Revised 552-19-103 Drawing - AD101.pdf
PDF 546 KB Posted
- Solicitation number
- 36C25020B0069
About this file
This solicitation is for project number 552-19-103 to improve a sub-specialty waiting area at building 310 of the Dayton VA Medical Center located at 4100 W Third Street in Dayton, Ohio. The project scope includes fully renovating approximately 4,000 square feet of a 20,000 square foot first floor suite and additional areas to receive new finishes and plumbing. Ten new exam rooms will be created and approximately 27 existing exam rooms will receive upgrades to sinks, fire alarm, and nurse call systems. Corridors will be abated and receive finish upgrades, and most areas will get new LED light fixtures. The estimated value is between $2-5 million and the NAICS code is 236220 with a size standard of $39.5 million. The solicitation is a 100% set-aside for SDVOSBs registered in the Vendor Information Pages and SAM.gov databases. The SDVOSB must perform a minimum of 15% of construction work. The duration shall not exceed 220 calendar days from notice to proceed and bonds are required. A site visit will be scheduled and the solicitation issued on July 29, 2020 with bids due approximately 30 days later. The agency is the Department of Veterans Affairs Veterans Health Administration VISN 10.
View the file
Other files
Show 40 more
Latest 50 of 75 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
4 4
H J K L M N
GE F
P
1 7
1 7
7 7
1 1
7 7
7 7
1 1
1 71
EXISTING
NEW
WOMENS
1E-158
BREAK ROOM
1E-112
STAFF LOUNGE
1E-112A
MENS
1E-158A
EXAM
1E-153
EXAM
1E-154
EXAM
1E-148
EXAM
1E-150
EXAM
1E-155
NEURO CHECK-IN
1E-152
SOILED UTILITY
1E-159
NURSE CHECK-IN
1E-160
CORRIDOR
C1-28
CLEAN UTILITY
1E-162
OUTPATIENT NURSE MGR
1E-161
DERM-MINOR SURGERY
1E-160A
ANESTHISIA CONSULTANT
1E-124B
PHOTOTHERAPY
1E-160B
DERM CHECK-IN
1E-160C
BLOOD DRAW
1E-124A
NURSE CHECK-IN
1E-160D
EXAM
1E-124
EXAM
1E-122
EXAM
1E-121
CAST ROOM
1E-115C
EXAM
1E-115D
EXAM
1E-115E
EXAM
1E-115F
EXAM
1E-116
VITALS
1E-117
EXAM
1E-118
EXAM
1E-119
EXAM
1E-120
STAIRS
SWC
TOILET
1E-123
CORRIDOR
C1-19
CORRIDOR
C1-17
EXAM 7
1E-128
TECHNICIAN 6
1E-129
EXAM 5
1E-130
EXAM 4
1E-131
EXAM 3
1E-132
PHYSICIAN
1E-136E
MANAGER
1E-136D
EXAM 2
1E-133
NURSE
1E-136F
OFFICE
1E-136C
EXAM
1E-164
EXAM
1E-163
EXAM
1E-165
EXAM
1E-166
EXAM
1E-167
EXAM
1E-168
ELECT. ROOM
1E-147
EXAM
1E-115
EXAM
1E-114
EXAM
1E-113
EXAM
1E-115A
STORAGE ROOM
1E-115B
STORAGE
1E-111A
ORTHOPEDIC CHECK-IN
1E-111
PROCEDURE ROOM
1E-109
EXAM
1E-109A
PRODECURE ROOM
1E-109
EXAM 1
1E-134
CORRIDOR
C1-20
WAITING AREA
1E-136
CORRIDOR
