Comments

65% Veterans Affairs Comments NTP + 134 65% Design Submittal & Meeting

95% Design Submittal & Meeting NTP + 180 65% Veteran Affairs Comments

95% Veteran Affairs comments NTP +194 100% Design Submittal & Meeting

100% Final Documents Submittal NTP + 210 100% Veterans Affairs comments

For the Design phase

For the Construction Phase

Total Contract time (120 + 120) = 550 days

4.0. DESIGN & CONSTRUCTION COORDINATION

4.1. Meetings (Minimum Requirements)

Meeting Purpose Participants

(Minimum) Timing/Frequency

Kick-Off Confirm scope, BOD

Outline, Schedule, roles, risks

VA PM/COR

AE PM/Leads

DB/GC PM

Design NTP + 7 Days

35% Review Workshop

Mobilization plan, safety/QC; traffic & pedestrian control

VA PM/COR

AE PM/Leads

DB/GC PM

At 35% Submittal

65% Review Workshop

Validate canopy typologies, footing

VA PM/COR

AE PM/Leads

At 65% Submittal

Meeting Purpose Participants (Minimum)

Timing/Frequency concepts, drainage & paths

DB/GC PM

Key Subs

100%/ Pre- Construction

Finalize utilities, structural, drainage, accessibility layouts

Mobilization plan

VA PM/COR

AE PM/Leads

DB/GC PM

At 100% Submittal

Weekly Design Progress

Status, look-ahead, RFIs, changes

VA PM/COR

VA Contracting

AE PM/Leads

DB/GC PM

Weekly During

Design

Weekly Construction Progress

Status, look-ahead, RFIs, changes, safety

VA PM/COR

VA Contracting

AE PM/Leads

DB/GC PM

Superintendent

Weekly During

Construction

Pre-Installation Verify layout, clearances, pier locations, utilities

DB Structural

AE Structural

VA PM/COR

Per Design Phase

Substantial Completion Meeting

Punch-list; turnover planning

VA PM/COR

VA Contracting

AE PM

DB/GC PM

At Substantial

Completion

Final Closeout Meeting

Punch-list close, As-builts, O&M Training

Plan, Warranty

Acceptance

VA PM/COR

VA Contracting

AE PM

DB/GC PM

Before Final

Acceptance

4.2. Investigative Site Visits (Minimum Requirements)

Visit Purpose/Tasks Minimum Frequency

Topographic & Layout

Verification

Confirm stall counts, aisle widths, island dimensions, curb lines, ADA/ABAAS routes

2 visits (pre-BOD & pre-65%)

Utilities SUE/Potholing

Coordination

Witness test pits in planned pier zones; map conflicts/avoidance

2 visits (pre-BOD & pre-65%)

Geotechnical Coordination Coordinate borings; verify soils vs. design assumptions, validate drainage inlets & flow paths, identify low spots/ponding risks

As Needed; minimum 1 visit pre-65%

5.0. SUBMISSION REQUIREMENTS FOR DELIVERABLES

5.1. The Contractor shall furnish the required documents in accordance with the

Submittal Table below.

5.2. All deliverables submitted as PDF files shall be searchable and contain a bookmarked Table of Contents linked to respective sections, title pages, etc.

Drawings in PDF shall have bookmarks for each drawing page within a table of contents to allow quick navigation to individual drawing sheets. Drawings in DWG shall be drawn in AutoCAD 2018.

5.3. All digital files shall be submitted via a File Transfer Protocol (FTP) website, such as Procore, Submittal Exchange, etc. Submittal title pages or labels shall contain at minimum the following; Project Name, Client Name (VA Southern Nevada

Health Care System), Contract Number, Project Number, Submittal phase, Name of Contractor/Designer, Submittal Date.

5.4. Provide hard copies of all submittals per the Submittal Table below.

5.5. All files, layers, naming conventions and standards should follow the VA BIM &

CAD Standards described on PG-18-13 of the TIL.

5.6. The Construction Contractor or assigned Architect-Engineer (A-E) shall develop

As-built drawings based on record drawings from construction.

