This solicitation is for design-build services to renovate the fire alarm system at the James A. Haley VA Medical Center in Tampa, Florida. The contractor will be required to provide all necessary professional services, equipment, labor, materials, and specialty services to upgrade 18 fire alarm nodes, update existing software in two nodes, replace six fire alarm panels, replace two TSW computers and graphics, determine which NAC extender panels will remain and update those that do, upgrade the campus main network communication loop to fiber optic, provide and install new smoke detectors in various buildings, and address any other issues found during the installation. The contractor must have a minimum of five years of experience working on fire alarm and related systems in healthcare, industrial, educational, or commercial facilities. The period of performance for design work is 155 days from notice to proceed, with construction to be completed within 205 days of the construction notice to proceed. The solicitation is set aside for verified Service-Disabled Veteran-Owned Small Businesses and responses are due by January 25, 2023.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24823R0036
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5.
REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE
DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL
SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
1. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than ____ ___________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24823R0036 X 673-22-107 36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) amy.shaw3@va.gov
Department of Veteran Affairs Network Contracting Office 8 (NCO 8) 8875 Hidden River, Suite 8 Tampa FL 33637 Amy Shaw 813-938-0528 Project Title: Renovate Fire Alarm System, James A. Haley VA Medical Center, Tampa, FL.
Project #: 673-22-107
IAW FAR 36.204 & VAAR 836.204 the VA's magnitude of this construction project is between $2,000,000.00 and $5,000,000.00 NAICS: 236220 - Commercial or Institutional Building Construction Product Service Code (PSC): 6350 - Miscellaneous Alarm, Signal, and Security Detection Systems This solicitation will be evaluat ed on a trade-off basis. As stated elsewhere in this solicitation, this procurement is a two (2) phase design/build IAW FAR 36.3. One solicitation will be issued covering both phases. In Phase I, proposals will be evaluated to determine which offerors will submit Phase II proposals. Block 13 A immediately below only refers to Phase One proposals.
This requirement is set-aside for VIP certified, Service-Disabled Veteran Owned Small Businesses (SDVOSB). Vendor verification for SDVOSB's can be found at https://www.vetbiz.va.gov. ANY PERSON OR ENTITY SUSPECTED OF MISREPRESENTATION FOR THE PURPOSE OF SECURING A GOVERNMENT CONTRACT MAY BE CRIMINALLY INVESTIGATED AND PROSECUTED FOR
FRAUD AGAINST THE UNITED STATES GOVERNMEN
T.
James A. Haley VAMC is a smoke free facility. Contractors, in order to enter the campus, you must have a pic ture ID.
All contractors are required to wear a face covering (per CDC guidelines) while on campus. All contractors will be screened at the entrance of the VA campus. A series of questions will be asked and temperatures taken. While working inside or outside the VAMC, the contractor will be responsible to wear a face covering at all times.
Personal Protective Equipment (PPE) is not provided.
Refer to solicitation instructions for Phase One cutoff date for submission and Request for Information (RFIs), or questions, if any. No site visit will be conducted during Phase One of this solicitation.
All offerors must comply with all solicitation terms and conditions (T&C's). Please refer to the instruction contained in RFP 36C24823R0036 for submission requirements.
Davis Bacon Wage Rate FL20220208 dated Sep 09, 2022 applies.
x x 52.211-10 X 16:00
EST
01-25-2023 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b.
SIGNATURE
20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to s ign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) 8875 Hidden River Pkwy Tampa FL 33637 Department of Veterans Affairs Financial Services Center P.O. Box 149971 Austin TX 78714-9971
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| A.3 PRICE/COST SCHEDULE | 6 |
| ITEM INFORMATION | 6 |
| A.4 DELIVERY SCHEDULE | 6 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 33 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 34 |
| 2.1 52.211-3 AVAILABILITY OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS (JUN 1988) | 34 |
| 2.2 52.216-1 TYPE OF CONTRACT (APR 1984) | 34 |
| 2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 34 |
| 2.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 35 |
| 2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 36 |
| 2.6 52.228-1 BID GUARANTEE (SEP 1996) | 37 |
| 2.7 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021) | 37 |
| 2.8 52.233-2 SERVICE OF PROTEST (SEP 2006) | 38 |
| 2.9 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 38 |
| 2.10 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 39 |
| 2.11 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 39 |
| 2.12 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 39 |
| 2.13 PARTNERING | 40 |
| REPRESENTATIONS AND CERTIFICATIONS | 41 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2022) (JUL 2020) (DEVIATION) | 41 |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 45 |
| 3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 47 |
| 3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021) | 49 |
| GENERAL CONDITIONS | 52 |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 52 |
| 4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (NOV 2021) | 52 |
| 4.3 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 53 |
