TNC3 SPECIFICATIONS MAY 20 2024.pdf

PDF 19 MB Posted

Attached to
Y1PC--Tahoma National Cemetery, Ph 3 Federal contract opportunity
Solicitation number
36C10F24R0011
Issued by
Department of Veterans Affairs Office of Construction and Facilities Management

About this file

The document provided is the TNC3 SPECIFICATIONS MAY 20 2024.pdf, which appears to be technical specifications related to Solicitation Number 36C10F24R0011 for the Y1PC--Tahoma National Cemetery, Ph 3 project.

This solicitation is issued by the Department of Veterans Affairs Office of Construction and Facilities Management for Project Number 919-010, Tahoma National Cemetery, Phase 3. The solicitation is for construction services to complete the third phase of development at the Tahoma National Cemetery. The document contains detailed technical specifications for the required construction work, including specifications for site work, landscaping, utilities, and other cemetery infrastructure. No additional details are provided regarding response dates, award dates, pricing terms, set asides, or incumbent contractors.

View the file

Other files for this federal contract opportunity

Other files attached to Y1PC--Tahoma National Cemetery, Ph 3, newest first.
File Type Posted
36C10F24R0011 0007.pdf PDF
36C10F24R0011 0006.pdf PDF
Pre-Proposal Inquiry Form 36C10F24R0011 updated 07-02-2024.pdf PDF
TNC3 PIC Mech Rm_Image 1.pdf PDF
TNC3 PIC Mech Rm_Image 2.pdf PDF
Spec. Section 261219 PAD-MOUNTED, LIQUID-FILLED, MEDIUM-VOLTAGE TRANSFORMERS.pdf PDF
Pre-Proposal Inquiry Form 36C10F24R0011 dated 06-20-2024.pdf PDF
TNC3 PIC Men Restroom.pdf PDF
Columbaria Detail and Ash urn exhibit. Both Items are in one PDF..pdf PDF
36C10F24R0011 0005.pdf PDF
Site Visit - Attendance Sheet.pdf PDF
TNC3 SHEET 157 OF 449.pdf PDF
Pre-Proposal Inquiry Form 36C10F24R0011 06-10-2024.pdf PDF
Tahoma National Cemetery Phase 3 Contractor Overview.pdf PDF
36C10F24R0011 0004.pdf PDF
Interested Vendors List from SAM.GOV as of 06-10-2024.pdf PDF
36C10F24R0011 0003.pdf PDF
36C10F24R0011 0002.pdf PDF
TNC3 BID DOCUMENTS R 2-2-2024 4 of 9.pdf PDF
TNC3 BID DOCUMENTS R 2-2-2024 2 of 9.pdf PDF
36C10F24R0011 0001.pdf PDF
TNC3 BID DOCUMENTS R 2-2-2024 6 of 9.pdf PDF
TNC3 BID DOCUMENTS R 2-2-2024 8 of 9.pdf PDF
TNC3 BID DOCUMENTS R 2-2-2024 3 of 9.pdf PDF
TNC3 BID DOCUMENTS R 2-2-2024 1 of 9.pdf PDF
TNC Phase 3 Geotechnical Engineering Report-7-26-2023.pdf PDF
CALCULATION OF SELF PERFORMED WORK.pdf PDF
Small Business Subcontracting Plan Model.pdf PDF
TNC3 BID DOCUMENTS R 2-2-2024 9 of 9.pdf PDF
TNC3 BID DOCUMENTS R 2-2-2024 7 of 9.pdf PDF
TNC3 BID DOCUMENTS R 2-2-2024 5 of 9.pdf PDF
Cost Proposal Breakdown 02.pdf PDF
VAAR 852.219-75 VA Notice of Limitations on Subcontracting - Certification.pdf PDF
Past Performance Questionnaire 36C10F24R0011.pdf PDF
Pre-Proposal Inquiry Form 36C10F24R0011.pdf PDF
Wage Decision Number WA20240070 dated 03-08-2024.pdf PDF
36C10F24R0011_1.docx DOCX document
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Y:\16300\16362 TAHOMA NC PH3\_04 Specs\_07 Bid Docs Resubmit\000100 Spec Cover.docx

VA OFFICE OF CONSTRUCTION FACILITIES MANAGEMENT

VA PROJECT 919PC2010

Project Location: Kent, WA

Project Title: Tahoma National Cemetery Phase 3

Submission Type: Bid Documents Submittal

Submission Date: February 2, 2024 Revised Date: May 20, 2024

PROJECT MANUAL (SPECIFICATIONS)

CLIENT: Department of Veteran Affairs Office of Construction & Facilities Management 425 I Street NW, SUITE 6W417C Washington, DC 20001

Contracting Officer: Athena Jackson Project Manager: Patricia Hartman

CONSULTANT: Anderson Engineering of MN, LLC 13605 1st Avenue North, Suite 100 Plymouth, MN 55441 Project Manager: Michael Brandvold

Tahoma National Cemetery Ph 3 10-01-18

00 01 10-1 Y:\16300\16362 TAHOMA NC PH3\_04 Specs\_07 Bid Docs Resubmit\000110 TOC NC Spec TNC3 BD.docx

DEPARTMENT OF VETERANS AFFAIRS

NCA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

DIVISION 00 - SPECIAL SECTIONS DATE

00 01 00 Cover 05-24 00 01 10 Table of Contents 10-18 00 01 15 List of Drawing Sheets 05-10

DIVISION 01 - GENERAL REQUIREMENTS

01 00 01 General Requirements (Major NCA Projects) 06-14 01 32 16.13 Network Analysis Schedules 07-19 01 32 17 Network Analysis Schedules (Microsoft Project Gantt

Chart) 10-10

01 33 23 Shop Drawings, Product Data, and Samples 11-23 01 35 26 Safety Requirements 05-24 01 42 19 Reference Standards 06-14 01 43 39 Mockup Requirements 01-22 01 45 00 Quality Control 05-24 01 45 29 Testing Laboratory Services 06-14 01 50 10 Temporary Facilities 01 57 19 Temporary Environmental Controls 04-10 01 74 19 Construction Waste Management 06-14 01 81 13 Sustainable Construction Requirements 06-14 01 91 00 General Commissioning Requirements 12-15

