S05 RFI 19 -20 Answered 36C26125Q0029 Amendment 0004.pdf

PDF 86 KB Posted

Attached to
Z1DA--36C261-24-AP-5056 | 36C26125Q0029 | VA Palo Alto Boiler Plant Retrofit
Solicitation number
36C26125Q0029
Issued by

About this file

This document is a Request for Information (RFI) related to the VA Palo Alto Boiler Plant Retrofit project, Solicitation #36C26125Q0029. The RFI contains responses from the VA Project Manager to two specific questions from the contractor:

  1. The performance period for each retrofit option is not possible considering material lead times, scope of work, and testing. The contractor estimates the work will take 2-3 times longer than the 120-day period listed in the solicitation. The VA Project Manager stated that no change in the performance period will be made at this time, but the contractor can provide a schedule after notice to proceed, and any extension will be approved by the Contracting Officer based on justified need.

  2. The contractor plans to quote a completely new control panel for each boiler as part of the repairs, as the original installing contractors did not follow the VA's specifications. The VA Project Manager reiterated the response to the first question, indicating no change to the performance period at this time.

The related federal contract opportunity is a Request for Quotes (RFQ) for the VA Palo Alto Boiler Plant Retrofit project. The objective is to retrofit three existing boilers at the VA Palo Alto Health Care System facility to meet safety standards. The solicitation includes two line items with different performance periods and requirements for as-built drawings.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C26125Q0029

36C261-24-AP-5056 | 36C26125Q0029 | NRM 640-25-900 VA Palo Alto Boiler Plant Retrofit

RFI FORM

Send to Contract Specialist: nicole.renfrew@va.gov

RFI

(REQUEST FOR INFORMATION)

RFQ #:

36C26125Q0029 CONTRACTOR RFI #: 19 and 20

PROJECT NAME:

VA Palo Alto Boiler

Plant Retrofit

DATE REQUESTED: 10/30/2024

ACQUISITION NO.:

N/A REFERENCE: Documents:

36C26125Q0029_1

DRAWING: n/a SPECIFICATION SECTION:

n/a

DESCRIPTION OF PROBLEM OR INFORMATION BEING REQUESTED

Please be specific as possible:

Please clarify the following RFI’s.

19. The performance period for each retrofit option is not possible considering the material lead times, scope of work, testing, etc. Based on experience with similar projects we estimate this will take 2X or 3X more days than the VA has listed. Does this need to be addressed before the bid or does this get extended once awarded and all lead times, scheduling, planning is complete for a realistic schedule to complete?

20. Based on our experience with the approval process for boiler plants, as part of the repairs we will be quoting a completely new control panel for each boiler to meet the VA specs. We do not see any other way to get this through their approval process, especially since the original installing contractors didn’t follow the specifications during the original retrofit. This retrofit scope relates to the extra time needed for the performance period and to complete our bid.

VA PROJECT MANAGER’S RESPONSE

19. No change in period of performance is made at this point. Contractor to provide a schedule after

NTP. Extension in period of performance will be approved by CO based on justified need.

20. See response to # 19.

VA TRACKING # FOR ALL RFIs: AMENDMENT #: 0004

VA PROJECT ENGINEER/MANAGER: Naveed Subhan DATE: 11/5/2024

2024-11-05T12:04:48-0800
NAVEED SUBHAN

File details come from the government source that posted it. Updated .