This presolicitation notice announces a requirement for construction services for Project #614-17-112 to renovate Building 1 Clinical Lab at the Memphis VA Medical Center. The project includes general hospital construction, plumbing, mechanical, electrical work, and exterior improvements. The estimate range is $5-10 million. The procurement will use FAR Part 15 for a lowest price technically acceptable source selection. Evaluation factors will be provided in the solicitation releasing on or by November 6, 2019. This is a 100% set-aside for service-disabled veteran-owned small businesses. Offerors must be listed in the CVE database and SAM. The awarded contractor must submit VETS-4212 enrollment. The contracting officer will determine responsibility prior to award. Questions must be submitted in writing to the identified contracting officer by the specified date.

36C24920R0008 0002 17.1044_2019.04.26_Bid Set_SpecsVol1.pdf

View the file

Other files

File Type Posted
36C24920R0008-0009005.docx DOCX document
36C24920R0008-0008000.docx DOCX document
36C24920R0008-0008003.pdf PDF
36C24920R0008-0008001.pdf PDF
36C24920R0008-0008002.pdf PDF
36C24920R0008-0007000.docx DOCX document
36C24920R0008-0006004.pdf PDF
36C24920R0008-0006007.pdf PDF
36C24920R0008-0006005.pdf PDF
36C24920R0008-0006011.pdf PDF
36C24920R0008-0006006.pdf PDF
36C24920R0008-0006001.pdf PDF
36C24920R0008-0006000.docx DOCX document
36C24920R0008-0006010.pdf PDF
36C24920R0008-0006012.pdf PDF
36C24920R0008-0006008.pdf PDF
36C24920R0008-0006002.pdf PDF
36C24920R0008-0006009.pdf PDF
36C24920R0008-0006003.pdf PDF
36C24920R0008-0005000.docx DOCX document
36C24920R0008-0004000.docx DOCX document
36C24920R0008-0004001.pdf PDF
36C24920R0008-0004002.pdf PDF
36C24920R0008-0003000.docx DOCX document
36C24920R0008-0003001.pdf PDF
36C24920R0008-0002006.pdf PDF
36C24920R0008-0002005.pdf PDF
36C24920R0008-0002008.pdf PDF
36C24920R0008-0002001.txt TXT text file
36C24920R0008-0002004.pdf PDF
36C24920R0008-0002000.docx DOCX document
36C24920R0008-0002007.pdf PDF
36C24920R0008-0002002.pdf PDF
36C24920R0008-0001000.docx DOCX document
36C24920R0008-011.pdf PDF
36C24920R0008-007.pdf PDF
36C24920R0008-003.pdf PDF
36C24920R0008-004.pdf PDF
36C24920R0008-010.xlsx XLSX spreadsheet
36C24920R0008-009.xlsx XLSX spreadsheet
36C24920R0008-005.pdf PDF
36C24920R0008-006.pdf PDF
36C24920R0008-012.pdf PDF
36C24920R0008-001.docx DOCX document
36C24920R0008-008.pdf PDF
36C24920R0008-002.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renovate Building 1 Clinical Lab

Memphis VAMC, TN

VA Contract No.: VA249-17-C-0236

Project # 614-17-112

For the

Department of Veterans Affairs

Network Contracting Office 9

1639 Medical Center Parkway

Suite 400

Murfreesboro, TN 37129

Project Manual Volume 1 (1 of 2): Divisions 00-14

BID DOCUMENTS

04/26/2019

GUIDON DESIGN INC.

Project Contacts:

OWNER: MEMPHIS VA MEDICAL CENTER

Attn: Leland Fong

1030 Jefferson Avenue

Memphis, TN 38104

Phone: 901-523-8990 x 15023

Email: Leland.Fong@va.gov

ARCHITECT: GUIDON DESIGN INC.