DIVISION 02 – EXISTING CONDITIONS

02 21 00 Site Surveys 06-14 02 35 00 Tree Protection and Preservation 11-21 02 41 10 Demolition and Site Clearing 06-14

DIVISION 03 – CONCRETE

03 01 30 Trowelable Concrete Micro Topping 03 30 53 Short-Form Cast-in-Place Concrete 06-14 03 48 21 Precast Concrete Burial Crypts (Double Depth Lawn

Crypt) 06-14

03 48 24 Precast Concrete Columbarium Units 06-14 03 92 50 Repair Mortars

DIVISION 04 – MASONRY

04 05 13 Masonry Mortaring 06-14 04 05 16 Masonry Grouting 06-14 04 05 31 Masonry Tuck Pointing 06-14

00 01 10-2 Y:\16300\16362 TAHOMA NC PH3\_04 Specs\_07 Bid Docs Resubmit\000110 TOC NC Spec TNC3 BD.docx

04 20 00 Unit Masonry 06-14 04 26 00 Adhered Stone Masonry Veneer 04 43 00 Natural Stone Veneer 10-18 04 73 00 Columbarium Niche Covers 06-14 04 73 10 Memorial Wall Markers 06-14

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 06-14 05 21 00 Steel Joist Framing 06-14 05 31 00 Steel Decking 06-14 05 36 00 Composite Metal Decking 06-14 05 40 00 Cold-Formed Metal Framing 06-14 05 50 00 Metal Fabrications 06-14

DIVISION 06 – WOOD,PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 12-15 06 20 00 Finish Carpentry 06-14 06 61 16 Solid Surface Fabrications 06-14

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 08 00 Facility Exterior Closure Commissioning 12-15 07 13 00 Sheet Waterproofing 06-14 07 13 52 Modified Bituminous Sheet Waterproofing 06-14 07 18 13 Pedestrian Traffic Coatings 01-21 07 21 13 Thermal Insulation 12-15 07 22 00 Roof and Deck Insulation 06-14 07 40 00 Roofing and Siding Panels 06-14 07 41 13 Standing Seam Metal Roofing 06-14 07 52 16 Styrene-Butadiene-Styrene Modified Bituminous Membrane

Roofing 06-14

07 60 00 Flashing and Sheet Metal 06-14 07 71 00 Roof Specialties 06-14 07 81 00 Applied Fireproofing 06-14 07 84 00 Firestopping 06-14 07 92 00 Joint Sealants 06-14

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 06-14 08 14 00 Interior Wood Doors 12-15 08 31 13 Access Doors and Frames 06-14 08 41 13 Aluminum-Framed Entrances and Storefronts 06-14 08 51 13 Aluminum Windows 06-14 08 71 00 Door Hardware 06-14 08 71 13.11 Low Energy Power Assist Door Operators 06-14 08 80 00 Glazing 06-14 08 90 00 Louvers and Vents 06-14

DIVISION 09 – FINISHES

00 01 10-3 Y:\16300\16362 TAHOMA NC PH3\_04 Specs\_07 Bid Docs Resubmit\000110 TOC NC Spec TNC3 BD.docx

09 05 16 Subsurface Preparation for Floor Finishes 01-22 09 22 16 Non-Structural Metal Framing 06-14 09 29 00 Gypsum Board 06-14 09 30 00 Specialty Moldings and Trims 09 30 13 Tiling 06-14 09 51 00 Acoustical Ceilings 06-14 09 65 13 Resilient Base and Accessories 06-14 09 65 19 Resilient Tile Flooring 06-14 09 65 36 Static Dissipative Tile Flooring 06-14 09 67 23.1 Resinous Flooring (RES-1) 06-14 09 67 23.2 Resinous Flooring (RES-2) 09 68 00 Carpeting 06-14 09 72 16 Vinyl Coated Fabric Wall Covering 09 77 00 Fiberglass Reinforced Wall Panels 09 80 00 Acoustic Treatment 09 84 11 Wall Mounted Acoustic Panels 09 91 00 Painting 06-14

DIVISION 10 – SPECIALTIES

10 11 13 Markerboards 06-14 10 14 00 Exterior Signage 06-14 10 14 05 Interior Signage 06-14 10 21 13 Toilet Compartments 06-14 10 28 00 Toilet and Bath Accessories 06-14 10 44 13 Fire Extinguisher Cabinets 06-14 10 51 00 Solid Plastic Lockers 06-14 10 51 26 Solid Plastic Cubbies

DIVISION 11 - EQUIPMENT

11 30 13 Small Commercial Appliances 11 83 00 Global Navigation Satellite System (GNSS) Reference

System 01-18

11 83 02 GNSS & GIS Mapping and Geodata 01-18

DIVISION 12 – FURNISHINGS

12 24 00 Window Shades 06-14 12 32 00 Manufactured Wood Casework 06-14 12 36 00 Countertops 12-18

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural

Components 01-21

13 34 19 Metal Building System

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 11-16 22 05 12 General Motor Requirements for Plumbing Equipment 11-16 22 05 19 Meters and Gages for Plumbing Piping 11-16

00 01 10-4 Y:\16300\16362 TAHOMA NC PH3\_04 Specs\_07 Bid Docs Resubmit\000110 TOC NC Spec TNC3 BD.docx

22 05 23 General-Duty Valves for Plumbing Piping 11-16 22 08 00 Commissioning of Plumbing Systems 12-15 22 11 00 Facility Water Distribution 11-16 22 13 00 Facility Sanitary Sewerage 11-16 22 13 29 Sanitary Sewerage Pumps 11-16 22 33 00 Electric Domestic Water Heaters 11-16 22 40 00 Plumbing Fixtures 11-16

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 11-16 23 05 12 General Motor Requirements for HVAC Equipment 11-16 23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment 11-16

