This document outlines requirements for a federal contract solicitation to renovate residential and treatment spaces at the Rocky Mountain Regional VA Medical Center. The solicitation seeks a contractor to complete three line items of renovation work, including converting an existing residential apartment to storage and office spaces, converting an existing nursing office to flexible treatment spaces, and an alternate bid option to convert the nursing office to two semi-private treatment rooms. Prospective offerors must submit questions by March 23, 2022 and final proposals by April 14, 2022. The work is to be completed within 90 calendar days of notice to proceed. The contractor must adhere to all applicable federal, state and local regulations and VA standards, and provide necessary documentation, schedules, safety plans and personnel qualifications. The estimated value of the contract is between $250,000 and $500,000.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Bid Meeting
FOR
The contractor is to provide all labor, tools, materials, equipment and supervision required to Renovate K1 SCI Residential Apartment at the Rocky Mountain Regional VA Medical Center.
Location: Rocky Mountain Regional VA Medical Center
AGENDA:
· Introduction of Joseph Wingfield CO, Mark Blehm COR, and Sylwia Zak CS
· The pre-bid meeting/site walk is not mandatory
· QUESTIONS During site visit MUST BE WRITTEN DOWN
· Address where to send RFP:
· Electronic submissions to sylwia.zak@va.gov
· Pertinent Dates:
· Questions due March 23, 2022 at 1pm, any questions submitted after this time will not be reviewed or answered! submit to sylwia.zak@va.gov
· We’ll get the answers back to you timely
· Proposals due on 4/14/2022 at 11 AM MT via email
· Prospective bidders are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.
· Prospective bidders are prohibited from visiting site other than through formal invitation by Contracting Officer.
· Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded
· Masks are required at all times while on VA property. Entrance screenings will be conducted each day.
· Confirmation of construction range is between $250,000.00 and $500,000.00
· Bid Guarantee & Payment/Performance Bonds: Are required at 20% of bid price of $3,000,000.00 whichever is less.
· Contractor shall begin performance within 10 days after Notice To Proceed (NTP) and complete within 90 calendar days.
· Post Award Compliance:
· Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor. The contractor can submit their weekly certified payrolls with their monthly invoice.