| 4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 54 |
| 4.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (OCT 2022) | 54 |
| 4.6 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020) | 57 |
| 4.7 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) | 58 |
| 4.8 52.223-99 ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS (OCT 2021) (DEVIATION) | 59 |
| 4.9 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022) | 60 |
| 4.10 SUPPLEMENTAL INSURANCE REQUIREMENTS | 65 |
| 4.11 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 65 |
| 4.12 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020) | 66 |
| 4.13 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018) | 68 |
| 4.14 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION) | 69 |
| 4.15 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 71 |
| 4.16 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP 2021) (DEVIATION) | 71 |
| 4.17 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 73 |
| 4.18 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 74 |
| 4.19 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 75 |
| 4.20 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) ALTERNATE I (APR 2019) | 76 |
| 4.21 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 77 |
| 4.22 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 78 |
| 4.23 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 78 |
| 4.24 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 80 |
| 4.25 IT CONTRACT SECURITY | 80 |
| DESIGN BUILD SPECIFICATIONS | 91 |
| 4.26 GENDER | 91 |
| 4.27 CONTRACTOR'S COST BREAKDOWN | 91 |
| 4.28 SCHEDULE OF PAYMENTS FOR DESIGN SERVICES | 91 |
| 4.29 OWNERSHIP OF ORIGINAL DOCUMENTS | 91 |
| 4.30 RETENTION OF REVIEW DOCUMENTS | 91 |
| 4.31 CONTRACT DRAWINGS AND SPECIFICATIONS GOVERNMENT FURNISHED PLANNING INFORMATION | 92 |
| 4.32 COORDINATION WITH MEDICAL CENTER | 92 |
| 4.33 RESPONSIBILITY OF THE DESIGN-BUILD CONTRACTOR | 92 |
| ATTACHMENTS | 94 |
| ATTACHMENT 1 - RELEASE OF CLAIMS | 95 |
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
1.00
| __________________ |
| __________________ |
Furnish all necessary professional services, equipment, labor materials, supervision, tools, testing, and specialty services (i.e. Industrial Hygienist, Asbestos Contractor, etc.) to perform a design-build for the NRM Project #673-22-107, " Renovate Fire Alarm System " at the James A. Haley VA Hospital, located at 13000 Bruce B. Downs Boulevard, Tampa, Florida, 33612. The work includes, but is not limited to site investigation, design and preparation of drawings, phase planning, specifications, construction, and installation (of the fire alarm system) as designed in the hospital areas identified in the project description in this SOW.
Contract Period: Base POP Begin:
POP End:
PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: 6350 - Miscellaneous Alarm, Signal, and Security Detection Systems
| GRAND TOTAL |
| __________________ |
A.4 DELIVERY SCHEDULE
| ITEM NUMBER |
| QUANTITY |
| DELIVERY DATE |
| 0001 |
| SHIP TO: |
| James A. Haley VAMC |
13000 Bruce B Downs Tampa, FL 33612 4745
USA
| 1.00 |
| 360 Days from NTP |
| MARK FOR: |
| Paul Guerra |
813-972-2000 x5481 paul.guerra@va.gov
Page 1 of Page 1 of
STATEMENT OF WORK
Renovate Fire Alarm System
PROJECT #673-22-107
I. SCOPE OF WORK:
A. Furnish all necessary professional services, equipment, labor materials, supervision, tools, testing, and specialty services (i.e. Industrial Hygienist, Asbestos Contractor, etc.) to perform a design-build for the NRM Project #673-22-107, " Renovate Fire Alarm System " at the James A. Haley VA Hospital, located at 13000 Bruce B. Downs Boulevard, Tampa, Florida, 33612. The work includes, but is not limited to site investigation, design and preparation of drawings, phase planning, specifications, construction and installation (of the fire alarm system) as designed in the hospital areas identified in the project description in this SOW. The DB Team is to include subcontractors performing professional services under this contract, shall perform its services consistent with the professional skill and care ordinarily provided by architects/engineers practicing in the same or similar locality under the same or similar circumstances. The DB Team shall perform its services as expeditiously as is consistent with such professional skill and care and the orderly progress of the project.
The design phases will include 65%, 95% and review stages. If the documents do not meet all of the requirements of each submission, then the portions of the documents that are not acceptable by the VA according to the design standards and criteria must be updated by the DB Team prior to moving on to the next scheduled submission.
The VA will provide requested As-Built drawings (in either AutoCAD, PDF, or JPG form) on a CD-ROM to the A/E for design purposes. The A/E is encouraged to review all drawings with the assigned VA representative COTR to verify what existing drawings are available. The A/E shall coordinate with the VA representative COTR prior to viewing the drawings located at the VA and shall not remove any documents from the files.
The existing drawings on file at the VA may not be 100% accurate and may not exactly reflect the current conditions of the James A. Haley VA Hospital. It is the responsibility of the A/E to review the existing drawings and verify the existing conditions.
B. Project Description: Provide design build services to accommodate the replacement of the devices and cabling infrastructure of the current Fire Alarm System (Simplex) within the JAHVA Campus as identified in this SOW. The project will bring the systems up to date with the most current product, infrastructure, hardware, and software available.
