About this file

This is a Pre-Bid Request for Information (RFI) responses document for VA Castle Point Roofing Replacement Project 620A4-22-103, issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2. The RFI addresses three primary bidding clarifications: ACM textured paint treatment, deduct alternates, and unit prices/allowances. Regarding the asbestos-containing material (ACM) textured paint on Buildings 19, 20, and 21 facades, the government confirmed the material will be treated as non-friable ACM and handled similar to waterproofing or flashing work, eliminating the need for full-elevation containment barriers. The government also clarified that all references to deduct alternates should be disregarded and the project shall be bid as a complete project without deduct alternate pricing for individual buildings or corridors.

The solicitation requires bidders to include a $50,000 allowance for any additional repairs or replacements discovered during construction and provide line item costs (unit prices) for specified materials including fire-resistant and pressure-treated lumber, plywood, nailable rigid insulation, brick/mortar/sealant repairs, painting, and plaster repair. The scope encompasses roof replacement and facade repair work across multiple buildings (B18-B21 and corridors) at the Castle Point Veterans facility, with the allowance and unit price schedule to be incorporated into the base bid submission. All bidders are instructed to disregard previous project documentation references to deduct alternates to ensure consistent bid submissions across all proposals.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DZ--620A4-22-103 Replace Roofs Castle Point, newest first.
File Type Posted
36C24226B0004 0007.docx DOCX document
Sign In Sheet Site Visit.pdf PDF
36C24226B0004 0006.docx DOCX document
21-442 - VA Castle Point Roofing - Responses continued.docx DOCX document
21-442 - VA Castle Point Roofing - Pre-Bid Responses Contd.docx DOCX document
36C24226B0004 0005.docx DOCX document
21-442 - VA Castle Point Roofing - Pre-Bid Questions Responses.pdf PDF
36C24226B0004 0004.docx DOCX document
21-442 - VA Castle Point Roofing - Pre-Bid Questions.pdf PDF
Survey Report CP Roofs.pdf PDF
36C24226B0004 0003.docx DOCX document
36C24226B0004 0002.docx DOCX document
P07 - Wage Rates DCNY.pdf PDF
36C24226B0004 0001.docx DOCX document
620A4-22-103 -Specifications.pdf PDF
620A4-22-103 Drawings.pdf PDF
36C24226B0004.docx DOCX document
Buy American Certificate.pdf PDF
852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING-CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION.pdf PDF
Wage Rates DCNY.docx DOCX document
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Bid RFI #5 Submission for 620A4-22-103 Roof Replacement and Façade Repair

1. B19/20/21 Facade ACM textured paint The Asbestos survey/lab package doesn’t state friable vs non-friable for B19, 20, & 21 facade textured paint. Lab sheets show analysis under NYS 198.6 (Non-Friable, Organically Bound) while NYS 198.1 (friable) was not analyzed. We do not see a work plan for this scope defining containment and removal methods. Various interpretations represent major cost differences. Please confirm the basis-of-bid for this ACM textured paint removal:

· Option #1: Treat as non-friable ACM with localized exterior controls (ground poly / limited draping at active areas), OR

· Option #2: Treat as friable requiring full-elevation containment (building draping and/or rigid hardwall type barriers at entirety of buildings – major cost implication).

· Is a NYSDOL variance/alternate procedure assumed for the intended removal method? Whose responsibility would this be?

· We are not requesting a bid extension—just trying to keep all abatement bids consistent.

Response: The textured paint will be considered nonfriable for this project and treated similar to waterproofing or flashing.

1. Deduct Alternates GI-003 “General Project Phasing Notes” says to provide deduct alternate pricing for each building roof (B18–B21 & corridors) and B19/20/21 facade work separately. Disregard all references to deduct alternates.

· The bid form we have does not include any deduct alternate lines. Please clarify if these deducts are required with the bid to have a complete bid submission. Disregard all references to deduct alternates.

· The deduct alternate lines do not call out the facade work for Bldgs. 16 & 18. Please clarify if the deduct for Bldg. 18 is intended to include all work at Bldg. 18 including the facade and not just the roof. Disregard all references to deduct alternates.

RESPONSE: The project shall be bid as a complete project, no deduct alternates.

1. Unit Prices GI-003 Scope/Note 5 says to include a $50k allowance, and to provide unit prices for various items (incl. F FRT/PT lumber, FRT/PT plywood, nailable rigid insulation, brick/mortar/sealant repair, painting, plaster repair, etc.)

· The bid form does not show an allowance line item or a unit price schedule. Please clarify if this allowance is included within the base bid and if the unit price schedule is required with the bid to have a complete bid submission. If the deducts are required, should the $50k allowance remain in the contract sum?

Response: Bid shall also include:

· Disregard all references to “Bid Deducts/Alternates”

· ALLOWANCE $50,000 for any additional repairs/replacements found during construction.

· Line item costs (unit prices) for:

· Fire resistant, pressure treat lumber, etc.

(See items listed on GI-003)