Construction Specification Institute Division Breakdown.xlsx

XLSX spreadsheet 28 KB Posted

Attached to
Z2DA--518-22-111 Elevator Replacement Ph. 3
Solicitation number
36C24125B0003
Issued by

About this file

This is a pricing template spreadsheet for a construction project bid, specifically for an Elevator Replacement Phase 3 project at Bedford VAMC (VA Medical Center). The template is structured as a Construction Specification Institute (CSI) division breakdown, requiring bidders to itemize labor and material costs across 24 divisions including general requirements, existing conditions, concrete, masonry, metals, conveying equipment, electrical, and other construction categories. The template includes fields for overhead percentage, profit percentage, and bond percentage calculations, which are applied to the division subtotals. The spreadsheet also contains sample tables for detailed labor and materials breakdowns, showing how to itemize specific costs like hourly labor rates and material units. This pricing template is associated with Department of Veterans Affairs solicitation number 36C24125B0003 for the Veterans Integrated Service Network 1.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base Offer

Base Offer Cost Breakdown

Project Number: 518-22-111 Edward L Roy: VA assigned project #

Date:
Project TitleElevator Replacement Phase 3

Edward L Roy: VA assigned Project Title

Project LocationBedford VAMC
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Sum of Overhead, Profit and Bond %.

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0

Labor Detail

Sample Example
DivisionLabor CategoryLabor RateHoursTotal
1Plumber$35.00123$4,305.00
1Laborer14.7570$1,032.50
$5,337.50

Materials and Equipment Details

Sample Example
DivisionItemRateUnitsTotal
1Pipe - 150'$1.50150$225.00
190 Degree Coupling$1.105$5.50
1Pump Rental - Hour$200.006$1,200.00
$1,430.50

File details come from the government source that posted it. Updated .