Clarification.pdf
PDF 61 KB Posted
- Attached to
- Z1DA--Upgrade Fire Alarm System 583-26-221 Federal contract opportunity
- Solicitation number
- 36C25025B0039
About this file
This document is a clarification document for a VA solicitation (36C25025B0039) seeking to upgrade fire alarm systems at multiple campuses. The document requests specifications for two key areas: 01 91 00 (General Commissioning Requirements) and 28 08 00 (Commissioning of electronic safety and security systems), and seeks clarification on commissioning responsibilities. Additionally, the document notes that electrical wiring route drawings are not currently available and recommends that the contractor conduct field investigation and verification. The VA specifications indicate that while commissioning is not a standard requirement for this project, testing and verification requirements are specified in 28-31-00 and will be provided by the contractor.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1) Please provide specifications for the following missing specifications:
A. 01 91 00 - General Commissioning Requirements
B. 28 08 00 - Commissioning of electronic safety and security systems.
C. Who is responsible for Commissioning? If the Contractor is responsible, please provide the specification section mentioned above.
2) Please provide drawings showing the routes for electrical wiring and where they will be connecting into panelboards.
VHAINDBoydN Inserted Text
VHAINDBoydN Text Box VA specs include commissioning as a standard but for some projects commissioning is not required. Commissioning is not required for this project. Testing and verification requirements are specified in 28-31-00
VHAINDBoydN Text Box VA specs include commissioning as a standard but for some projects commissioning is not required. Commissioning is not required for this project. Testing and verification requirements are specified in 28-31-00
VHAINDBoydN Text Box VA specs include commissioning as a standard but for some projects commissioning is not required. Commissioning is not required for this project. Testing and verification requirements are specified in 28-31-00 and shall be provided by the contractor for this project.
VHAINDIbrahM Text Box The drawing are not available, field verification is required by the contractor. Contractor is more than welcome to come in for field investigation/verification.