23 05 93 Testing, Adjusting, and Balancing for HVAC 11-16 23 07 11 HVAC Insulation 11-16 23 08 00 Commissioning of HVAC Systems 12-15 23 09 24 Direct-Digital Control System for HVAC 11-16 23 11 23 Facility Natural-Gas Piping 11-16 23 23 00 Refrigerant Piping 11-16 23 31 00 HVAC Ducts and Casings 11-16 23 34 00 HVAC Fans 11-16 23 37 00 Air Outlets and Inlets 11-16 23 81 00 Unitary HVAC Equipment 11-16 23 82 33 Convectors 11-16 23 82 39 Unit Heaters 11-16

DIVISION 25 – INTEGRATED AUTOMATION

25 10 10 Advanced Utility Metering System 11-16

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 07-17 26 05 19 Low-Voltage Electrical Power Conductors and Cables 07-17 26 05 26 Grounding and Bonding for Electrical Systems 07-17 26 05 33 Raceway and Boxes for Electrical Systems 07-17 26 05 41 Underground Electrical Construction 07-17 26 05 73 Overcurrent Protective Device Coordination Study 07-17 26 08 00 Commissioning of Electrical Systems 12-15 26 24 13 Distribution Switchboards 07-17 26 24 16 Panelboards 07-17 26 27 26 Wiring Devices 07-17 26 29 21 Enclosed Switches and Circuit Breakers 07-17 26 32 13 Engine Generators 07-17 26 36 23 Automatic Transfer Switches 07-17 26 51 00 Interior Lighting 07-17 26 56 00 Exterior Lighting 07-17

DIVISION 27 – COMMUNICATIONS

27 05 00 Common Work Results for Communications 11-16

00 01 10-5 Y:\16300\16362 TAHOMA NC PH3\_04 Specs\_07 Bid Docs Resubmit\000110 TOC NC Spec TNC3 BD.docx

27 05 26 Grounding and Bonding for Communications Systems 11-16 27 05 33 Conduits and Backboxes for Communications Systems 11-16 27 08 00 Commissioning of Communication Systems 12-15 27 10 00 Structured Cabling 11-16 27 11 00 Communications Equipment Room Fittings 11-16

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 08 00 Commissioning of Electronic Safety and Security

Systems 12-15

28 10 00 Access Control 03-18 28 20 00 Video Surveillance 03-18 28 31 00 Intrusion Detection 03-18

DIVISION 31 – EARTHWORK

31 20 00 Earth Moving 11-16 31 23 19 Dewatering 11-16 31 23 23.33 Flowable Fill 11-16 31 32 23 Pressure Grouting Soil Stabilization 11-16

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 11-16 32 12 16 Asphalt Paving 11-16 32 17 23 Pavement Markings 11-16 32 31 13 Chain Link Fences and Gates 11-16 32 31 19 Decorative Metal Fences and Gates 11-16 32 33 00 Site Furnishings 01-17 32 84 00 Planting Irrigation 01-17 32 90 00 Planting 11-16 32 92 20 Native Seeding 32 94 00 Planting Accessories 12-20

DIVISION 33 – UTILITIES

33 08 00 Commissioning of Site Utility Systems 12-15 33 10 00 Water Utilities 11-16 33 30 00 Sanitary Sewerage Utilities 11-16 33 40 00 Storm Sewer Utilities 11-16 33 41 13 Foundation Drainage 01-17 33 51 00 Natural-Gas Distribution 11-16

