9-H1091.pdf
PDF 423 KB Posted
- Solicitation number
- 36C25626R0067
About this file
This is a technical drawing document detailing environmental hazards and abatement requirements for Building 109 at the Michael E. DeBakey Veterans Affairs Medical Center (VAMC) in Houston, Texas, as part of a construction project involving the installation of a new overhead paging system.
The project, identified as Drawing Number H1091 (Project 580-25-101), requires contractors to perform work within Building 109 across three levels while managing significant asbestos-containing material (ACM) hazards. The scope includes approximately 160 penetrations across the three levels (18 on Level 0, 42 on Level 1, and 20 on Level 2) plus 80 negative pressure mini-enclosures to accommodate new telecommunications infrastructure for the paging system. All drywall walls and ceilings contain applied ACM joint compound and texture; penetrations must be made using manual means within negative pressure enclosures, with encapsulant applied at all through-penetrations in double-sided drywall walls. The existing ceiling grid and wall angle edging must be maintained. Additional hazardous materials present throughout the building but not anticipated to be impacted include black mastic underlying floor tile (presumed asbestos-containing), all beige 12" x 12" floor tile (ACM with underlying asbestos black mastic), and mastic on wooden beams at the penthouse level. Work likely to impact these materials must be performed by a licensed abatement contractor. The document requires contractors to replace ceiling tiles at the end of each work shift outside rated construction barriers or implement 1-hour fire-rated separation between construction areas and occupied portions of the building.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25626R0067 0005.docx | DOCX document | |
| 36C25626R0067 0004.docx | DOCX document | |
| 36C25626R0067 0003.docx | DOCX document | |
| 36C25626R0067 0002.docx | DOCX document | |
| Sign in Sheet 580-25-101.jpg | JPG image | |
| DOL Wage Determinations dated 5-18-26.pdf | ||
| 36C25626R0067 0001.docx | DOCX document | |
| SF24 Bid Bond.pdf | ||
| 580-25-101 Project Specifications.pdf | ||
| 36C25626R0067_1.docx | DOCX document | |
| DOL Wage Determinations TX20260253 dated 1-2-26.pdf | ||
| 580-25-101 Statement of Work.docx | DOCX document | |
| 580-25-101 Project Drawings.pdf | ||
| 36C25626R0067.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
Veterans Health
Administration
VA FORM 08-6231
DRAWING TITLE PROJECT TITLE
LOCATION
DATE CHECKED DRAWN
PROJECT NUMBERCONSULTANTS:
DRAWING #
VA HEALTH CARE SYSTEM APPROVAL:
ARCHITECT:
FULLY SPRINKLERED
1 2 � 4 � 6 � 8 �
1 2 � 4 � 6 � 8 �
STAMP:
DRAWING NUMBER
BUILDING NUMBER
ARCHITECT MECH / ELEC / PLUMB / TELECOM
SPUR DESIGN
2519 MADISON AVE., STE 100
KANSAS CITY, MO 64108
(913) 369-7200
SPUR DESIGN
312 SW 25TH STREET
OKLAHOMA CITY, OK 73109
(405) 842-6100
FIRE PROTECTION ENGINEER
RATED ENGINEERING
609 S. KELLY AVENUE, STE H2
EDMOND, OK 73003
(405) 210-5814
INDUSTRIAL HYGENIST
RIVERFRONT SAFETY & HEALTH
11140 S TOWNE SQUARE, STE 100
ST. LOUIS, MO 63123
(314) 917-0148
PHYSICAL SECURITY
FORCE PROTECT
10901 FRONT BEACH RD, UNIT 1415
PANAMA CITY BEACH, FL 32407
(502) 836-4232
H2B ENGINEERS, INC.
1225 NORTH LOOP WEST, # 800
HOUSTON, TEXAS 77008
(713) 864-2900
TEXAS FIRM REGISTRATION #: 8856
H2B#: 23-133
2/1 9/2
4 9
:13 :29
A M
BUILDING 109 - ENVIRONMENTAL HAZARDS
AND ABATEMENT
CD 13 OF 231JR
OVERHEAD PAGING SYSTEM
07/21/2025
580-25-101
MICHAEL E. DEBAKEY VAMC
2002 HOLCOMBE BLVD
HOUSTON, TX 77030 H1091
No. REVISION DESCRIPTION DATE
ENVIRONMENTAL HAZARDS - BUILDING 109 - LEVEL 01ENVIRONMENTAL HAZARDS - BUILDING 109 - LEVEL 12
ENVIRONMENTAL HAZARDS - BUILDING 109 - LEVEL 23
HAZARDOUS MATERIAL KEYNOTES
DRYWALL WALLS AND CEILINGS HAVE APPLIED ACM DRYWALL JOINT COMPOUND
AND/OR INFREQUENT APPLICATION OF ACM TEXTURE. USING MANUAL MEANS WITHIN A
NEGATIVE PRESSURE ENCLOSURE, PROVIDE PENETRATIONS THROUGH THE DRYWALL
AS NECESSARY TO WIRE AND INSTALL FIXTURES FOR NEW OVERHEAD PAGING
SYSTEM AS SHOWN BY TELECOMMUNICATIONS DRAWINGS. APPLY ENCAPSULANT AT
AND WITHIN THROUGH NORMALLY DOUBLE SIDED DRYWALL WALLS. EXISTING CEILING
GRID IS TO BE MAINTAINED, INCLUDING CEILING GRID WALL ANGLE (EDGING) AS
ATTACHED TO ACM DRYWALL WALL SYSTEM. COORDINATE LOCATION AND EXTENTS
OF PENETRATIONS WITH THE GENERAL CONTRACTOR AND INSTALL PENETRATIONS IN
THE APPROXIMATE QUANTITIES OF, 18 PENETRATIONS ON LEVEL 0, 42 PENETRATIONS
ON LEVEL 1, 20 PENETRATIONS ON LEVEL 2 AND 80 NEGATIVE PRESSURE
MINI-ENCLOSURES.
