G E N E R A L N O T E S
O
N
M
L
K
K.1
7 8 9 10 11 12 13 14
P
7' - 8"
7' - 11"
8' - 0"
8' - 0"
TYP.
LOGISTICS
CLEAN SUPPLY
STORAGE
A-019b
INSTRUMENT
PREP ROOM
B-039
BREAK ROOM
B-040
SPD OFFICE
B-039a
WOMEN'S
SHOWER
B-041
MEN'S SHOWER
B-042
DECONTAMINATION
ROOM
A-018
CART WASH
A-018bEQUIP
A-019a
MATERIAL
MANAGEMENT
STORAGE
A-019
5' - 10 1/4"
/4
3' - 9 1/2" 6' - 0" 6' - 0" 6' - 0"
3' - 6"
TYP.
8' - 0"5' - 8" 6' - 5" 6' - 2" 2' - 4"
/4
/4
TYP.
/2
6' - 2 1/4"
2' - 2"
BREAKDOWN
AREA
A023C
WAREHOUSE
A023
8' - 0"
OFFICE
A023B
8' - 0"
INCOMING
INSPECTION
OFFICE
A023D
/2
/2
8' - 0"
AE202
AE202
Sim
16"
8" 8" 8"
8"
8"
8"
8"
8"
8"
16"
24"
24"
24"
12"
16"
24"
24"
VESTIBULE
B039
8' - 0"
8' - 0"
EQEQ
8' - 0"
8' - 0"
24"
24"
8"
16"
16"
CL
CL
C L C L
C L
CLCLCL CL
8"
7' - 3"
7' - 3"
7' - 3"
7' - 8"
STERILIZERS
B-039c
CL
CL CL
7' - 3"
8' - 0"
4' - 1 1/4"
8' - 7" 3' - 9"
/4
16"
24"
16"
24"
3' - 4"
CART WASH
CORRIDOR
A-018C
PHASE II
2' X 4' LIGHT FIXTURE.
ACCESS PANEL
GYPSUM BOARD CEILING
ACOUSTIC TILE CEILING
HVAC SUPPLY
HVAC RETURN
2' X 4' EMERGENCY LIGHT FIXTURE.
EXIT SIGN
LINEAR SLOT DIFFUSER
EXHAUST GRILLE
EXHAUST GRILLE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% BID DOCUMENTS
ROBLEY
REX
VA MEDICAL
CENTER
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
603-20-201
800 Zorn Ave., Louisville, KY
REPLACE SPS AIR HANDLER
ARCHITECT/ENGINEER OF RECORDCONSULTANT
C U s e rs
\c ra ig \D o c u m e n ts
\F F
E
L o u is v ill e
R e p la c e S
P S
A H
U c ra ig .l ie g ib e l@ ff e -s e rv
.c o m
.r v t
/2
/2
:4
:4
A
M
AE141
REFLECTED CEILING PLAN
06/29/2021 PQ DB
1/4" = 1'-0"
BASEMENT - REFLECTED CEILING PLAN
K E Y N O T E S
1 NEW GYPSUM BOARD CEILING WITH RES-W FINISH.
2 ACOUSTIC CEILING TILE SYSTEM.
3 NEW ACCESS PANEL IN GYP. BD. CEILING.
4 AIR LOCK AND LINEAR DIFFUSER
5 GYPSUM BOARD CONTROL JOINT
6 REINSTALL SUPPORT POLES, ESCUTCHEON PLATE, AND ELECTRICAL
OUTLETS IN PREVIOUS LOCATIONS. REFER TO ELECTRICAL DRAWINGS.
7 NEW WALL TO STRUCTURE CONSTRUCTED OF 3 5/8" METAL STUD WITH
ONE LAYER OF 5/8" GYPSUM BOARD ON EACH SIDE. PATCH AND REPAIR
ADJACENT WALLS AT INTERSECTION OF NEW CONSTRUCTION
INCLUDING FLOORS AND WALLS. PROVIDE RUBBER BASE (RB-1) TO
MATCH ADJACENT WALL CONSTRUCTION. PAINT NEW WALLS WITH
RES-W.
8 PROTECT EXISTING CORNER GUARDS. LOCATE WALL ADJACENT TO
EXISTING CORNER GUARD. VERIFY DIMENSION IN FIELD.
9 PROVIDE PREFABRICATED TEMPORARY CONSTRUCTION SMOKE
PARTITION WALL TO TERMINATE AT EXISTING CEILING - EXISTING
CEILING SHALL REMAIN - SEE ICRA REQUIREMENTS IN SPECIFICATIONS
FOR INSTRUCTIONS AT PARTITION AND DOOR - REMOVE AT
COMPLETION OF WORK - IF ADJACENT SURFACES ARE DISTURBED,
CONTRACTOR SHALL PATCH AND REPAIR TO MATCH EXISTING.
10 PATCH CEILING AS REQUIRED FROM INSTALLATION OF NEW
DIFFUSERS.
LEGEND
N.T.S.Scale:
KEY PLAN
A. PROVIDE 8" ACCESS PANELS AT ALL DAMPERS AND PIPING VALVES LOCATED
ABOVE CEILING.
B. ACCESS PANELS SHALL BE INSTALLED AT ALL VAV BOXES, TURNING VANES AT
EXHAUST, DAMPERS AND VALVES. VERIFY LOCATION OF DAMPERS, TURNING
VANES IN FIELD, AND INSTALL ACCESS PANELS AS REQUIRED.
C. MAINTAIN 4" GYPSUM BOARD CLEARANCE GAP BETWEEN CEILING FIXTURES.
D. PAINT ALL NEW GYPSUM BOARD CEILINGS WHITE TO MATCH WALL COLOR. USE
RES-W PER SPECIFICATION.
E. NEW CEILING HEIGHTS SHALL BE AT LOCATION OF EXISTING CEILING HEIGHTS.
VERIFY IN FIELD. ALL CEILING HEIGHT TAGS ARE APPROXIMATE. SEE NOTES FOR
VARIATIONS AT BULKHEADS AND SOFFITS.
1616637 Exp:12/31/2021
PATRICK R. QUINN
Revisions: Date:
100% BID DOCUMENTS 07/13/2021
ADDENDUM #1 09/20/2021
| Sheets |
| AD141 - DEMOLITON REFLECTED CEILING PLAN |
| AE101 - BASEMENT FLOOR PLAN |
| AE141 - REFLECTED CEILING PLAN |
| AE501 - PLAN DETAILS, DOOR SCHEDULE, AND FINISH LEGEND |