This document outlines a federal contract solicitation for construction services. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19 is seeking a contractor to provide all labor, materials, equipment and services required to remodel the west and south wings of the 5th floor in Building 1 at the VA Western Colorado Health Care System campus in Grand Junction, Colorado. The project budget is between $500,000 and $1,000,000. The solicitation number is 36C25921R0031 and is designated as a 100% set-aside for verified Service-Disabled Veteran-Owned Small Businesses. Offerors must be verified and listed in the Vendor Information Pages database prior to award. The contractor is expected to begin performance within 10 days of the Notice to Proceed and complete the project within 120 days, with an anticipated possession of the first phase after 30 days.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25921R0031 0005.docx | DOCX document | |
| 36C25921R0031 0004.docx | DOCX document | |
| 03c Combined Specifications-3-17-2021.pdf | ||
| 36C25921R0031 0003.docx | DOCX document | |
| Instructions to Offerors - PPT-updated.pdf | ||
| G3 SARRTP DEMO.pdf | ||
| G6 SARRTP FIRE SYSTEM.pdf | ||
| G8 SARRTP DETAIL.pdf | ||
| G4 SARRTP CONSTRUCTION.pdf | ||
| G7 SARRTP VIDEO SYSTEM.pdf | ||
| G1 SARRTP FUNCTIONAL PLAN.pdf | ||
| RFI 3 factor 1.pdf | ||
| Past Performance Questionnaire.docx | DOCX document | |
| G2 SARRTP EXISTING _ ICRA.pdf | ||
| G5 SARRTP EQUIPMENT.pdf | ||
| 010000 General Conditions.pdf | ||
| RFI 1.pdf | ||
| 36C25921R0031 0002.docx | DOCX document | |
| RFI 2.pdf | ||
| 36C25921R0031 0001.docx | DOCX document | |
| 20210224_575-20-114 SARRTP PreBid GC Site Walk.pdf | ||
| 36C25921R0031_1.docx | DOCX document | |
| 03b Background.pdf | ||
| 03a Combined Drawings.pdf | ||
| 01b Bid Sheet.xlsx | XLSX spreadsheet | |
| 03c Combined Specifications.pdf |
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Bid Meeting
FOR
Repurpose 5th Floor for SARRTP Project 575-20-114
The contractor is to provide all labor, tools, materials, equipment and supervision required to complete the construction of the Station Level Project 575-20-114 entitled Repurpose 5th Floor for SARRTP Provide labor, materials, equipment, and other services as necessary to remodel the West and South wings of the 5th floor in Building 1 at the Grand Junction VA campus, 2121 North Ave., Grand Junction, CO 81501.
Time: 2/24/2021, 10:00 AM MST
Location: VA Western Colorado Health Care System, 2121 North Avenue, Grand Junction, CO 81501.
AGENDA:
Introduction of Project Manager/COR
Discussing renovation of project The pre-bid meeting/site walk is not mandatory Review Instructions to offerors for information on preparing and submitting proposal.
QUESTIONS During site visit MUST BE WRITTEN DOWN Address where to send RFP:
o Electronic submissions to Robyn.young2@va.gov Pertinent Dates:
o Questions due by 3/8/2021, any questions submitted after this time will not be reviewed or answered. Submit to Robyn.young2@va.gov o We’ll get the answers back to you timely o Proposals due on 3/22/2021 at 2:00 PM MDT via email
Confirmation of construction range is between $500,000 and $1,000,000.00.
Bid Guarantee & Payment/Performance Bonds: Bid Guarantee & Payment/Performance Bonds:
IAW FAR 52.228-15, offerors are reminded that any award amount exceeding $150,000 shall require both Payment and Performance Bonds. Performance and Payment bonds are due no later than 10 calendar days after award. Original bid guarantee due at time of solicitation closing.
Address to send original bid bonds is in instructions to offerors. If original bid guarantee is not received by the solicitation closing date and time, proposal will be late and will not be considered.
Contractor shall begin performance within 10 days after Notice To Proceed (NTP) and complete within 120 days. This will be a two-phase project running concurrently. It is the Government’s expectation to take possession of phase I of the project when completed after 30 days.
Post Award Compliance:
o Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor. The contractor can submit their weekly certified payrolls with their monthly invoice.