The following fire alarm system areas have been identified as in need of the upgrade. The DB Team shall review all the existing field conditions and perform a survey of these affected areas (to verify the existing conditions):
· Upgrade the following 18 Nodes from 4100U CPU/Display to latest version of 4100ES CPU/Display
| NODE |
| BUILDING |
| LOCATION |
| EQUIPMENT ID |
| 2 |
| CEP NDU |
| CEP |
| 3 |
| CEP NVCC |
| CEP |
| 4 |
| BLD 39 CEP |
| CEP |
| 38099 |
| 5 |
| BLD 38 SCIU/BLD 40 |
| A224-38 |
| 84122 |
| 6 |
| BLD 32 RTU/BLD 63/T98 |
| 127-32 |
| 83137 |
| 7 |
| BLD 1 MRI/BLD 56 |
| C052-01 |
| 83133 |
| 9 |
| BLD 1/BLD 19/T33 PULLS |
| GA-023 |
| 83134 |
| 10 |
| BLD 2 |
| 1FL ELEC CLOSET |
| 25073 |
| 11 |
| BLD 36 |
| 113-36 |
| 100559 |
| 12 |
| BLD 41 |
| 135-41 |
| 63692 |
| 13 |
| BLD 68/T62/T80/T81/T82/T83 |
| 119-68 |
| 80844 |
| 14 |
| BLD 53 FH1 |
| 117-53 |
| 80843 |
| 15 |
| BLD 1 ER EXPANSION |
| GE005-01 |
| 72619 |
| 16 |
| BLD 1 A WING/T33 SMKS |
| GA-016C |
| 83135 |
| 17 |
| BLD 30/BLD 64/T77/T78 |
| 171-30 |
| 80869 |
| 19 |
| BLD 1 OR EXPANSION |
| BD-11 |
| 74194 |
| 20 |
| BLD 1 D WING |
| D131B-01 |
| 83136 |
| 21 |
| BLD 42/T73/T74/T75/T76 |
| 228-42 |
| 80406 |
· Update existing 4100ES software to the latest revision in the following nodes:
| NODE |
| BUILDING |
| LOCATION |
| EQUIPMENT ID |
| 8 |
| BLD 1 C WING |
| C101C-01 |
| 84121 |
| 24 |
| BLD 52 FH2 |
| KITCHEN |
| 139813 |
· Replace the following 4010 fire alarm panels to the latest version of 4100ES:
| NODE |
| BUILDING |
| LOCATION |
| EQUIPMENT ID |
| 22 |
| BLD 54 MAINT |
| 004-54 |
| 114698 |
| 23 |
| BLD 55 GARAGE |
| 104-55 |
| 100483 |
· Replace the following TSW Computers and upgrade graphics to reflect the current floor plans:
| NODE |
| BUILDING |
| LOCATION |
| EQUIPMENT ID |
| 1 |
| CEP TSW |
| CEP |
| 18 |
| ELECTRONICS SHOP |
| GD-023 |
· Determine which 4009 NAC Extender panels will remain and ones that do remain will be updated with new chips/firmware. The quantity of 4009’s will be affected by the addressable notification portion of the project.
· The Campus Main Network Communication Loop will receive upgrades replacing any building inter-connections that are not fiberoptic. It will replace the two copper networks for the fire alarm system. One is the node-to-node connection for comms, the other is the connection for the audio riser. According to the product specifications, both networks can utilize a common fiber route as described as follows:
| NODE |
| FROM BUILDING |
| NODE |
| TO BUILDING |
| 1 |
| CEP TSW |
| 2 |
| CEP NDU |
| 2 |
| CEP NDU |
| 3 |
| CEP NVCC |
| 3 |
| CEP NVCC |
| 4 |
| BLD 39 CEP |
| 4 |
| BLD 39 CEP |
| 5 |
| BLD 38 SCIU/BLD 40 |
| 5 |
| BLD 38 SCIU/BLD 40 |
| 6 |
| BLD 32 RTU/BLD 63/T98 |
| 6 |
| BLD 32 RTU/BLD 63/T98 |
| 7 |
| BLD 1 MRI/BLD 56 |
| 7 |
| BLD 1 MRI/BLD 56 |
| 8 |
| BLD 1 C WING |
| 8 |
| BLD 1 C WING |
| 9 |
| BLD 1/BLD 19/T33 PULLS |
| 9 |
| BLD 1/BLD 19/T33 PULLS |
| 10 |
| BLD 2 |
| 10 |
| BLD 2 |
| 11 |
| BLD 36 |
| 11 |
| BLD 36 |
| 12 |
| BLD 41 |
| 12 |
| BLD 41 |
| 24 |
| BLD 52 FH2 |
| 24 |
| BLD 52 FH2 |
| 13 |
| BLD 68/T62/T80/T81/T82/T83 |
| 13 |
| BLD 53 FH1 |
| 22 |
| BLD 54 MAINT |
| 22 |
| BLD 54 MAINT |
| 23 |
| BLD 55 GARAGE |
| 23 |
| BLD 55 GARAGE |
| 14 |
| BLD 53 FH1 |
| 14 |
| FH1 |
| 15 |
| BLD 1 ER EXPANSION |
| 15 |
| BLD 1 ER EXPANSION |
| 16 |
| BLD 1 A WING/T33 SMKS |
| 16 |
| BLD 1 A WING/T33 SMKS |
| 17 |
| BLD 30/BLD 64/T77/T78 |
| 17 |
| BLD 30/BLD 64/T77/T78 |
| 18 |
| ELECTRONICS SHOP |
| 18 |
| ELECTRONICS SHOP |
| 19 |
| BLD 1 OR EXPANSION |
| 19 |
| BLD 1 OR EXPANSION |
| 20 |
| BLD 1 D WING |
| 20 |
| BLD 1 D WING |
| 21 |
| BLD 42/T73/T74/T75/T76 |
| 21 |
| BLD 42/T73/T74/T75/T76 |
| 1 |
| CEP TSW |
· Provide and install a new smoke detector, along with any conduit/wiring needed for the following locations and devices:
1. 7 locations: Bldg 38 Third FL
2. 6 locations: Bldg 38 Second Fl
3. 4 locations: Bldg 38 Ground Fl
4. 5 locations: Bldg 1 Second Fl
5. 4 locations: Bldg 1 Fifth floor
6. 1 location : Bldg 1 Seventh Fl
· Incidentals:
1. Any troubles, grounds, opens or shorts found during the installation shall be recorded in detail and documentation submitted to the COR. This will be addressed as a possible change order or separate project depending on the magnitude of the findings.