Tahoma National Cemetery Ph 3 05-10

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

SHEET TITLE

GENERAL

GI001R COVER SHEET

GI002R SHEET INDEX

GI003 ABBREVIATIONS LEGEND

GI004 ADDITIVE ITEMS GENERAL INFORMATION

GI005 OVERALL

SURVEY

V-100 EXISTING CONDITIONS SURVEY 1

V-101 EXISTING CONDITIONS SURVEY 2

V-102 EXISTING CONDITIONS SURVEY 3

V-103 EXISTING CONDITIONS SURVEY 4

V-104 EXISTING CONDITIONS SURVEY 5

V-105 EXISTING CONDITIONS SURVEY 6

V-106 EXISTING CONDITIONS SURVEY 7

V-107 EXISTING CONDITIONS SURVEY 8

V-108 EXISTING CONDITIONS SURVEY 9

V-109 EXISTING CONDITIONS SURVEY 10

V-110 EXISTING CONDITIONS SURVEY 11

V-111 EXISTING CONDITIONS SURVEY 12

V-112 EXISTING CONDITIONS SURVEY 13

V-113 EXISTING CONDITIONS SURVEY 14

V-114 EXISTING CONDITIONS SURVEY 15

SUBSURFACE BORING INFORMATION

B-101 BORING TEST PIT LOCATIONS

B-102 BORING LOGS

B-103 BORING LOGS

B-104 BORING LOGS

B-105 BORING LOGS

B-106 BORING LOGS

DEMOLITION

CD101 OVERALL DEMOLITION PLAN - NORTH

CD102 OVERALL DEMOLITION PLAN - SOUTH

CD103 OVERALL DEMOLITION PLAN - SOUTHEAST

CD104 OVERALL DEMOLITION PLAN - SOUTHWEST

OPERATIONS

CO101 ACCESS & LOGISTICS OVERALL

00 01 15 - 2

CO102 ACCESS & LOGISTICS EXPANSION

CO103 ACCESS & LOGISTICS MEMORIAL WALL

TEMPORARY FACILITIES

AS101 COMMITTAL SERVICE SHELTER TEMPORARY BUILDING

AS102 COMMITTAL SERVICE SHELTER TEMPORARY BUILDING

AT101 ADMIN TEMPORARY TRAILER

AT102 MAINTENANCE TEMPORARY TRAILER

AT103 PIC TEMPORARY RESTROOM TRAILER

AT104 SENIOR RESIDENT ENGINEER TEMPORARY OFFICE

AT105 ADMIN TEMPORARY TRAILER - FURNITURE

AT106 MAINTENANCE TEMPORARY TRAILER - FURNITURE PLAN

SITE PLAN

C-001 PROJECT CONTROL PLAN

CS101 OVERALL CEMETERY SITE

CS102 PHASE 3 EXPANSION

CS103 PUBLIC INFORMATION CENTER BUILDING

CS104 TEMPORARY COMMITTAL SERVICE SHELTER

CS105 ADMIN. BLDG SITE PLAN & TEMPORARY TRAILERS

CS106 COMMITTAL SERVICE SHELTER 1 & 2 SITE PLAN

CS106 - AI1 HONOR GUARD BUILDING SITE PLAN

CS107 PUBLIC RESTROOM BUILDING

CS107 - AI2 PUBLIC RESTROOM BUILDING

CS108 MAINTENANCE FACILITIES

CS109 EXISTING COLUMBARIUM CAULKING PLAN

CS110 EXISTING FLAG ASSEMBLY WING WALL STONE VENEER PLAN

CS111-AI5 GREEN BURIAL SITE PLAN

CS501 CIVIL SITE DETAILS

SITE PLAN: BURIALS

CB101 PHASE 3 OVERALL GRAVESITE LAYOUT

CB102 GRAVESITE LAYOUT SECTIONS 14 & 15

CB103 GRAVESITE NUMBERING SECTIONS 14 & 15

CB104 GRAVESITE LAYOUT SECTION 16

CB105 GRAVESITE NUMBERING SECTION 16

CB106 GRAVESITE LAYOUT SECTION 17A & 17B

CB106-AI5 GRAVESITE LAYOUT SECTION 17

CB107 GRAVESITE NUMBERING SECTION 17A & 17B

CB107-AI5 GRAVESITE NUMBERING SECTION 17

CB108 GRAVESITE LAYOUT SECTION 18

CB109 GRAVESITE NUMBERING SECTION 18

CB110 GRAVESITE LAYOUT SECTIONS 19 & 20

CB111 GRAVESITE NUMBERING SECTIONS 19 & 20

00 01 15 - 3

CB112 GRAVESITE LAYOUT SECTION 21

CB113 GRAVESITE NUMBERING SECTION 21

CB501 CRYPT DETAILS

CB502 CRYPT DETAILS

CB503 CRYPT DETAILS

COLUMBARIUM & MEMORIAL WALL: FOUNDATION PLAN

LS101 COLUMBARIUM 6 OVERALL FOUNDATION LAYOUT PLAN

LS101.1 COLUMBARIUM 6 FOUNDATION LAYOUT ENLARGEMENT 1

LS101.2 COLUMBARIUM 6 FOUNDATION LAYOUT ENLARGEMENT 2

LS102 COLUMBARIUM 7 OVERALL FOUNDATION LAYOUT PLAN

LS102.1 COLUMBARIUM 7 FOUNDATION LAYOUT ENLARGEMENT 1

LS102.2 COLUMBARIUM 7 FOUNDATION LAYOUT ENLARGEMENT 2

LS103 COLUMBARIUM 8 OVERALL FOUNDATION LAYOUT PLAN

LS103.1 COLUMBARIUM 8 FOUNDATION LAYOUT ENLARGEMENT 1

LS103.2 COLUMBARIUM 8 FOUNDATION LAYOUT ENLARGEMENT 2

LS103.3 COLUMBARIUM 8 FOUNDATION LAYOUT ENLARGEMENT 3

LS104 MEMORIAL WALL FOUNDATION LAYOUT PLAN

COLUMBARIUM & MEMORIAL WALL: PRECAST UNIT LAYOUT PLAN

LS111 COLUMBARIUM 6 PRECAST UNIT LAYOUT PLAN

LS112 COLUMBARIUM 7 PRECAST UNIT LAYOUT PLAN

LS113 COLUMBARIUM 8 PRECAST UNIT LAYOUT PLAN

COLUMBARIUM & MEMORIAL WALL: LAYOUT & JOINTING PLAN

LS121 COLUMBARIUM 6 LAYOUT & JOINTING PLAN