5.7. All submittals via FTP website shall be zipped for archive at Substantial

Completion and sent to the VA for record.

DELIVERABLE

SUBMISSION

TIMING

(Relative to NTP or Design

Milestone)

HARD

COPIES TO

VA

PAPER SIZE

DIGITAL FILE

FORMATS

Basis of Design (BOD) report)

NTP + 35 Days

(Initial Concept)

0 Letter (8 ½ x 11 inch) PDF

Utility Survey Report

With BOD report 0 Letter PDF

Geotechnical Report

With BOD report 0 Letter PDF

Quality Control Plan

NTP + 45 Days 0 Letter PDF

35% Design Submittal

NTP + 60 Days 2

(Drawings, 1 Narrative)

Drawings: Arch E1 &

Half-Size

Narrative: Letter

PDF (all), DWG

(drawings)

65% Design Submittal

NTP + 120 Days 2

(Drawings, 1 Narrative)

Drawings: Arch E1 &

Half-Size

Narrative: Letter

PDF (all), DWG

(drawings)

95% Design Submittal

NTP + 180 Days 2

(Drawings, 1 Narrative)

Drawings: Arch E1 &

Half-Size

Narrative: Letter

PDF (all), DWG

(drawings)

100 % Construction Documents

NTP + 210 Days 2

(Drawings, 1 Narrative)

Drawings: Arch E1 &

Half-Size

Narrative: Letter

PDF (all), DWG

(drawings)

Construction Schedule

With

65%/95%/100%

Submittal

0 Letter PDF

Structural Calculations

With

65%/95%/100%

Submittal

0 Letter PDF

DELIVERABLE

SUBMISSION

TIMING

(Relative to NTP or Design

Milestone)

HARD

COPIES TO

VA

PAPER SIZE

DIGITAL FILE

FORMATS

Drainage Analysis

With

65%/95%/100%

Submittal

0 Letter PDF

Parking Lot Reconfiguration Plan

At 35%;

updated at 65%/95%/100%

(must be substantially complete/approv ed at 65%)

0 Letter PDF

As-Builts Drawings

30 Days after

Substantial

Completion

2 Arch E1 & Half-Size PDF, DWG

O&M Manuals

30 Days after

Substantial

Completion

1 Letter PDF

Warranty Documentation

30 Days after

Substantial

Completion

1 Letter PDF

6.0. HOURS OF OPERATION AND PHASING

6.1. Normal duty hours are 8:00 AM – 4:30 PM, Monday through Friday, excluding standard Federal Holidays. Federal Holidays can be obtained on OPM’s website

(www.opm.gov). All work shall be coordinated and scheduled through the COR.

6.2. All work carried out for this contract shall maintain hospital operations; phase work to keep maximum parking availability.

6.2.1. Sequence lot closures in short, managed segments with clear detours and temporary, accessible routes.

7.0. COST & SCHEDULE

7.1. Develop and update cost estimates and schedules in accordance with VA standards, following the Cost Estimating Manual found in the VA TIL

(www.cfm.va.gov/TIL).

7.1.1. Break out costs by individual parking lot and provide a prioritized list for implementing shade structures and pedestrian-safety reconfiguration.

Identify infill of additional parking stalls and/or lots as deduct alternates to maintain the established construction limit.

8.0. CONSTRUCTION PERIOD SERVICES

8.1. RFI Response Time: 14 calendar days from receipt by AE and 14 calendar days from receipt by VA (individually); if the construction timeline is impacted, responses shall be expedited earlier to avoid delay.

8.2. Submittal Review: 14 calendar days by AE and 14 calendar days by VA

(individually) per submittal, unless schedule impacts require earlier action.

8.3. Field Clarifications/Directives: Provide written field clarifications within 14 calendar days unless safety/operations require immediate direction; coordinate through COR.

8.4. Shop Drawing Reviews: Meet the 14-day standard; prioritize canopy steel, foundations, traffic/pedestrian control, and drainage submittals to support phasing.

8.5. Change Order Pricing/Time Impact Analyses: Provide within 14 calendar days of request unless otherwise negotiated for critical path items.