Attn: Andrew Schaewe, AIA

905 N. Capitol Ave., Suite 100

Indianapolis, Indiana 46204

Phone: 317-800-6388 x ___

Email: aschaewe@guidondesign.com

M/E/P ENGINEER: CMTA CONSULTING ENGINEERS, INC

Andrew J. Myers, PE, LEED AP, CxA

10411 Meeting Street

Prospect, KY 40059

Phone: 502-326-3085

Email: amyers@cmtaegrs.com

ISSUE DATE: April 26, 2019

Department of Veterans Affairs

Network Contracting Office 9

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-17

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

DIVISION 00 - SPECIAL SECTIONS DATE

00 01 15 List of Drawing Sheets 07-15

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 10-17

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-13

01 33 23 Shop Drawings, Product Data, and Samples 05-17

01 35 26 Safety Requirements 02-17

01 42 19 Reference Standards 05-16

01 45 00 Quality Control 01-18

01 57 19 Temporary Environmental Controls 01-11

01 58 16 Temporary Interior Signage 07-15

01 74 19 Construction Waste Management 09-13

01 81 13 Sustainable Construction Requirements 10-17

01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

02 82 11 Traditional Asbestos Abatement 09-15

02 83 33.13 Lead-Based Paint Removal and Disposal 08-16

02 84 16 Handling of Lighting Ballasts and Lamps Containing PCBs and Mercury

12-17

DIVISION 05 – METALS

05 50 00 Metal Fabrications 07-14

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

06 20 00 Finish Carpentry 08-16

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 01 50.19 Preparation for Re-Roofing 02-16