CDR
RECEPTION
1E-136G
EXAM
1E-149
EXAM
1E-151
OFFICE
1E-142
OFFICE
1E-143
LACTATION
1E-145
TRAVEL OFFICE
1E-146
TELE/DATA CLOSET
1E-172
ELEVATOR
ELEVATOR
AGENT CASHIER
1E-173
RELEASE OF INFORMATION
1E-174
STAIRS
SWD
SUPERVISOR
1E-170D
OFFICE
1E-170C
OFFICE
1E-170B
OFFICE
1E-170A
STEAM MECH ROOM
1E-171
STAIRS
SWF
TRAVEL AND ELEGEBILITY
1E-170
CHECK-IN
1E-170E
WAITING AREA
1E-135
KIOSKS
1E-169
TOILET
1E-104
EXAM ROOM
1E-105
EXAM ROOM
1E-106
ONCOLOGY CONSULT
1E-156
HAC
1E-157
EXAM
1E-110
PRE-OP CHECK-IN
1E-126
EXAM 8
1E-127
CORRIDOR
CC
WAITING AREA
C1-22
PATIENT SCREENING
C1-26
CORRIDOR
C1-25
CORRIDOR
C1-14
TELE CLO
1E-176
CORRIDOR
C1-24
CORRIDOR
C1-29
CORRIDOR
C1-15
CORRIDOR
C1-12
CORRIDOR
C1--11
CORRIDOR
C1-9
OUTPATIENT WAITING AREA 1
C1-13
EXAM 10
1E-125
OUTPATIENT WAITING AREA 2
C1-21
OFFICE
1G-133
COMM
1E-107A
ALCOVE
1E-146B
CORRIDOR
C1-7
ELEVATOR LOBBY
CORRIDOR
C1-31
TELE/CLO
1E-175
CORRIDOR
C1-19
200 Envoy Circle, Suite 201, Louisville, KY 40299 www.paradigmusa.com
BID DOCUMENTS
FOR CONSTRUCTION
FULLY SPRINKLERED
IMPROVE SUB-SPECIALTY
WAITING
AREA B310
552-19-103
03-20-2020
4100 W THIRD ST, DAYTON, OH 45428
DAYTON VA MEDICAL CENTER
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date
Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
Architecture Engineering Design-Build paradigm
U.S. Department of Veterans Affairs
FIRST FLOOR DEMOLITION PLAN
AD101
DML WOS
GENERAL DEMOLITION PLAN NOTES
N
NTS
KEY PLAN - FIRST FLOOR
DEMOLITION PLAN LEGEND
EXISTING PARTITION TO
REMAIN
EXISTING PARTITION TO BE
REMOVED
EXISTING DOOR & FRAME
TO REMAIN
EXISTING DOOR, FRAME &
PARTITION TO BE REMOVED
EXISTING DOOR & FRAME
TO BE REMOVED
EXISTING WINDOW TO REMAIN
EXISTING MILLWORK TO
REMAIN
EXISTING FIXTURES TO
REMAIN
AREA NOT IN CONTRACT
EXISTING MILLWORK TO BE
REMOVED
EXISTING FIXTURES TO BE
REMOVED
EXISTING WINDOW TO BE
REMOVED
DESCRIPTIVE NOTE FOR
AREA TO BE REMOVED
DEMOLITION PLAN NOTES
1. REMOVE EXISTING VINYL COMPOSITION TILE FLOORING, VINYL BASE AND
ADHESIVE TO BARE SUBSTRATE. PREP FOR NEW FLOOR FINISH. REFER
TO INTERIOR FINISHES SCHEDULE FOR MORE INFORMATION.
2. REMOVE SECTION OF PLASTER AND/OR GYPSUM PARTITION AS REQUIRED
FOR NEW WORK. REMOVAL OF SUCH PARTITION REQUIRES THAT ITEMS
SUCH AS CONDUIT, OUTLETS, RAILING, WALL BASES, PIPING, ETC ARE TO
BE REMOVED AND REROUTED. REFER TO MEP DRAWINGS FOR
ADDITIONAL INFORMATION. COORDINATE WITH NEW CONSTRUCTION.
3. REMOVE EXISTING PLUMBING FIXTURES AND RELATED ACCESSORIES
COMPLETE. COORDINATE WITH PLUMBING DRAWINGS.
4. REMOVE EXISTING DOOR, FRAME AND RELATED HARDWARE IN IT'S
ENTIRETY.