The DB Team shall evaluate these areas to determine if utilities or any other objects will need to be relocated or addressed in the design. The DB Team shall also review the as–Built drawings and the site drawings for the areas affected.
The DB Team shall show a detailed containment plan for infection control for this design. This plan shall be detailed showing locations and what infection control requirements are to be used for each area. The HPMs for Safety and Infection Control will be provided to the D/B Team for their use. Construction barriers will be required for the duration of the construction to isolate patients and staff from dust, debris and construction hazards as determined by the Safety Officer and Infection Control representatives. The D/B Team will also have to indicate these construction barriers on their drawings.
New work includes, but is not limited to designing and preparing drawings, phasing planning, and specifications for all disciplines to create the upgrade of the fire alarm system in the hospital campus areas listed in this SOW. The D/B Team will be required to attend phase meetings at 65% and 95% to discuss progress with the VA staff. The D/B Team will be required to take meeting minutes and distribute to the VA for approval and as documentation of what was covered in the meeting.
C. Design Tasks:
1. SITE INVESTIGATION: Design Services shall conduct a site survey of the project area to ensure that the design is feasible and without any major obstacles. Available as–built drawings and related other project drawings are available to the DB Team, but field verification by the DB Team must be completed to verify existing site conditions and to collect data as required for design development work to successful completion of design and construction documents.
2. DEMOLITION: The project demolition work may include structural, architectural, electrical demolition to clear space for the new systems.
3. CIVIL / STRUCTURAL: Work may include architectural modification and structural work. Structural engineering is expected to be completed by a Florida Licensed Structural Engineer for any needed structural reinforcements. All required borings and structural testing shall be completed by the DB Team. The D/B team shall proceed with a structural design that will not impede on pedestrian traffic at the ground level.
4. ARCHITECTURAL: Field verification of elevations and architectural dimensions are crucial to the success of this project, as the existing drawings are best represented. Exterior work must blend into the surrounding buildings and architectural appearances.
Patient and Family Centered Care concepts are to be included in the design of this project. These concepts are outlined in the VA technical information library design guide documents. See paragraph I.D.2 for additional information.
5. INTERIOR DESIGN: The VA Interior Designer will perform all interior color and material selections from the D/B Team’s recommended items. The D/B team will coordinate all interior selections with the VA interior design staff.
6. ELECTRICAL: The D/B team must evaluate the electrical systems serving the design scope area to determine if there is enough, and provide modifications and extensions to the existing electrical systems, security system, communications system, fire / safety system, etc. as needed and with available capacity.
7. INDUSTRIAL HYGIENIST: An Industrial Hygienist (IH), licensed by the State of Florida as an Asbestos Consultant, may be required due to the existence of asbestos containing materials that may be encountered during the construction project.
8. ASBESTOS: The D/B Team shall investigate the construction site to verify any asbestos containing materials. A NESHAP is required. Asbestos containing sprayed-on fireproofing, floor tile & mastic, and other asbestos containing / contaminated materials / items may be encountered in buildings 1. If asbestos is encountered, it is the D/B Team and their subcontractor’s responsibility to adhere to all VA, OSHA, Federal, and State regulations of ACM procedures. All work performed in areas containing asbestos will be done after normal working Submittal packages for the Asbestos & IAQ qualifications shall be provided to the VA. The IH shall perform duties as necessary by monitoring, inspecting and testing inside / outside the work area in accordance with OSHA requirements.
a. NOTE: Some site investigation work may be in asbestos contaminated areas and will require the D/B team to have their personnel trained for Class 3 Asbestos Work (Maintenance & Operations within Asbestos Contaminated areas).
b. IAQ: The IH will also have to design IAQ measures for construction work in relevant areas.
9. EQUIPMENT: The D/B Team shall coordinate the design work directly with the suppliers / manufacturers of the new equipment to produce a completely designed operational project. All drawings, schematics, and other data available from the equipment suppliers shall be incorporated in the A/E drawings and specifications. The D/B Team is to determine the points of connection between old and new equipment and clearly detail these connections on the drawings.
10. Design the project by using site measurements and verifying site conditions. The D/B Team shall not rely solely on the As–Built drawings.