07 72 00 Roof Accessories 10-15

07 84 00 Firestopping 02-16

07 92 00 Joint Sealants 10-17

07 95 13 Expansion Joint Cover Assemblies 02-16

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-17

00 01 10-2

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 08-16

08 14 00 Interior Wood Doors 02-16

08 31 13 Access Doors and Frames 02-16

08 41 13 Aluminum-Framed Entrances and Storefronts 08-16

08 71 00 Door Hardware 01-16

08 71 13.11 Low Energy Power Assist Door Operators 08-16

08 80 00 Glazing 10-15

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 02-15

09 06 00 Schedule for Finishes 04-15

09 22 16 Non-Structural Metal Framing 05-16

09 29 00 Gypsum Board 11-14

09 30 13 Ceramic/Porcelain Tiling 09-15

09 51 00 Acoustical Ceilings 12-16

09 65 13 Resilient Base and Accessories 02-16

09 65 16 Resilient Sheet Flooring 02-16

09 65 19 Resilient Tile Flooring 12-15

09 68 00 Carpeting 10-15

09 91 00 Painting 01-16

DIVISION 10 – SPECIALTIES

10 11 13 Chalkboards and Markerboards 10-15

10 11 23 Tackboards 10-15

10 14 00 Signage 10-15

10 21 13 Toilet Compartments 12-15

10 21 23 Cubicle Curtain Tracks 05-15

10 26 00 Wall and Door Protection 10-15

10 28 00 Toilet, Bath, and Laundry Accessories 02-16

10 44 13 Fire Extinguisher Cabinets 08-14

DIVISION 11 – EQUIPMENT

11 26 00 Unit Kitchens 11-11

11 41 21 Walk-In Coolers and Freezers 05-15

DIVISION 12 – FURNISHINGS

12 24 00 Window Shades 08-17

12 24 21 Lightproof Shades 05-15

12 31 00 Manufactured Metal Casework 05-15

12 32 00 Manufactured Wood Casework 09-15

12 36 00 Countertops 12-15

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural 01-14

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-17

00 01 10-3

Components

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16

22 05 12 General Motor Requirements for Plumbing Equipment 09-15

22 05 23 General-Duty Valves for Plumbing Piping 09-15

22 07 11 Plumbing Insulation 09-15

22 08 00 Commissioning of Plumbing Systems 11-16

22 11 00 Facility Water Distribution 09-15

22 13 00 Facility Sanitary and Vent Piping 09-15

22 14 00 Facility Storm Drainage 09-15

22 40 00 Plumbing Fixtures 09-15

22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 08-17

23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment

08-17

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment

02-15

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15

23 07 11 HVAC and Boiler Plant Insulation 02-15

23 08 00 Commissioning of HVAC Systems 11-16

23 09 23 Direct-Digital Control System for HVAC 09-11

23 21 13 Hydronic Piping 08-17

23 21 23 Hydronic Pumps 08-17

23 22 13 Steam and Condensate Heating Piping 08-17

23 23 00 Refrigerant Piping 02-15

23 25 00 HVAC Water Treatment 02-15

23 31 00 HVAC Ducts and Casings 03-13

23 34 00 HVAC Fans 02-15

23 36 00 Air Terminal Units 02-15

23 37 00 Air Outlets and Inlets 02-15

23 40 00 HVAC Air Cleaning Devices 02-12

23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 04-11

23 82 16 Air Coils 04-11

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17

26 05 26 Grounding and Bonding for Electrical Systems 01-17

26 05 33 Raceway and Boxes for Electrical Systems 05-14

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-17

00 01 10-4

26 05 41 Underground Electrical Construction 01-17

26 05 73 Overcurrent Protective Device Coordination Study 12-15

26 08 00 Commissioning of Electrical Systems 11-16

26 09 23 Lighting Controls 05-14

26 22 00 Low-Voltage Transformers 12-15

26 24 16 Panelboards 05-14

26 27 26 Wiring Devices 01-16

26 29 11 Motor Controllers 08-14

26 29 21 Enclosed Switches and Circuit Breakers 01-17

26 36 23 Automatic Transfer Switches 01-17

26 51 00 Interior Lighting 08-14

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 06-15

27 05 26 Grounding and Bonding for Communications Systems 06-15

27 05 33 Raceways and Boxes for Communications Systems 06-15

27 08 00 Commissioning of Communications Systems 11-16

27 10 00 Control, Communication and Signal Wiring 06-15

27 11 00 Communications Equipment Room Fittings 06-15

27 51 23 Intercommunications and Program Systems 06-15

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16

28 13 00 Physical Access Control System 10-11

28 23 00 Video Surveillance 09-11

28 31 00 Fire Detection and Alarm 10-11

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

07-01-15

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

GI000 COVER SHEET

GI101 LIFE SAFETY PLAN

GI102 INFECTION CONTROL/PHASING PLAN

GI103 BID ALTERNATES

HA101 HAZARDOUS MATERIAL REMOVAL PLAN

ARCHITECTURAL

AS001 ARCHITECTURAL ABBREVIATIONS AND GENERAL NOTES

AS002 ARCHITECTURAL SYMBOLS AND WALL TYPES

AD101 FIRST FLOOR DEMOLITION PLAN

AS101 FIRST FLOOR ARCHITECTURAL PLAN

AS102 FIRST FLOOR DIMENSION PLAN

AS103 SECOND FLOOR ARCHITECTURAL PLAN

AS104 SECOND FLOOR ROOF PLAN

AS111 FIRST FLOOR REFLECTED CEILING PLAN

AS401 ENLARGED PLANS

AS501 DETAILS

AS502 CASEWORK SECTIONS AND DETAILS

AS601 DOOR & WINDOW SCHEDULE

AS801 INTERIOR ELEVATIONS

AS802 CASEWORK ELEVATIONS

AS901 SIGNAGE PLAN

AS902 SIGNAGE TYPES

AF101 FIRST FLOOR WALL FINISH PLAN

AF102 FIRST FLOOR - FLOOR FINISH PLAN

AF601 FINISHES AND EQUIPMENT SCHEDULE

AQ101 EQUIPMENT FLOOR PLAN

AQ401 ENLARGED EQUIPMENT PLAN

AQ801 EQUIPMENT CASEWORK ELEVATIONS

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

07-01-15

00 01 15 - 2

AQ802 EQUIPMENT CASEWORK ELEVATIONS

HEATING, VENTILATING, & AIR CONDITIONING (HVAC)