5. REMOVE EXISTING CASEWORK (UPPER AND/OR LOWER) IN ITS ENTIRETY,
INCLUDING, BUT NOT LIMITED TO ALL ACCESSORIES AND PLUMBING.
REFER TO PLUMBING DRAWINGS FOR ADDITIONAL INFORMATION.
6. REMOVE EXISTING STORAGE CABINET OR LOCKERS IN THEIR ENTIRETY.
7. REMOVE EXISTING ACOUSTICAL CEILING SYSTEM IN ITS ENTIRETY.
A. SCOPE OF WORK INCLUDES THE CUTTING, PATCHING AND INTERIOR FINISH
REPLACEMENT REQUIRED TO ACCOMMODATE THE ADDITION OF NEW
PLUMBING WORK INDICATED BY (PRIMARILY) PLUMBING PLANS.
B. CONTRACTOR SHALL COORDINATE DEMOLITION WORK WITH ALL TRADES,
FOR ITEMS SHOWN TO BE REMOVED ON THIS PLAN. GENERAL
CONTRACTOR SHALL ALSO COORDINATE WITH ALL TRADES, THE REMOVAL
REINSTALLATION, AND/OR REWORKING OF THE EXISTING FINISHES AS
REQUIRED FOR THE ROUTING OF EXISTING/NEW SERVICES INTO THE
PROJECT AREA.
C. COORDINATE WORK WITH MECHANICAL, ELECTRICAL AND PLUMBING (M.E.P.)
CONSTRUCTION DOCUMENTS AND THEIR RESPECTIVE TRADES.
D. PRIOR TO THE START OF DEMOLITION, CONTRACTOR SHALL WALK TO
SPACE WITH THE C.O.R. TO IDENTIFY ANY ITEMS TO BE TURNED OVER TO
THE GOVERNMENT.
E. PROVIDE 2 HR. FIRE STOPPING WHEREVER NEW PIPING, CONDUIT, TUBING,
CABLE OR DUCTWORK PENETRATES EXISTING FLOOR CONSTRUCTION
UNLESS PENETRATION IS FULLY ENCLOSED WITHIN UL APPROVED 2-HR.
RATED SHAFT CONSTRUCTION. (REFER TO SPECIFICATION SECTION 07 84
00; FIRE STOPPING.)
F. ALL WORK IN CORRIDORS OF GROUND AND FIRST FLOOR LEVELS WILL BE
ALLOWED ONLY DURING WEEKENDS OR AFTER NORMAL VAMC HOURS OF
OPERATION. RETURN CORRIDOR CEILING FINISH TO SUBSTANTIALLY
ORIGINAL CONDITION PRIOR TO BEGINNING OF WORK WEEK OR BEGINNING
OF NORMAL WORK HOURS FOR VAMC.
G. CONTRACTOR SHALL THOROUGHLY CLEAN ALL WORK AREAS BEFORE
TURNING SITE OVER TO VAMC FOLLOWING CONTRACTOR'S PERFORMANCE
OF 'OFF-HOURS' WORK.
H. WORK SCHEDULE WITHIN EXISTING ROOMS SHALL BE SCHEDULED AND
COORDINATED WITH THE VAMC COR.
I. WHERE CUTTING AND PATCHING EXISTING CEILING SYSTEMS IS REQUIRED:
I.A. TEMPORARILY SUSPEND ALL ELECTRICAL LIGHTING FIXTURES,
ELECTRICAL DEVICES, MECHANICAL DIFFUSERS AND OTHER CEILING
MOUNTED SYSTEMS.
I.B. ONCE EXISTING CEILING SYSTEM IS REPLACED - OR NEW SYSTEM IS
INSTALLED - RE-INSTALL EXISTING CEILING MOUNTED DEVICES TO
MATCH ORIGINAL ASSEMBLY.
J. CONTRACTOR IS STRONGLY ENCOURAGED TO VERIFY IN FIELD THE EXISTING
CEILING SYSTEM TYPE LOCATED IN EACH AREA SHOWN FOR NEW WORK.
MATCH ANY NEW REPLACEMENT FINISHES TO EXISTING FINISHES.