11. The D/B Team shall provide other documentation (i.e., calculations, reports, recommendations, etc.) that is appropriate to support the design effort and to keep the Government fully informed of all issues or potential problems. Provide computations and sizing calculations for any anticipated new loads, altered loads, and existing loads for electrical, mechanical (HVAC, plumbing, medical gas and steam), sanitary, structural and fire protection designs. For computerized calculations, submit complete and clear documentation of computer programs, interpretation of input / output, and description of program procedures. Provide an investigation and explanation of code requirements incorporated into the design. Furnish a copy of each code quoted or used in the design, when necessary to provide additional understanding of design decisions.
12. The D/B Team shall provide all schedules and tables used on the drawings in MS Excel.
D. Additional Requirements and Information:
1. LIFE SAFETY: Requirement for acquiring and incorporating a Certified Independent Third-Party Safety Professional review of design documents. The D/B Team shall design the necessary Life Safety and Interim Life Safety provisions for impacted areas, both temporary and permanent measures. The D/B Team shall provide and coordinate the review of the Life Safety Provisions of the project design with a third party, independent licensed Fire Protection Engineer. The following areas will be reviewed by the third party:
a. NFPA Code Compliance
b. Environmental / EPA Impacts, Permits, etc.
c. OSHA Compliance (i.e., Excavation, Demolition, etc.)
d. Security Property / Infrastructure Management, Homeland Security, etc.
e. Emergency preparedness
f. Disability Accessibility Compliance
g. National and Local Codes. The D/B Team shall deliver a letter certifying compliance with all Life Safety Codes and Requirements applicable to this project from the third party.
In addition, it is required that the D/B Team update all Life Safety Drawings associated with the designed space and affected by the project.
2. NOTES: NFPA 101 primarily addresses life safety and fire protection features while the IBC addresses a wide range of considerations, including, but not limited to, structural strength, stability, sanitation, adequate light and ventilation, and energy conservation. VA buildings must meet the requirements of NFPA 101 and documents referenced by NFPA 101 in order to comply with the accreditation requirements of the joint Commission. Therefore, designs shall comply with the requirements of the latest edition of NFPA 101 and documents referenced therein. Design features not addressed by NFPA 101 or documents referenced therein shall comply with the requirements of the latest edition of the IBC or as otherwise addressed above in this Program Guide. For design features that are addressed by both the IBC as well as NFPA 101 or a document referenced by NFPA 101, the requirements of NFPA 101 or the document referenced by NFPA 101 shall be used exclusively. This applies even if the IBC requirements are different.
3. Conflicts between Nationally Recognized Codes and Standards and VA Requirements: Should a conflict exist between VA requirements and VA adopted nationally recognized codes and standards, the conflict shall be brought to the attention of the VA. The resolution of the conflict shall be made by the authority having jurisdiction for the VA to ensure a consistency system wide.
4. DRAWINGS: The A/E shall provide electronic copies of drawings at each review step generated in the latest version of AutoCAD or its companion products (digitally signed DWGs) and PDF format in individual sheet files on CD-ROM. Include all associated support files (i.e. plot styles, external referenced files, etc.). This facility currently uses AutoCAD. The standard drawing size shall be ARCH E1 (30” x 42”). The format to be used in creating the CAD drawings (i.e. layer / level structure, fonts, font sizing, file naming conventions, etc.) is that of the latest edition of the National CAD Standard (www.nationalcadstandard.org).
a. The D/B Team shall follow these level / layer formats, file – naming conventions, and symbol library.
b. Drawings are to be drawn from the VA’s “As-Built” or construction drawings updated by site verification, not scanned reproductions.
c. The final sets of the new construction drawings, including the film copies, shall be sealed (embossed & ink stamps) and signed by each respective Professional Engineer in their discipline, Industrial Hygienist, Architect and other necessary licensed professional consultants.
5. SPECIFICATIONS: The D/B Team may obtain the list of the complete VA Construction Specifications from the VA Facilities Management Technical Information Library (TIL), which is located at http://www.cfm.va.gov/TIL/spec.asp#02. The Tampa VA has specifications that have been edited for general use at this facility and are the preferred specification to be used. If there are missing specifications sections from the Tampa VA specific specification then the specifications from the Technical Information Library shall be used. Any specifications that are edited by the contractor shall be submitted to the VA for approval. The edited version of the specification shall be in Microsoft Word in the editing format and all changes shall be in RED. Contact the project COTR to obtain a copy of these specifications on CD-ROM. This facility will provide the specification sections needed based on the master list provided in the first review. The A/E shall provide the final edited specifications on CD-ROM in Microsoft Word. The VA uses MS Word 2013. The format shall be 1.5 spaced, left justified, 2-sided, laser quality, and courier-new size 10 font. The specifications shall be provided in four (4) copies with rubber bands around three (3) of the copies. The remaining copy shall be in a colored, 3-“D”-ring loose-leaf binder, with identification labels on the binding and cover so the project title and number are readily visible and with tabbed dividers between each specification section. Any files submitted electronically (including but not limited to specifications and drawings) shall not have the following characters in their file name: \ / : * ? “ < > | # { } % ~ &.