ASBESTOS DRYWALL CEILING SYSTEM. WHERE KEYNOTE H1 IS PRESENT, PERFORM
WORK IN ACCORDANCE WITH KEYNOTE H1 AND THE CEILING PENETRATIONS ARE
INCLUDED IN ESTIMATED TOTALS.
INTERMITTENT SMALL NUMBERS OF DRYWALL CEILING PANELS MAY BE PRESENT IN
SUSPENDED ACOUSTICAL CEILING GRID. WHERE A DRYWALL PANEL IS ENCOUNTERED
WITH APPLIED DRYWALL JOINT COMPOUND AND/OR TEXTURE, DO NOT DISTURB AND
REMOVAL IS TO BE PERFORMED BY THE LICENSED ABATEMENT CONTRACTOR.
H1
12010
108A
FH
FH
FH2
KEY PLAN - BLDG 109
H1 H1
H1
H1
H1
H1H1
H1
H1
H1
H1
H1
H1
H1
H1
H1 H1 H1
H1
H1
H1 H1
H1
H1
H1 H1 H1
H1H1
H1
H1H1 H1 H1
H1
H1
H1
H1
H1
H1 H1 H1 H1H1
H1
H1
H1
H1
100% BID DOCUMENTS
H2
H3
HAZARDOUS MATERIAL NOTES
THE FOLLOWING HAZARDOUS MATERIALS ARE PRESENT THROUGHOUT BUILDING 109
BUT ARE NOT ANTICIPATED TO BE IMPACTED WITHIN THE TARGETED SCOPE OF WORK.
SHOULD THESE MATERIALS OR ADDITIONAL SUSPECT MATERIALS BE ENCOUNTERED,
STOP WORK IMMEDIATELY AND CONTACT VA COR FOR DIRECTION.
DRYWALL WITH JOINT COMPOUND AND TEXTURE IS ASBESTOS CONTAINING. ANY
WORK LIKELY TO IMPACT WALL SYSTEMS THROUGHOUT WILL REQUIRE
ABATEMENT BY A LICENSED ABATEMENT CONTRACTOR
BLACK MASTIC UNDERLYING FLOOR TILE OR OTHER COVERINGS IS GENERALLY
PRESENT THROUGHOUT BUILDING AND PRESUMED TO BE ASBESTOS
CONTAINING. WORK LIKELY TO IMPACT ASBESTOS BLACK MASTIC ON FLOOR IS
TO BE PERFORMED BY A LICENSED ABATEMENT CONTRACTOR. ALL BEIGE 12" X
12" FLOOR TILE IS CONSIDERED AN ASBESTOS CONTAINING MATERIAL(ACM) AND
ASBESTOS BLACK MASTIC (PACM) WILL BE UNDERLYING.
MASTIC ON WOODEN BEAMS AT THE PENTHOUSE LEVEL IS ASBESTOS
CONTAINING.
NOTE: AT END OF EACH SHIFT, THE REPLACEMENT OF CEILING TILES IS REQUIRED
WITHIN WORK AREAS OUTSIDE OF A RATED CONSTRUCTION BARRIER. IF THE TILES
CANNOT BE REPLACED, THE SPRINKLER SYSTEM MAY BE CONSIDERED OUT OF
SERVICE IN THESE AREAS AND 1-HOUR FIRE RATED SEPARATION WILL BE REQUIRED
BETWEEN THE CONSTRUCTION AREA AND THE OCCUPIED PORTIONS OF THE BUILDING.
H1 H2
H1
H1 H1 H1
H1
H3
H2
H1
H1
H1
H1H1
H1
H1 H1
H2 H2 H2 H2 H2 H2
H2 H2
H2
H2
H2
H2
H2
H2
H2 H2 H2 H2 H2 H2
H2
H2 H2 H2
H2 H2 H2 H2 H2
H2
H2
H2 H2
H2 H2
H2
H2
H2 H2 H2 H2
H1
H1
1 BUILDING 109 ABATEMENT UPDATE 06/26/2026
| Sheets and Views |
| Model |
File details come from the government source that posted it. Updated .