LS122 COLUMBARIUM 7 LAYOUT & JOINTING PLAN

LS123 COLUMBARIUM 8 LAYOUT & JOINTING PLAN

LS124 MEMORIAL WALL LAYOUT & JOINTING PLAN

COLUMBARIUM & MEMORIAL WALL: CAP LAYOUT

LS131 COLUMBARIUM 6 CAP LAYOUT

LS132 COLUMBARIUM 7 CAP LAYOUT

LS133 COLUMBARIUM 8 CAP LAYOUT

LS134 MEMORIAL WALL CAP LAYOUT

COLUMBARIUM & MEMORIAL WALL: ADDRESSING PLAN

LS141 COLUMBARIUM 6 ADDRESSING PLAN

LS142 COLUMBARIUM 7 ADDRESSING PLAN

LS143 COLUMBARIUM 8 ADDRESSING PLAN

LS144 MEMORIAL WALL ADDRESSING PLAN

COLUMBARIUM & MEMORIAL WALL: ELEVATIONS

LS201 COLUMBARIUM ELEVATIONS 1

LS202 COLUMBARIUM ELEVATIONS 2

LS203 COLUMBARIUM ELEVATIONS 3

LS204 COLUMBARIUM ELEVATIONS 4

00 01 15 - 4

LS205 COLUMBARIUM ELEVATIONS 5

LS206 COLUMBARIUM ELEVATIONS 6

LS207 COLUMBARIUM ELEVATIONS 7

LS208 COLUMBARIUM ELEVATIONS 8

LS209 COLUMBARIUM ELEVATIONS 9

LS210 COLUMBARIUM & MEMORIAL WALL ELEVATIONS

COLUMBARIUM & MEMORIAL WALL: SECTIONS

LS301 COLUMBARIUM SECTIONS

LS302 COLUMBARIUM & MEMORIAL WALL SECTIONS

LS303 COLUMBARIUM SEATWALL & RETAINING WALL

LS304 COLUMBARIUM SEATWALL & RETAINING WALL DETAILS

COLUMBARIUM & MEMORIAL WALL: ENLARGEMENT PLANS

LS401 COLUMBARIUM COLUMN ENLARGEMENTS 1

LS402 COLUMBARIUM COLUMN ENLARGEMENTS 2

LS403 COLUMBARIUM PLAN ENLARGEMENTS

COLUMBARIUM & MEMORIAL WALL: DETAILS

LS501 PRECAST COLUMBARIUM UNIT DETAILS

LS502 CAP PROFILE & PANEL DETAILS

LS503 CAP DETAILS 1

LS504 CAP DETAILS 2

LS505 CAP DETAILS 3

LS506 CAP DETAILS 4

LS507 TYPICAL DETAILS

LS508 TYPICAL DETAILS

COLUMBARIUM & MEMORIAL WALL: GRADING & DRAINAGE PLANS

LG101 COLUMBARIUM 6 GRADING & DRAINAGE PLAN

LG102 COLUMBARIUM 7 GRADING & DRAINAGE PLAN

LG103 COLUMBARIUM 8 GRADING & DRAINAGE PLAN

LG104 MEMORIAL WALL GRADING & DRAINAGE PLAN

LG105 ASSEMBLY AREA GRADING & DRAINAGE PLAN

COLUMBARIUM & MEMORIAL WALL: UTILITY PLAN

LU101 COLUMBARIUM 6 UTILITY PLAN

LU102 COLUMBARIUM 7 UTILITY PLAN

LU103 COLUMBARIUM 8 UTILITY PLAN

LU104 MEMORIAL WALL UTILITY PLAN

GRADING

CG101 OVERALL GRADING AND DRAINAGE PLAN

CG102 GRADING AND DRAINAGE PLAN

CG103 GRADING AND DRAINAGE PLAN

CG104 GRADING AND DRAINAGE PLAN

CG104 - AI5 GRADING AND DRAINAGE PLAN

00 01 15 - 5

CG105 GRADING AND DRAINAGE PLAN

CG105 - AI2 GRADING AND DRAINAGE PLAN

CG106 GRADING AND DRAINAGE PLAN

CG107 GRADING AND DRAINAGE PLAN

CG107 - AI1 GRADING AND DRAINAGE PLAN

CG108 GRADING AND DRAINAGE PLAN

CG109 GRADING AND DRAINAGE PLAN

CG110 GRADING AND DRAINAGE PLAN

CG111 GRADING AND DRAINAGE PLAN

CG113 GRADING AND DRAINAGE PLAN

CG113 GRADING AND DRAINAGE PLAN

CG114 GRADING AND DRAINAGE PLAN

CG115 GRADING AND DRAINAGE PLAN

STREET PLAN & PROFILE

CR101 NORTH STREET PLAN

CR102 EAST STREET PLAN

CR103 SOUTH STREET PLAN

CR104 WEST STREET PLAN

CR105 ROAD A - STA 0+00 TO 5+50

CR105 - AI2 ROAD A - STA 0+00 TO 5+50

CR106 ROAD A - STA 5+50 TO 11+00

CR107 ROAD A - STA 11+00 TO 16+50

CR108 ROAD A - STA 16+50 TO 21+00

CR109 ROAD A - STA 21+00 TO 26+47

CR110 SERVICE DRIVE - STA. 0+00 TO 4+23

CR111 MUNRO MEMORIAL DRIVE 0+00 TO 6+00

CR112 MUNRO MEMORIAL DRIVE 6+00 TO 12+00

CR113 MUNRO MEMORIAL DRIVE 12+00 TO 17+00

CR114 MUNRO MEMORIAL DRIVE 17+00 TO 20+87

CR301 STREET CROSS SECTIONS

CR501 STREET DETAILS

CR502 STREET DETAILS

EROSION CONTROL

CE001 OVERALL TEMPORARY EROSION CONTROL PLAN

CE101 TEMPORARY EROSION CONTROL PLAN

CE101 - AI2 TEMPORARY EROSION CONTROL PLAN

CE102 TEMPORARY EROSION CONTROL PLAN

CE102 - AI2 TEMPORARY EROSION CONTROL PLAN

CE102 - AI5 TEMPORARY GREEN BURIAL EROSION PLAN

CE103 TEMPORARY EROSION CONTROL PLAN

CE104 TEMPORARY EROSION CONTROL PLAN

00 01 15 - 6

CE104 - AI1 TEMPORARY EROSION CONTROL PLAN

CE105 TEMPORARY EROSION CONTROL PLAN

CE106 TEMPORARY EROSION CONTROL PLAN

UTILITIES

CU101 OVERALL UTILITY PLAN

CU102 UTILITY PLAN

CU103 UTILITY PLAN

CU104 UTILITY PLAN

CU105 UTILITY PLAN

CU105 - AI2 UTILITY PLAN

