This is an Amendment to a Request for Lease Proposals (RLP) for a Department of Veterans Affairs (VA) facility. The amendment modifies 14 key sections of the original RLP and associated lease requirements.
The amendments address facility specifications and design requirements. On-site parking requirements remain at a minimum of 150 spaces, with adjustments to meet local code requirements. New construction must be built to LEED Checklist standards, though LEED certification is not required. The Building and Design Concept evaluation factor now emphasizes accommodation of Patient Aligned Care Team (PACT) design, contiguous single-story first-floor access, exterior tenant entrances, and core infrastructure elements including structural, mechanical, electrical, plumbing, HVAC, telecommunications, Wi-Fi, security, fire protection, and life-safety systems. The design and completion schedule has been revised with specific milestone dates: schematic design due Day 15, 35% design Day 60, 65% design Day 105, 95% design Day 150, and final construction documents due Day 175, with government review completing by Day 180. Tenants Improvement (TI) construction documents must conform to approved Data Item Descriptions (DIDs) within 15 calendar days of approval. Janitorial services will be provided by the Government, with the Lessor responsible for plant and lawn maintenance, light bulb replacement, pest control using integrated pest management, and nuisance wildlife control in accordance with U.S. Department of Agriculture Wildlife Services. Fire protection code review will be conducted at the 65% and 95% design review stages. Exhibit B Agency Specific Requirements have been replaced with revised technical requirements contained in Attachment 5.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 3 Page 1 of 3
Amendment to RLP:
Section Action 1 RLP Section 1.05, Paragraph A Replace the bolded number within the following sentence:
The VA dedicated on-site parking will be no less than 150 spaces and shall be increased to meet current local code required if necessary.
2 RLP Section 3.02, Receipt of Lease Proposals
Add Volumes, see RLP Amendment 0001 Attachment 4.
3 RLP Section 3.06, Paragraphs R Replace paragraph its entirety with the following:
New construction must be built to LEED Checklist, LEED certification is not required.
4 RLP Section 3.06, Paragraphs S Remove in its entirety.
5 RLP Section 4.05 Evaluation Factor Description
Subfactor 2. Building and Design Concept
Replace paragraph in its entirety with the following:
Subfactor 2: Building and Design Concept:
Subfactor considers ability to accommodate Patient Aligned Care Team (PACT) design;
contiguous single story, first floor (street-level) access; exterior entrances for tenant usage; core elements (i.e., structural, mechanical, electrical, plumbing, HVAC, telephone and data distribution system, Wi-Fi; security, fire protection and life-safety systems).
6 RLP Section 4.07 Evaluation Factor Submittal Requirement
Remove Volumes from this section in its entirety.
Volumes were revised and moved under RLP Section 3.02 Receipt of Lease Proposals.
7 Lease Section 3.49 High- Performance Building Rating Certification for Tenant Interiors
Remove in its entirety.
8 Lease Section 4.01, Schedule for Completion of Space, Paragraph A
Replace table in its entirety with the following:
Award of Lease Day 0 Initial meeting with Government
– Floor Plan Concept
Day 5
Schematic Design due to VA Day 15 Design Review meeting (Schematic Design)
Day 30
35% Design due to VA Day 60 35% Design review meeting Day 75 65% Design due to VA Day
65% Design Review meeting – No significant changes on design layout after this meeting
Day
Attachment 3 Page 2 of 3
95% Design due to VA Day
95% Design review meeting Day
Final CD submission due to VA Day
Government review CD 180
9 Lease Section 4.01, Schedule for Completion of Space, Paragraph D
Replace the bolded number within the following sentence:
The Lessor as part of the TI must complete CDs conforming to the approved DIDs not later than 15 Calendar Days following the approval of DIDs.
10 Lease Section 6.07 Janitorial Services.
Replacing this section in its entirety with the following:
Janitorial services will be provided by the Government. Lessor must provide the following:
A. As required. Properly maintain plants and lawns. Provide initial supply, installation, and replacement of light bulbs, tubes, ballasts, and starters.
B. Pest control. Control pests as appropriate, using integrated pest management techniques.
C. Nuisance Wildlife. Control nuisance wildlife, including migratory birds, in accordance with the U.S. Department of Agriculture Wildlife Services. This includes routine assessments, damage prevention strategies, individual removal as necessary to prevent conflicts, and sanitary cleanup of animal waste in all pedestrian accessible areas to maintain a safe and healthy environment.
11 Lease Section 6.08 Selection of
Cleaning Products Removed in its entirety.
12 Lease Section 6.09 Selection of Paper Products
Removed in its entirety
13 Lease Section 7.06 Fire Protection Code Review
Replace the bolded number within the following sentence:
All fire protection code review shall be conducted at the 65% and 95% design review, with all comments responded to, resolved and incorporated, as required, into design by the 95% design review and in a manner that is acceptable
Attachment 3 Page 3 of 3 to the design team, the reviewer(s), and the Chief Engineer or designee (e.g., Contracting Officer’s Representative) responsible for managing the project.
14 Replace Exhibit B. Agency Specific Requirement in its entirety.