6. DESIGN SCHEDULES: Design schedules shall be submitted to the VA as an 11x17 Microsoft Projects file at the beginning of the Notice to Proceed, with each invoice for payment and shall never be more than 4 weeks old. Approximate time frames are presented below. Actual timelines submitted for approval should reflect the project complexity and follow the format presented below:
a. Begin Design Development (Notice to Proceed): NTP
b. First Submission Contract Documents (CD1-65%): NTP + 80 Days
c. First Review Meeting and Return First Submission: NTP + 95 Days
a. Second Submission Contract Documents (CD2-95%): NTP + 120 Days
b. Second Review Meeting and Return Third Submission: NTP + 135 Days
c. Forth Submission (Deliver Final Contract Documents) (CD3-100%): NTP + 155 Days
7. REVIEW MEETINGS: The DB Team is required to attend a design review meeting after each submission during the design process and provide meeting minutes to the VA for approval and distribution.
1. Sections of the documents that are not acceptable by the VA according to the design standards and criteria must be updated by the A/E prior to moving on to the next scheduled submission.
E. COMPLIANCE
· The contractor shall be fully responsible for compliance with all VA, local, state, and Federal occupational safety laws, rules, and regulations.
· The contractor shall follow life and safety codes and take necessary actions to avoid conditions that may be hazardous to the health and safety of hospital personnel and patients.
· The contractor is responsible for meeting all applicable OSHA and VA guidelines for safe working procedures.
· All work for the duration of the contract shall be performed by certified trained technicians.
F.CONTRACTOR EMPLOYEES
Contractor personnel shall present a neat appearance and be easily recognized as contract employees. Example: wearing steel toe boots and safety glasses ID badges and or name tags.
G.CONTRACTOR EMPLOYEE IDENTIFICATION
All contractor employees must be clearly identified as contractors (not VA employees) when performing services under this contract. This includes visual (appearance), verbal (phone), and electronic (email). The contractor must provide all employees with a contractor identification (ID) badge at the contractor’s expense prior to performing work under this contract. Contractor employees are always required to display this badge when performing services under this contract.
Employees released from service by the contractor must have their badge collected by the contractor. All badges must contain an expiration date and photograph of the employee.
All contractor employees must also be required to wear VA issued badges and must always display these badges while in the performance of this contract and/or as instructed by the COR.
The contractor supervisor must ensure that all contractor employees display their VA issued badges.
The contractor supervisor must be responsible for managing all VA issued badges provided to contractor employees and immediately collect these badges from employees no longer working on the contract.
H.CONTRACTOR EMPLOYEE CONDUCT
· The contractor is completely responsible for all actions and conduct of their employees. Contractor employees must be well-groomed and neat in appearance.
· Contract employees must be professional in attire and must not wear any offensive clothing.
· Contractor employees must conduct themselves in a socially acceptable manner appropriate for an office work environment; Loudness, vulgarity, rudeness, smoking, or other similar offensive conduct by a contractor employee may be grounds for denying the employee further access to VA premises.
· Contractor employees must not consume alcohol or illegal drugs during working hours or at any other time the employees are performing work under this contract.
I.CONTRACTOR RESPONSIBILITY
· The contractor shall obtain all necessary licenses and/or permits as required to perform this work.
· He/she shall take all reasonable precautions necessary to protect persons and property from injury or damage during the performance of this contract.
· He/she shall be responsible for any injury to himself/herself, his/her employees, as well as for any damage to personal or public property that occurs during the performance of this contract that is caused by his/her employees’ fault or negligence and shall maintain personal liability and property damage insurance having coverage for a limit as required by the laws of the State of Florida.
· Further, it is agreed that any negligence of the Government, its officers, agents, servants, and employees, shall not be the responsibility of the contractor hereunder with the regard to any claims, loss, damage, injury, and liability resulting there from.
J.UNSCHEDULED REPAIRS AND EMERGENCY SERVICE:
· Contractor shall provide a telephone number for repair services assistance. Contractor shall notify the COR immediately if the telephone number is changed.
· Contractor shall respond to emergency repair calls with their installation/warranty by phone normally within two (2) hours but no more than four (4) hours. Contractor shall provide an on-site response time of no more than four (4) hours or next business day if call is made after 1:00 p.m. and be required to repair the equipment and place it back in service within twenty-four (24) hours after notification by telephone call (unless another specified time is agreed to by the COR placing the service call request). Response time is defined as time contractor is first notified until the time vendor arrives on station. Failure to meet the required on-site response or repair time shall allow the Government an option to contact a third-party vendor to provide services. Costs for services provided by a third party shall be billed against the Contractor.
K.CONTRACT AWARD MEETING:
· The contractor shall not commence performance on the tasks in this SOW until the CO has conducted a Kickoff Meeting or advised the contractor that a kickoff meeting is waived. The initial Notice to Proceed will be for "design work only." NO construction effort is authorized until the Contracting Officer (CO) issues the NTP for construction. The POP for design is 155 days. The POP for construction is 205 days from the issuance of the NTP for construction.
L.PERIOD OF PERFORMANCE:
· This shall be a firm-fixed price contract. Warranty period for the installation and repair will be provided as part of the original contract documents for the project.