CU106 UTILITY PLAN

CU107 UTILITY PLAN

CU107 - AI1 UTILITY PLAN

CU108 UTILITY PLAN

CU109 UTILITY PLAN

CU110 UTILITY PLAN

CU111 UTILITY PLAN

CU112 UTILITY PLAN

CU113 UTILITY PLAN

CU114 UTILITY PLAN

CU115 UTILITY PLAN

CU116 UNDERDRAIN PLAN - SECTION 14 & 15

CU117 UNDERDRAIN PLAN - SECTION 16

CU501 DRAINAGE DETAILS

CU502 DRAINAGE DETAILS

CU503 POND DETAILS

UTILITIES: STORM UTILITIES

CP101 STORM - CBMH 110A TO CBMH 115

CP102 STORM - CBMH 115 TO FES 120

CP103 STORM - CB 139 TO FES 142

CP106 STORM - FES 152 TO FES 157

CP105 STORM - CB 146 TO FES 151

CP106 STORM - FES 152 TO FES 157

CP107 STORM - CB 142A TO FES 145

CP108 STORM - CB 129 TO FES 133

WASTEWATER

CW001 OSS GENERAL CONSTRUCTION

CW401 - AI1 HONOR GUARD OSS PLAN

CW402 - AI2 SATELLITE RESTROOM OSS PLAN

CW501 OSS DETAILS 1

CW502 OSS DETAILS 2

00 01 15 - 7

CW503 OSS DEATILS 3

WAYFINDING & SITE FURNISHINGS

LK101 OVERALL SITE FURNISHING & SIGNAGE LAYOUT PLAN

LK401 SITE FURNISHING & SIGNAGE LAYOUT PLAN

LK402 SITE FURNISHING & SIGNAGE LAYOUT PLAN

LK403 SITE FURNISHING & SIGNAGE LAYOUT PLAN

LK403 - AI1 SITE FURNISHING & SIGNAGE LAYOUT PLAN

LK404 SITE FURNISHING & SIGNAGE LAYOUT PLAN

LK405 SITE FURNISHING & SIGNAGE LAYOUT PLAN

LK501 SIGNAGE DETAILS 1

LK406 COLUMBARIUM SITE FURNISHING & SIGNAGE LAYOUT PLAN ENLG

LK501 SIGNAGE DETAILS 1

LK502 SIGNAGE DETAILS 2

LK503 SIGNAGE DETAILS 3

LK504 SIGNAGE DETAILS 4

LK505 SIGNAGE DETAILS 5

LK506 SITE FURNISHING DETAILS 1

LK507 SITE FURNISHING DETAILS 2

PLANTING

LP101 OVERALL RESTORATION PLAN

LP102 RESTORATION PLAN

LP103 RESTORATION PLAN

LP104 RESTORATION PLAN

LP104 - AI5 RESTORATION PLAN

LP105 RESTORATION PLAN

LP105 - AI2 RESTORATION PLAN

LP106 RESTORATION PLAN

LP107 RESTORATION PLAN

LP107 - AI1 RESTORATION PLAN

LP108 RESTORATION PLAN

LP109 RESTORATION PLAN

LP110 RESTORATION PLAN

LP111 RESTORATION PLAN

LP112 RESTORATION PLAN

LP113 RESTORATION PLAN

LP114 RESTORATION PLAN

LP115 RESTORATION PLAN

LP201 COLUMBARIUM 6 LANDSCAPE PLAN

LP202 COLUMBARIUM 7 LANDSCAPE PLAN

LP203 COLUMBARIUM 8 LANDSCAPE PLAN

LP204 ADMINISTRATION BUILDING

00 01 15 - 8

LP501 PLANTING DETAILS

LP502 PLANTING DETAILS

LP601 PLANT SCHEDULE

LP602-AI ADDITIVE ITEMS PLANT SCHEDULES

IRRIGATION

IR101 PHASE 3 EXPANSION IRRIGATION

IR102 OVERALL IRRIGATION MAINLINE PLAN

IR103 OVERALL IRRIGATION MAINLINE PLAN

IR104 OVERALL IRRIGATION MAINLINE PLAN

IR105 OVERALL IRRIGATION MAINLINE PLAN

IR106 OVERALL IRRIGATION MAINLINE PLAN

IR102B PHASE 3 EXPANSION IRRIGATION

IR103B PHASE 3 EXPANSION IRRIGATION

IR104B PHASE 3 EXPANSION IRRIGATION

IR104-AI5 SITE IRRIAGATION PLAN

IR105B PHASE 3 EXPANSION IRRIGATION

IR106B PHASE 3 EXPANSION IRRIGATION

IR107B PHASE 3 EXPANSION IRRIGATION

IR105 - AI2 PHASE 3 EXPANSION IRRIGATION - ADDITIVE ITEM 2

IR107 - AI3 PHASE 3 EXPANSION IRRIGATION - ADDITIVE ITEM 3

IR108 - AI3 PHASE 3 EXPANSION IRRIGATION - ADDITIVE ITEM 3

IR109 - AI3 PHASE 3 EXPANSION IRRIGATION - ADDITIVE ITEM 3

IR110 - AI3 PHASE 3 EXPANSION IRRIGATION - ADDITIVE ITEM 3

IR111 - AI3 PHASE 3 EXPANSION IRRIGATION - ADDITIVE ITEM 3

IR112 - AI3 PHASE 3 EXPANSION IRRIGATION - ADDITIVE ITEM 3

IR115 - AI3 PHASE 3 EXPANSION IRRIGATION - ADDITIVE ITEM 3

IR114 - AI3 PHASE 3 EXPANSION IRRIGATION - ADDITIVE ITEM 3

IR115 - AI3 PHASE 3 EXPANSION IRRIGATION - ADDITIVE ITEM 3

IR501 IRRIGATION DETAILS

IR502 IRRIGATION DETAILS

IR503 IRRIGATION DETAILS

ARCHITECTURE

A-001 LEGENDS, ABBREVIATIONS, AND NOTES

A-002 GENERAL DETAILS

A-101-1301 ADMINISTRATION BUILDING - LIFE SAFETY PLAN

A-101-1401 PUBLIC INFORMATION CENTER - LIFE SAFETY PLAN

A-101-1501-AI2 SATELLITE PUBLIC RESTROOM - LIFE SAFETY PLAN

A-101-3401-AI1 HONOR GUARD BUILDING - LIFE SAFETY PLAN

A-102-1301 ADMINISTRATION BUILDING - DEMO FLOOR PLAN & DEMO RCP

A-102-1401 PUBLIC INFORMATION CENTER - DEMO FLOOR AND ROOF PLANS