ML100 MECHANICAL LEGEND AND GENERAL NOTES

MD100 PARTIAL GROUND FLOOR PLAN - MECHANICAL

DEMOLITION

MD101 PARTIAL FIRST FLOOR PLAN - AIR DISTRIBUTION

DEMOLITION

MD102 PARTIAL FIRST FLOOR PLAN - HYDRONICS DEMOLITION

MH100 PARTIAL GROUND FLOOR PLAN - MECHANICAL

MH101 PARTIAL FIRST FLOOR PLAN - AIR DISTRIBUTION

MH102 PARTIAL SECOND FLOOR PLAN - MECHANICAL

MH103 PARTIAL ROOF PLAN - MECHANICAL

MH104 PARTIAL ROOF PLAN - MECHANICAL

MP101 PARTIAL FIRST FLOOR PLAN - HYDRONICS

MP102 PARTIAL FLOOR PLAN - HYDRONICS

MP103 PARTIAL SECOND FLOOR PLAN - HYDRONICS

MH105 MECHANICAL SECTIONS

MH106 MECHANICAL SECTIONS

MH200 MECHANICAL DETAILS

MH201 MECHANICAL DETAILS

MH202 MECHANICAL DETAILS

MH203 MECHANICAL DETAILS

MH204 MECHANICAL DETAILS

MH205 MECHANICAL DETAILS

MS100 MECHANICAL SCHEDULES

MS101 MECHANICAL SCHEDULES

ELECTRICAL

ES101 ELECTRICAL LEGEND

ED101 PARTIAL FIRST FLOOR PLAN - ELECTRICAL

DEMOLITION

ES201 PARTIAL FIRST FLOOR PLAN - LIGHTING

ES301 PARTIAL FIRST FLOOR PLAN - POWER

ES302 PARTIAL ROOF PLAN - ELECTRICAL

ES401 PARTIAL FIRST FLOOR PLAN - SYSTEMS

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

07-01-15

00 01 15 - 3

ES500 PARTIAL GROUND FLOOR PLAN - ELECTRICAL

INTERCONNECTIONS

ES501 PARTIAL FIRST FLOOR PLAN - ELECTRICAL

INTERCONNECTIONS

ES502 PARTIAL SECOND FLOOR PLAN - ELECTRICAL

INTERCONNECTIONS

ES601 POWER DISTRIBUTION RISER DIAGRAM AND DETAILS

ES701 LIGHT FIXTURE SCHEDULE AND DETAILS

ES702 PANELBOARD SCHEDULES

ES703 PANELBOARD SCHEDULES

ES704 PANELBOARD SCHEDULES

ES801 TELECOMMUNICATION DETAILS

ES802 ELECTRICAL DETAILS

ES803 ELECTRICAL DETAILS

FIRE PROTECTION

FX101 FIRE PROTECTION NOTES & DETAILS

FX102 FIRST FLOOR - FIRE PROTECTION PLAN

PLUMBING

PL101 PLUMBING LEGEND, SCHEDULES & DETAILS

PD101 GROUND FLOOR - PLUMBING DEMOLITION PLAN

PD102 FIRST FLOOR - PLUMBING DEMOLITION PLAN

PP101 GROUND FLOOR - PLUMBING PLAN

PP102 FIRST FLOOR - PLUMBING PLAN

PP201 WASTE & VENT RISER DIAGRAM

- - - END - - -

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15 i

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 SAFETY REQUIREMENTS

1.2 GENERAL INTENTION

1.3 STATEMENT OF BID ITEM(S)

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.5 CONSTRUCTION SECURITY REQUIREMENTS

1.6 OPERATIONS AND STORAGE AREAS

1.7 ALTERATIONS

1.8 DISPOSAL AND RETENTION

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

1.10 RESTORATION

1.11 PHYSICAL DATA

1.12 PROFESSIONAL SURVEYING SERVICES

1.13 LAYOUT OF WORK

1.14 AS-BUILT DRAWINGS

1.15 USE OF ROADWAYS

1.16 CONTRACTORS FIELD OFFICE

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.18 TEMPORARY USE OF EXISTING ELEVATORS

1.19 TEMPORARY TOILETS

1.20 AVAILABILITY AND USE OF UTILITY SERVICES

1.21 NEW TELEPHONE EQUIPMENT

1.22 TESTS

1.23 INSTRUCTIONS

1.24 GOVERNMENT-FURNISHED PROPERTY

1.25 RELOCATED EQUIPMENT ITEMS

1.26 CONSTRUCTION SIGN

1.27 SAFETY SIGN

1.28 PHOTOGRAPHIC DOCUMENTATION

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the expansion of Building 1

First Floor Clinical Lab Construction as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the

Medical Center Engineering Officer, COR.

C. Offices of Guidon Design, Inc, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -2

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: 1. Work includes general construction for the renovation of Building 1 existing space into a clinical lab space for the VA. Modifications will include complete demolition and reconstruction of the interior walls within the project boundaries.

There will be the addition of new finishes, equipment, built in refrigerators and freezers, and casework within the space. There will be new compressors and an new air handling unit located on the roof of the existing facility. All structural, mechanical, electrical, plumbing and fire protection work will be to modify any and all exiting systems to facilitate the new design.

B. ALTERNATE NO. A: Omit scientific systems casework to be purchase and installed by contractor from the project bid.

ALTERNATE NO. B: Omit built in place walk in refrigerator and freezers to be purchased and installed by the contractor from the project bid.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -3

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer.

4. VA reserves the right to close or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting Officers Representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71

00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -4

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2 to 5) permits shall be issued for General

Contractor and its employees for parking in designated areas only.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -5

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workmen are subject to rules of Medical Center applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -6 by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of

Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

G. Phasing:

The Medical Center must maintain its operation 24 hours a day, seven days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to insure accomplishment of this work in successive phases mutually agreeable to

Medical Center Director, COR and Contractor, as follows:

Phase I: Submission of submittals to VA and architect/engineer for review and approval.

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -7

Phase II:

H. Building(s) No.(s) 1 will be occupied during performance of work, but immediate areas of alterations will be vacated for renovation work.

Refer to drawings for locations, and further phasing instructions to be outlined in general contractor’s phasing schedule. Dates for areas to be vacated to be approved by stake holders and COR.

1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.

Coordinate alteration work in areas occupied by Department of

Veterans Affairs so that Medical Center operations will continue during the construction period.

I. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.

Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm

(one inch) above grade. Remove the fence when directed by COR.