M. CHANGES TO THE Statement of Work
· Any changes to this SOW shall be authorized and approved only through written correspondence from the CO. A copy of each change will be kept in a project folder with all other products of the project. Costs incurred by the contractor through the actions of parties other than CO shall be borne by the contractor.
N. Performance Requirements:
· Contractor shall provide the necessary personnel and equipment to meet or exceed required service. Contractor shall have the following responsibilities:
· Provide licensed and trained personnel to perform the project in the State of Florida.
· Provide all supervision, labor and materials to complete all requirements described in this SOW.
· Contractor shall obtain all necessary licenses and permits required to perform this work required by this SOW, with each having completed the Occupational Safety & Health Administration (OSHA) approved 10-hour Construction Outreach Training or General Industry Outreach Training.
· Contractor shall take all precautions necessary to protect persons and property from injury and/or damage during performance of this contract.
· Contractor shall be responsible for any injury to their employees as well as for any damages to personnel or Government property that occurs during the performance of this contract that is caused by the Contractor’s fault or negligence.
· Contractor shall insure that all areas where equipment is serviced under this contract are left in a clean, neat and orderly condition.
· Contractors shall have technical training and evident track records of working experience in fire alarm and related components in healthcare, industrial, educational, or commercial facilities for a minimum of five (5) years.
· Contractors shall possess and utilize all necessary tools, equipment, and Personal Protective Equipment (PPE) to perform all work safely, effectively, and timely. Tools, equipment, and PPE shall comply with OSHA Standard 29 CFR 1910, (Subpart I), and NFPA 70E. Prior to initiating work, the Contractor shall provide documentation demonstrating that all instruments, test equipment, tools, and PPE possess current calibration and safety inspections. Dated calibration and safety inspection labels shall be visible on all equipment as applicable
· Arrange and pay for all proper disposal of waste and debris.
· Maintain project schedule agreed upon in the purchase order documents.
· Provide all OSHA site safety for each employee during work.
· Contractor employees shall have background checks completed.
O.DELIVERABLES
· The Contractor shall perform the services necessary to complete the tasks in accordance with the procedures described in a timely and professional manner, consistent with industry standards, at the location, place and time that the VA has set aside, and all in accordance with the SOW and RFP documents.
· Contactor shall provide a copy of the inspection document used (field report) on the day of each performed inspection.
P.TESTING SPECIFICATIONS
· All testing/inspections of the shall be in accordance with applicable industry standards and manufacturers recommendations. The initial test schedule shall be submitted to the COR no later than 10 days after award. The inspection schedule shall be submitted to the COR sixty (60) days prior to the start of the next inspection.
Q.ROLES AND RESPONSIBILITIES:
· Contracting Officer (CO) - A person duly appointed with the authority to enter, administer and terminate contracts on behalf of the Government. The CO is the only person who can legally commit the Government and only the CO, as the Government's agent, can modify the contract/order. The CO is the final authority for determining the adequacy of the Contractor's performance. CO decisions arising under or relating to the contact are final.
· Contracting Officer's Representative (COR) — An individual designated in writing by the CO to perform specific technical and administrative functions within the scope and limitations of their written appointment (e.g., surveillance of Contractor's performance, accept services). The COR is not empowered to make any contractual commitments or authorize any changes to the order/contract or in any way obligate additional funds by the Government; such authority' rests solely with the CO. The COR’s primary duty is to monitor the Contractor's performance by physically checking to see that tasks are completed, reports are submitted, and desired outcomes are achieved. When a surveillance observation results in an unacceptable evaluation, the COR will report the unacceptable performance to the COR. The COR is not authorized to direct work, offer advice on how the work should be performed, change the contract, or in any way obligate payment of funds by the Government.
R. SECURITY CLAUSES:
With No Sensitive Data but Requires Training
VA INFORMATION AND INFORMATION SYSTEM SECURITY/PRIVACY LANGUAGE
VA INFORMATION CUSTODIAL LANGUAGE:
a. Contractors, contractor personnel, subcontractors, and subcontractor personnel shall be subject to the same Federal laws, regulations, standards, and VA Directives and Handbooks as VA and VA personnel regarding information and information system security.
b. If VA determines that the contractor has violated any of the information confidentiality, privacy, and security provisions of the contract, it shall be sufficient grounds for VA to withhold payment to the contractor or third party or terminate the contract for default or terminate for cause under Federal Acquisition Regulation (FAR) part 12.
c. A contractor/subcontractor shall request logical (technical) or physical access to VA information and VA information systems for their employees, subcontractors, and affiliates only to the extent necessary to perform the services specified in the contract, agreement, or task order.
d. All contractors, subcontractors, and third-party servicers and associates working with VA information are subject to the same investigative requirements as those of VA appointees or employees who have access to the same types of information. The level and process of background security investigations for contractors must be in accordance with VA Directive and Handbook 0710, Personnel Suitability and Security Program. The Office for Operations, Security, and Preparedness is responsible for these policies and procedures.
SECURITY INCIDENT INVESTIGATION:
a. The term “security incident” means an event that has, or could have, resulted in unauthorized access to, loss or damage to VA assets, or sensitive information, or an action that breaches VA security procedures. The contractor/subcontractor shall immediately notify the COR and simultaneously, the designated ISO and Privacy Officer for the contract of any known or suspected security/privacy incidents, or any unauthorized disclosure of sensitive information, including that contained in system(s) to which the contractor/subcontractor has access.
b. To the extent known by the contractor/subcontractor, the contractor/subcontractor’s notice to VA shall identify the information involved, the circumstances surrounding the incident (including to whom, how, when, and where the VA information or assets were placed at risk or compromised), and any other information that the contractor/subcontractor considers relevant.
c. With respect to unsecured protected health information, the business associate is deemed to have discovered a data breach when the business associate knew or should have known of a breach of such information. Upon discovery, the business associate must notify the covered entity of the breach. Notifications need to be made in accordance with the executed business associate agreement.
d. In instances of theft or break-in or other criminal activity, the contractor/subcontractor must concurrently report the incident to the appropriate law enforcement entity (or entities) of jurisdiction, including the VA OIG and Security and Law Enforcement. The contractor, its employees, and its subcontractors and their employees shall cooperate with VA and any law enforcement authority responsible for the investigation and prosecution of any possible criminal law violation(s) associated with any incident. The contractor/subcontractor shall cooperate with VA in any civil litigation to recover VA information, obtain monetary or other compensation from a third party for damages arising from any incident, or obtain injunctive relief against any third party arising from, or related to, the incident.
LIQUIDATED DAMAGES FOR DATA BREACH:
a. Consistent with the requirements of 38 U.S.C. §5725, a contract may require access to sensitive personal information. If so, the contractor is liable to VA for liquidated damages in the event of a data breach or privacy incident involving any SPI the contractor/subcontractor processes or maintains under this contract. However, it is the policy of VA to forgo collection of liquidated damages in the event the contractor provides payment of actual damages in an amount determined to be adequate by the agency.
b. The contractor/subcontractor shall provide notice to VA of a “security incident” as set forth in the Security Incident Investigation section above. Upon such notification, VA must secure from a non-Department entity or the VA Office of Inspector General an independent risk analysis of the data breach to determine the level of risk associated with the data breach for the potential misuse of any sensitive personal information involved in the data breach. The term 'data breach' means the loss, theft, or other unauthorized access, or any access other than that incidental to the scope of employment, to data containing sensitive personal information, in electronic or printed form, that results in the potential compromise of the confidentiality or integrity of the data. Contractor shall fully cooperate with the entity performing the risk analysis. Failure to cooperate may be deemed a material breach and grounds for contract termination.
SECURITY CONTROLS COMPLIANCE TESTING:
On a periodic basis, VA, including the Office of Inspector General, reserves the right to evaluate any or all of the security controls and privacy practices implemented by the contractor under the clauses contained within the contract. With 10 working-days’ notice, at the request of the government, the contractor must fully cooperate and assist in a government-sponsored security controls assessment at each location wherein VA information is processed or stored, or information systems are developed, operated, maintained, or used on behalf of VA, including those initiated by the Office of Inspector General. The government may conduct a security control assessment on shorter notice (to include unannounced assessments) as determined by VA in the event of a security incident or at any other time.
TRAINING:
a. All contractor employees and subcontractor employees requiring access to VA information and VA information systems shall complete VA Privacy and Information Security Awareness and Rules of Behavior Training before being granted access to VA information and its systems.
i. Sign and acknowledge (either manually or electronically) understanding of and responsibilities for compliance with the Rules of Behavior before being granted access to VA information and its systems.
b. The contractor shall provide to the contracting officer and/or the COR a copy of the training certificates and certification of signing the Rules of Behavior for each applicable employee within 1 week of the initiation of the contract and annually thereafter, as required.
c. Failure to complete the mandatory annual training and sign the Rules of Behavior annually, within the timeframe required, is grounds for suspension or termination of all physical or electronic access privileges and removal from work on the contract until such time as the training and documents are complete.
The Certification and Accreditation (C&A) requirements do not apply and a Security Accreditation Package is not required for this SOW.
All Contractor, Pharmaceutical Company Representative (PCR), and Healthcare Industry Representatives (HIR) will coordinate with Contracting Officer Representative for instructions so they are in compliance with James A. Haley Veterans’ Hospital policies listed on the JAHMC Document Management Center share point site:
HPM NO. 90-25; HEALTHCARE VENDOR ACCESS AND COMPETENCY
HPM NO. 132-04; SECURITY MANAGEMENT PROGRAM
HPM NO. 13205; HOSPITAL IDENTIFICATION PROGRAM
HPM NO. 11-91; PHARMACEUTICAL COMPANY REPRESENTATIVES
HIR are required to report to MSDU (Room GC-003), immediately after entering the facility. HIR will be required to sign into the monitoring system and print a badge for proper identification. . The Healthcare Industry Representatives for Nutrition and Food Services, Office of Information and Technology, and Social Work Services are in included in this policy; vendors (HIR) for Pharmacy Services are to follow (HPM 11-91) policy. HIR must be sponsored by a physician, a Service Chief, or their designee, for a specified date and a specified case. HIR are not permitted in patient care areas or clinics unless a prior appointment has been made.
Pharmaceutical Company Representative (PCR) refers to anyone acting on behalf of a pharmaceutical company or its business partners for the purpose of promoting the use of…