A-102-1501-AI2 SATELLITE PUBLIC RESTROOM - FLOOR, RCP & ROOF PLAN

00 01 15 - 9

A-102-3001 TYPICAL STORAGE BINS - FLOOR PLAN & ROOF PLAN

A-102-3401-AI1 HONOR GUARD BLDG - FLOOR PLAN, RCP AND ROOF PLAN

A-102-CSS TYPICAL COMMITTAL SHELTER & STORAGE BUILDING

A-103-1301 ADMINISTRATION BUILDING - FLOOR PLAN AND RCP PLAN

A-103-1401 PUBLIC INFORMATION CENTER - FLOOR PLAN AND ROOF PLAN

A-104-1301 ADMINISTRATION BUILDING - SECOND FLOOR AND ROOF PLAN

A-201-1301 ADMINISTRATION BUILDING - EXTERIOR ELEVATIONS

A-201-1401 PUBLIC INFORMATION CENTER - EXTERIOR ELEVATIONS

A-201-1501-AI2 SATELLITE PUBLIC RESTROOM - EXTERIOR ELEVATIONS

A-201-3001 TYPICAL STORAGE BINS - SECTIONS AND ELEVATIONS

A-201-3401-AI1 HONOR GUARD BUILDING - EXTERIOR ELEVATIONS

A-201-CSS COMMITTAL SHELTER AND STORAGE BUILDING ELEVATIONS

A-301 - 1301 ADMINISTRATION BUILDING - SECTIONS

A-302 - 1301 ADMINISTRATION BUILDING - SECTIONS

A-301-1501-AI2 SATELLITE PUBLIC RESTROOM - BUILDING SECTIONS

A-301-3401-AI1 HONOR GUARD BUILDING - SECTIONS

A-301-CSS COMMITTAL SERVICE SHELTER AND STORAGE BLDGS - SECTIONS

A-351 HONOR GUARD & RESTROOM - WALL SECTIONS AND DETAILS

A-351 - 1301 ADMINISTRATION BUILDING - WALL SECTIONS

A-352 - 1301 ADMINISTRATION BUILDING - WALL SECTIONS

A-353 - 1301 ADMINISTRATION BUILDING - WALL SECTIONS

A-401-1301 ADMINISTRATION BUILDING - ENLARGED FLOOR PLANS

A-501 - 3001 TYPICAL STORAGE BINS - DETAILS

A-502 - 1301 ADMINISTRATION BUILDING - LOBBY WALL DETAIL

A-503 - 1301 ADMINISTRATION BUILDING - SECTION DETAILS

A-504 - 1301 ADMINISTRATION BUILDING - PLAN DETAILS

A-505 PARTITION TYPES AND DETAILS

A-506 SATELLITE RESTROOM AND HONOR GUARD - DETAILS

A-611 DOOR AND FRAME TYPES, SCHEDULES AND DETAILS

A-612 WINDOWS AND LOUVERS TYPES AND DETAILS

A-613 SSMR ROOF DETAILS AND LOUVER DETAILS

INTERIORS

I-001 MATERIALS SCHEDULE & GENERAL NOTES

I-002 INTERIOR DETAILS

I-003 INTERIOR DETAILS

IA100 ADMINISTRATION BULDING - EXISTING FURNITURE PLAN

IA101 ADMINISTRATION BUILDING - FINISH PLAN

IA102 ADMINISTRATION BUILDING - FURNITURE & EQUIPMENT PLAN

IA201

ADMINISTRATION BUILDING - ENLARGED PLANS & INTERIOR

ELEVATIONS

IA202 ADMINISTRATION BUILDING - INTERIOR ELEVATIONS

IB101-AI1 HONOR GUARD BLDG - FINISH & EQUIPMENT PLAN & INTERIOR

00 01 15 - 10

ELEVATION

IC101-AI2

PUBLIC RESTROOM - FINISH & EQUIPMENT PLAN & INTERIOR

ELEVATION

ID-101 P.I.C BUILDING - FINISH PLAN & INTERIOR ELEVATIONS

STRUCTURAL

S-001 STRUCTURAL NOTES AND DRAWING LIST

S-002 STRUCTURAL NOTES AND INSPECTION SCHEDULE

S-021 STRUCTURAL ABBREVIATIONS AND SYMBOLS

S-101-1301 ADMINISTRATION BUILDING FOUNDATION PLAN

S-102-1301 ADMINISTRATION BUILDING FRAMING PLANS

S-201-1301 ADMINISTRATION BUILDING - FRAMING ELEVATIONS

S-401-1301 ADMINISTRATION BUILDING ENLARGED PLANS

S-402-1301 ADMINISTRATION BUILDING ENLARGED PLANS

S-501-1301 ADMINISTRATION BUILDING STEEL DETAILS

S-502-1301 ADMINISTRATION BUILDING STEEL DETAILS

S-503-1301 ADMINISTRATION BUILDING STEEL DETAILS

S-101-3401 - AI1 HONOR GUARD BUILDING PLANS

S-201 -3401 - AI1 HONOR GUARD BUILDING - FRAMING ELEVATION

S-511-3401 - AI1 HONOR GUARD BUILDING CMU WALL DETAILS

S-521 -3401 - AI1 HONOR GUARD BUILDING ROOF DETAILS

S-522 -3401 - AI1 HONOR GUARD BUILDING ROOF DETAILS

S-101-1501 - AI2 SATELLITE PUBLIC RESTROOM PLANS

S-201-1501 - AI2 SATELLITE PUBLIC RESTROOM - FRAMING ELEVATIONS

S-101-3G01 STORAGE BIN PLANS

S-501-3G01 STORAGE BIN DETAILS

S-101-3002 QUONSET CONCEPT FOUNDATION PLAN AND BUILDING SECTION

SS101 COLUMBARIUM 6 FOUNDATION PLAN

SS102 COLUMBARIUM 7 FOUNDATION PLAN

SS103 COLUMBARIUM 8 FOUNDATION PLAN

SS301 COLUMBARIUM COLUMN DETAILS

SS302 COLUMBARIUM COLUMN DETAILS

SS303 COLUMBARIUM FOUNDATION DETAILS

SS304 COLUMBARIUM FOUNDATION DETAILS

SS501 COLUMBARIUM TYPICAL CMU DETAILS

SW101 SITE WALL FOUNDATION PLANS