8.6. AE shall provide responses in less time within reason if the contract time of 14 days would cause a delay or other impact to the contract

9.0. ABBREVIATIONS

ABAAS – Architectural Barriers Act Accessibility Standard ADA – Americans with Disabilities Act AE – Architect/Engineer BOD – Basis of Design CM – Construction Manager COR – Contracting Officer’s Representative DB – Design–Build FHWA – Federal Highway Administration GC – General Contractor www.cfm.va.gov/TIL

IBC – International Building Code IFC – Issued for Construction LED – Light Emitting Diode MUTCD – Manual on Uniform Traffic Control Devices NTP – Notice to Proceed O&M – Operations and Maintenance OPM – Office of Personnel Management PG-18-10 – VA Design Manual Series (Site, Parking, Signage, etc.)

PoP – Period of Performance RFI – Request for Information RRFB – Rectangular Rapid Flashing Beacon SUE – Subsurface Utility Engineering VA – Department of Veterans Affairs VASNHS – VA Southern Nevada Healthcare System

10.0. REFERENCE MATERIAL (VA-PROVIDED)

REFERENCE DOCUMENT NAME

Assignment 21 – Draft Schematic Design and Report.PDF

Assignment 44 – Conceptual Design for Carports.PDF

Assignment 44 – Parking Study.PDF

593-14R-200 – Existing Carport Design.PDF

ED Parking Expansion.PDF

11.0. VA SECURITY REQUIREMENTS FOR CONTRACTORS

All contractor’s and subcontractor’s personnel shall be subject to VA Directive 0735, Homeland

Security Presidential Directive 12 (HSPD-12) Program, Federal laws, regulations, standards, and VA Handbooks regulating VA personnel regarding information and information system security.

a. Non-Personal Identity Verification (PIV) Card requests shall be submitted to

VA COR (Contracting Officer Representative) by the contractor. Request submission is the contractor’s responsibility to properly fill out the documents identified below. These documents will become a package for submission of

Non-PIV Card application:

1. VA Fingerprinting form

2. Declaration for Federal Employment (OF306), if there are any questions that were answered “yes” on item 9-13 on this form, fill out the appropriate addendum and include in the package.

3. Authorization For Release of Information (VA Form 0710)

4. Self-Certification of Continuous Service

5. Contractor Background Investigation Request

b. Non-PIV Card process may take 30-45 days, depending on the contractor’s personnel background check, Special Agreement Check (SAC). SAC is an automated records check conducted by the Federal Bureau of Investigation in collaboration with the Office of Personnel Management (OPM).

c. Non-PIV Card Applicant is subject to National Agency Check with written

Inquiries (NACI) conducted by OPM. This investigation covers a period of 5 years and a review of current records in the OPM Security Investigation Index (SII), DOD Defense Central Investigations Index (DCII), FBI name check, and FBI fingerprint check as well as written inquiries from previous employers and references on the application for employment. It is used for Non-sensitive or Low

Risk positions in VA.

d. Once all documents are complete and properly filled out, hand carry and submit to VA COR. Do not send completed forms through email due to Personal

Identifiable Information.

e. VA COR will then provide all documents to Engineering Service’s VA PIV

Sponsor/Manager to initiate the Non-PIV process.

f. PIV Sponsor/Manager will notify each applicant when to proceed for fingerprinting appointment.

g. Each applicant shall be fingerprinted at VA Southern Nevada Healthcare

System’s PIV Office, located on the first floor in Building 6 (Administration

Building), 6900 N. Pecos Road, N. Las Vegas, NV 89086. Each applicant shall sign in at the Security Desk.

h. VA COR or PIV Sponsor/Manager will provide status of each applicant’s Non-PIV

Card.

i. Non-PIV Card is critical for the construction start date, as the contractor’s personnel without Non-PIV Card may result with a restricted, limited, or no access to the job site. See attached blank forms/documents that are required for submission of Non-PIV Card application for each of contractors/sub-contractors

Contractor shall not require access to the VA internal trusted network for this scope. The certification and accreditation (C&A) requirements do not apply, and a Security Accreditation

Package is not required.

– END OF STATEMENT OF WORK –