K. WHERE ROOMS ARE INDICATED TO HAVE THE ENTIRE CEILING SYSTEM
REMOVED FOR INSTALLATION OF NEW WORK - CONTRACTOR TO INSTALL
NEW CEILING SYSTEM MATCHING EXISTING AT COMPLETION OF M.E.P.
WORK. (REFER TO SPECIFICATION SECTION 09 51 00.)
L. REMOVE ALL WALL MOUNTED ACCESSORIES, WALL PROTECTION, INCLUDING
BUT NOT LIMITED TO WALL MOUNTED HAND SANITIZER DISPENSERS,
BOX DISPENSERS SHARPS CONTAINERS, PAPER TOWEL HOLDERS, GRAB BARS,
SOAP DISPENSERS, ETC IN THEIR ENTIRETY. TURN OVER TO VA.
M. REMOVE ALL WALL PAPER AND WALL PROTECTION AS NECESSARY.
N. ANY ITEMS DAMAGED BY THE CONTRACTOR OR BY PERSONS UNDER THE
SUPERVISION OF THE CONTRACTOR THAT ARE NOT INDICATED TO BE
REMOVED OR DEMOLISHED SHALL BE REPAIRED/REPLACED TO LIKE NEW
CONDITION AT THE CONTRACTORS EXPENSE.
O. CONTRACTOR SHALL MAINTAIN THE EXISTING BUILDING IN A WATERTIGHT
STATE THROUGHOUT CONSTRUCTION. ANY DAMAGE CAUSED BY THE
CONTRACTOR SHALL BE REPAIRED TO BE LIKE NEW AND SHALL MATCH
NEW CONSTRUCTION.
P. CONTRACTOR SHALL MAINTAIN A FULLY SEALED ENTRY POINTS TO THE
ROOMS AND/OR AREAS BEING RENOVATED. ROOMS MUST BE SEALED TO
PREVENT THE TRANSFER OF DUST AND DEBRIS TO ADJACENT SPACES.
Q. EXISTING SPRINKLER SYSTEM SHALL REMAIN LIVE AND FUNCTIONAL DURING
ALL PHASES OF CONSTRUCTION. CONTRACTOR SHALL TAKE GREAT CARE
TO NOT DAMAGE ANY EXISTING HEADS OR PIPING, UNLESS OTHERWISE
INDICATED ON FIRE PROTECTION DRAWINGS.
R. WORK THAT GENERATES LEVELS OF NOISE OR VIBRATION THAT IS
DISRUPTIVE TO PATIENTS, VISITORS, AND/OR STAFF WILL BE SCHEDULED
FOR OFF-SHIFTS AND/OR WEEKENDS.
2 HOUR FIRE RATED
PARTITION (90 MIN. DOOR)
8. EXISTING FINISHES TO REMAIN, PATCH AND REPAIR AS NECESSARY.
AREA OF FLOOR TO BE
REMOVED FOR TRENCH
DRAIN
9. REMOVE EXISTING DOORS AND FRAME, RETAIN FOR REINSTALLATION.
10. AREA OF SLAB EXCAVATION, CONTRACTOR SHALL COORDINATE NECESSARY
EXTENTS OF DEMOLITION WITH PD101 AND PP101.
11. REMOVE EXISTING WALL PROTECTION.
12. REMOVE DRYWALL AS NECESSARY TO PERMIT NEW PIPING, COORDINATE
WITH PD101 & PP101.
13. EXISTING 1500LB. SAFES. CONTRACTOR TO COORDINATE REMOVABLE &
RELOCATION W/ VAMC.
14. REMOVE & RETAIN EXISTING DOOR, FRAME & HARDWARE (INCLUDING
KEYPAD) FOR REINSTALLATION.
15. TEMPORARILY REMOVE CEILING TILIES TO ACCOMMODATE ABOVE CEILING
MECHANICAL WORK.
FIRST FLOOR DEMOLITION PLAN
1/4'' = 1'-0''
F1
| Sheets and Views |
| AD101 |
File details come from the government source that posted it. Updated .