J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

Comment [AS1]: ASK CMTA IF THIS IS

APPROPRIATE

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -8

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

K. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR

COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR

ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to

COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -9

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

M. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -10

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur, and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative , to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by

Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE

CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR

852.236-88).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -11 and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of

Contractor to restore damage caused by Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled, and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR .

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -12

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the

Contractor fails or refuses to repair the damage promptly, the

Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

(FAR 52.236-9)

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -13

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

COR . Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR

52.236-2).

1.11 PHYSICAL DATA

A. Data and information furnished or referred to below is for the

Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -14

1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations completed in the Expand Building 1 Lower Level SPD.

(FAR 52.236-4)

B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically on drawings.

C. A copy of the soil report will be made available for inspection by bidders upon request to the Engineering Officer at the VA Medical

Center, and shall be considered part of the contract documents.

D. Government does not guarantee that other materials will not be encountered, nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of

Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.

1.12 PROFESSIONAL SURVEYING SERVICES

A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.

The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.13 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The

Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -15 for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.

If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

(FAR 52.236-17)

B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, parking lots, are in accordance with lines and elevations shown on contract drawings.

C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, and center lines of columns in both directions, major utilities and elevations of floor slabs:

1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.

D. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings.

Furnish such certification to the COR before any major items of

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -16 concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.

1. Lines of each building and/or addition.

2. Elevations of bottoms of footings and tops of floors of each building and/or addition.

3. Lines and elevations of sewers and of all outside distribution systems.

4. Lines of elevations of all swales and interment areas.

5. Lines and elevations of roads, streets and parking lots.

E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.

F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of

Article "Professional Surveying Services".

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -17

1.15 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed, and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.

C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.

1.16 CONTRACTORS FIELD OFFICE

A. The Contractor may, within fifteen (15) days after receipt of Notice to

Proceed, provide where shown on the drawings a temporary field office, furniture, and two-inch-deep gravel surfaced area for use by the general contractor.

B. The field office shall provide not less than 67 square meters (720 gross square feet) of floor area in one unit. Installation of the office shall meet all local codes.

C. Provide office with two, 900 mm (three foot) wide exterior doors, including hardware and OSHA approved platform and stairs leading to grade.

D. Enclose the entire perimeter of the office from the floor to the ground and finish to match exterior. Provide R7 insulation and seal tight to ground with a painted 19 mm (3/4 inch) exterior grade plywood skirt.

E. Exterior finishes shall be manufacturer's standards.

F. Provide floor, wall, and roof with not less than R5 insulation.

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -18

G. Interior finishes shall consist of resilient flooring, plywood paneling or painted wallboard on walls, and acoustical tile ceilings. Interior doors may be either painted or stained.

H. Provide 750 mm (2-1/2 feet) wide by 900 mm (3 feet) high operable windows; two in each room (none required in sample room), except provide only one 600 mm (2 foot) high window in toilet room(s). Window openings shall be fitted with security bars to prevent any forced entry. The doors of field office shall have a hasp and padlock and also deadbolts keyed from both sides.

I. Provide sufficient fluorescent lighting in each room to deliver 750 lux

(70 foot-candles) of light at desk top height without the aid of daylight. Provide one light switch in each room.

J. Provide one duplex receptacle in each wall of each room. If a wall is

3.0 m (10 feet) long or more, provide two receptacles for each 3.0 m

(10 feet), or portion thereof, of wall. Provide two duplex receptacles in low partition at secretary's desk.

K. The Contractor may provide the following:

1. Electricity, hot and cold water, and necessary utility services

(except telephone).

2. All necessary piping, power circuits network cabling, cat 5e or better cabling for phones and computers, electrical fixtures, lighting, and other items necessary to provide a habitable structure for the purpose intended. The number of network and electrical receptacles will be as per attached drawing of the field office.

3. Thermostatically controlled, centralized heating and air conditioning system designed to maintain the temperature between 21 and 27 degrees C (70 and 80 degrees F) with 50 percent relative humidity maintained during the air conditioning season.

4. One water closet, lavatory, mirror, toilet paper dispenser, paper towel dispenser, soap dispenser, towel bar, and two-prong coat hooks for each toilet room.

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -19

M. At the completion of all work, including the punch list, the Contractor shall remove same, including utility connections, from the Medical

Center. The site shall be restored to original condition and finished in accordance with contract requirements.

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the

COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.

Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014

Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned.

Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be

VA: 61417-112 Renovate Building 1 Clinical Lab

Memphis VAMC, Memphis Tn.

04.26.2019

Bid Documents

11-01-15

01 00 00 -20 replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

C. This paragraph shall not reduce the requirements of the mechanical and electrical…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .