This is an Amendment/Modification to Solicitation (SF 30) for the 646-20-109 UD Chiller Capacity and Controls Upgrade project at the Pittsburgh VA Medical Center, issued by the Department of Veterans Affairs Network Contracting Office. The amendment extends the proposal submission deadline from June 12, 2026 to June 26, 2026 at 3:30 PM EDT and schedules a second mandatory site visit for June 12, 2026 at 1:00 PM EST at Pittsburgh VAMC, Building One Atrium, with strong encouragement for bidders to bring all relevant subcontractors.
The amendment includes responses to eight Request for Information (RFI) submissions from May 12, 2026, addressing technical specifications and clarifications. Key requirements identified include: Schweitzer Engineering Laboratories relays (SEL-700G for generator, SEL-751 for feeder) with specific ANSI functions; a three-phase automatic transfer switch matching existing Selector Switch 53 operations for redundancy; a GE-manufactured heat trace control panel with one 70A/3P, 65kAIC circuit breaker input and ten integral 20A/1P GFEP output breakers; combined training for multiple equipment categories into a single four-hour session; and masonry demolition and repair work with flush finish and thinset mortar repair. Additional RFIs must be submitted electronically to Amy Demarest and Elijah McIntosh by June 17, 2026 at 3:30 PM EST, with final proposals due electronically by June 26, 2026 at 3:30 PM EST. Full-size drawings (30x42) are now available on SAM.gov to support accurate scaling and interpretation.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 05-29-2026 646-20-109 00244 Department of Veterans Affairs Network Contracting Office 4
00244 Department of Veterans Affairs Network Contracting Office 4
To all Offerors/Bidders
36C24426R0062
X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 06-26-2026 3:30 PM EDT X The above numbered solicitation for 646-20-109 UD Chiller Capacity and Controls Upgrade is amended to reflect the following:
Please see attached responses from RFI's submitted 12 May 2026.
SITE VISIT: A second site visit will be conducted at the Pittsburgh VAMC on 12 June 2026 at 1:00 PM EST. All interested parties will meet at the Pittsburgh VAMC, Building One Atrium. It is strongly encouraged to bring all relevant subcontractors, as this is the last scheduled site visit.
RFIs: Any additional RFI's must be provided electronically to Amy. Demarest@va.gov and Elijah.McIntosh@va.gov no later than 17 June 2026 at 3:30PM EST.
PROPOSAL: The proposal due date is being extended from 12 June 2026 until 26 June 2026.
Proposals must be provided electronically no later than 06/26/2026, 3:30 PM EST.
Elijah McIntosh Contracting Officer
| # |
| Question |
| VA Final Answer |
| 1 |
| Drawing E603 Note 4 & 5: Is there a specification or preference for the Relays to be provided for 8-MVSWGR-1 (section 1) What functions are needed? |
| For bidding purposes, basis of design relays shall be Schweitzer Engineering Laboratories SEL-700G (for generator) & SEL-751 (for feeder). ANSI Functions 27, 50 (Phase & Neutral), 51 (Phase & Neutral), and 59 shall be included. Associated PTs and CTs must also be included. |
| 2 |
| Drawing E603 Note 16: What is the existing make/manufacturer of Panel 8A? |
| GE Spectra Series APNB Bolt-On Style. Please see photo below. |
| 3 |
| Drawing E604 8-MVSWGR-2. Please confirm what is needed for the “3P Automatic transfer switch”. Is it to be similar to 8-MVSWGR-1 (section 1) OR Existing Selector Switch 53. Is there a specification or sequence of operation? |
| The new 3P automatic transfer switch in 8-MVSWGR-2 shall match the same operation as the existing ATS in Selector Switch 53. The new 3P automatic transfer switch was designed to provide additional redundancy to the incoming power feed from Building 31’s main electrical distribution gear. As designed, these two ATS equipment shall communication with each other to avoid double switching of alternating sources at the same time. |
| 4 |
| Drawing E604 Note 7 – Note that the 30mA GFCI breakers are only rated for 10kAIC. Panel is listed at 65kAIC on the SLD. |
| In lieu of providing (10) 20A/1P breakers in Distribution Panel 8C, provide (1) 70A/3P, 65kAIC circuit breaker in Distribution Panel 8C. The heat trace control panel shall be provided with (1) 70A/3P input and (10) integral 20A/1P GFEP output breakers to serve the heat tracing circuits. Associated costs for all equipment, circuit breakers, controls, wiring, etc. shall be included. |
| 5 |
| Drawing E604 Note 14 –Is there a specific product or manufacturer of the requested design |
| The manufacturer is GE. Refer to RFI-76 response in “UD Chillers RFI VA responses.pdf” as provided in the SAM.gov listing. |
| 6 |
| 26 13 13 MV circuit breaker switchgear, 26 13 15 MV interrupter, 26 24 13 Distribution Switchboards, 26 36 23 Automatic Transfer Switch all call for 4 hours of training. Can any of these be combined? |
| Yes, all trainings may be combined into one session. |
| 7 |
| A vendor was looking at the add to existing SQD switchboard and wondered why add a bus transition that is not being added to another switchgear lineup but to just feed cables to two different pull boxes. Could they just be separated on the load side of the switch and direct them to different pull boxes? |
| Please provide supporting documentation on the recommendation. During design, we coordinated the design intent with Square D and this was the most feasible approach at that time. |
| 8 |
| Detail 1/SD501: what is the intent at either end of the wall, where it ties into the other walls? Demo flush as best as possible, or demo into these walls, let's say 2", cut reinforcing steel, form and pump the wall patch? Please provide a detail. |
| Demo flush as best as possible. Trim rebar to be flush. Finish with thinset repair mortar as needed to achieve smooth surface. |
| 9 |
| Detail 5/SD501: This detail is referenced on drawing SD121 on the masonry wall on the left that needs to be demolished. Please clarify the extent of that item. Is it along the entire wall? |
| Detail 5/SD501 is a typical detail for slab-on-grade demolition along the wall on column line X5. This demolition only needs to occur where the slab is demolished as shown on SD111 and where the slab is new on SF111. |
| 10 |
| Additionally, is it possible to obtain full-size drawings (e.g., 22x34 or 30x42) in lieu of the current 8.5"x11" versions? We are particularly concerned that the reduced-size sheets may impact the ability to accurately scale and interpret dimensions. |
| Full-size drawings (30x42) have been uploaded to SAM.gov. |