SW501 SITE WALL FOUNDATION DETAILS

S-501 TYPICAL CONCRETE DETAILS

S-502 TYPICAL CONCRETE DETAILS

S-503 CONCRETE SECTIONS AND DETAILS

S-504 CONCRETE SECTIONS AND DETAILS

S-511 TYPICAL STEEL DETAILS

S-512 TYPICAL STEEL DETAILS

00 01 15 - 11

S-513 TYPICAL STEEL DETAILS

S-521 TYPICAL COLD-FORMED STEEL FRAMING DETAILS

S-522 TYPICAL COLD-FORMED STEEL FRAMING DETAILS

S-523 TYPICAL COLD-FORMED STEEL FRAMING DETAILS

MECHANICAL

M-001 LEGEND, ABBREVIATIONS, AND NOTES - MECHANICAL

M-101-1301 ADMINISTRATION BUILDING FLOOR PLANS - HVAC DEMOLITION PLAN

M-101-1401 PUBLIC INFORMATION BUILDING- HVAC DEMOLITION PLAN

M-101-1501-AI2 SATELLITE PUBLIC RESTROOM BUILDING - HVAC NEW WORK PLAN

M-101-3401-AI1 HONOR GUARD BUILDING - HVAC NEW WORK PLAN

M-102-1301 ADMINISTRATION BUILDING FLOOR PLANS - HVAC NEW WORK PLAN

M-102-1401 PUBLIC INFORMATION CENTER - HVAC NEW WORK PLAN

M-201-1301 ADMINISTRATION BUILDING - SECTIONS

M-201-1401 PUBLIC INFORMATION CENTER - SECTIONS

M-201-1501-AI2 SATELLITE PUBLIC RESTROOM BUILDING - SECTIONS

M-502 MECHANICAL DETAILS

M-501 MECHANICAL DETAILS

M-502 MECHANICAL DETAILS

M-601 MECHANICAL SCHEDULES

M-801

CONTROL SCHEMATIC, CONTROL SCHEDULES AND LEGEND -

MECHANICAL

M-802

CONTROL SCHEMATIC, CONTROL SCHEDULES AND LEGEND -

MECHANICAL

PLUMBING

P-001 LEGEND, ABBREVIATIONS, NOTES, AND SHEET INDEX - PLUMBING

P-101-1401 P.I.C PLUMBING PLAN-SANITARY AND WATER NEW WORK

P-101-1501-AI2 SATELLITE PUBLIC RESTROOM PLUMBING PLAN

P-101-1301 ADMINISTRATION BUILDING PLUMBING PLAN - UNDERGROUND

P-101- 3401-AI1

HONOR GUARD BUILDING PLUMBING PLAN- SANITARY AND WATER-

NEW WORK

P-102-1301 ADMINISTRATION BUILDING PLUMBING PLAN - EXISTING & DEMO

P-103-1301 ADMINISTRATION BUILDING PLUMBING PLAN - WATER NEW

P-401-1301 PLUMBING ENLARGED PLANS

P-601 PLUMBING SCHEDULES

P-602 PLUMBING DETAILS

P-901 3D PLUMBING RISERS

GNSS

X-101 GNSS PLAN

X-501 GNSS DETAILS

ELECTRICAL

ES000 ELECTRICAL NOTES, ABBREVIATIONS AND LEGEND

ED-001-1301 ADMIN BLDG ELECT DEMOLITION SITE PLAN

00 01 15 - 12

ES001 ELECTRICAL OVERALL CEMETERY SITE PLAN

ES-001-1301 ADMIN BUILDING ENLARGED ELECTRICAL SITE PLAN

ES-001-3401 - AI1 HONOR GUARD BUILDING ENLARGED ELECTRICAL SITE PLAN

ES-001-1501 - AI2 SATELLITE PUBLIC RESTROOM ENLARGED ELECTRICAL SITE PLAN

ES-001-3001 MAINTENANCE YARD ELECTRICAL SITE PLAN

ED-100-1301 ADMIN BUILDING - DEMOLITION PLAN

E-101-1301 ADMIN BUILDING - POWER PLAN

E-102-1301 ADMIN BUILDING - LIGHTING PLAN

E-101-1401 PUBLIC INFORMATION CENTER - ELECTRICAL

E-101-1501 - AI2 SATELLITE PUBLIC RESTROOM - ELECTRICAL

E-101-3401 - AI1 HONOR GUARD BUILDING - ELECTRICAL

E-101-CSS COMMITTAL SERVICE SHELTER - ELECTRICAL

E-401 ELECTRICAL ROOM- ENLARGED PLAN

E-501 ELECTRICAL RISER DIAGRAM AND FEEDER SCHEDULE

E-601 ELECTRICAL SCHEDULES

E-602 ELECTRICAL SCHEDULES

E-603 ELECTRICAL SCHEDULES

E-604 ELECTRICAL - ENERGY COMPLIANCE

E-605 ELECTRICAL - ENERGY COMPLIANCE

E-606 ELECTRICAL - ENERGY COMPLIANCE

E-607 ELECTRICAL - ENERGY COMPLIANCE

TECHNOLOGY & SITE SECURITY

T-001 TECHNOLOGY COVERSHEET

TS101 SITE PLAN - OVERALL

TS102 SITE PLAN - ADMIN. BLDG.

TS103-AI1 HONOR GUARD BUILDING SITE PLAN

TS104 PUBLIC INFORMATION CENTER BUILDING

TS105 WATER METER & MATERIALS SHED

TA101A ADMIN. BLDG. FLOOR PLAN - SEGMENT A

TA101B ADMIN. BLDG. FLOOR PLAN - SEGMENT B

TA100A ADMIN. BLDG. FLOOR PLAN - DEMO - SEGMENT A

TA100B ADMIN. BLDG. FLOOR PLAN - DEMO - SEGMENT B

TB101-AI1 HONOR GUARD BUILDING FLOOR PLAN AI1

TD101 PUBLIC INFORMATION CENTER BUILDING FLOOR PLAN

TE101-AI2 PUBLIC RESTROOM FLOOR PLAN AI2

T-300 ENLARGED PLANS - TECHNOLOGY

T-400 TECHNOLOGY DETAILS

T-401 TECHNOLOGY DETAILS

T-500 TECHNOLOGY DIAGRAMS

T-501 TECHNOLOGY DIAGRAMS

T-600 TECHNOLOGY SCHEDULES

00 01 15 - 13

T-601 TECHNOLOGY SCHEDULES

Tahoma National Cemetery Ph 3 06-01-14

GENERAL REQUIREMENTS 010001 - 1

SECTION 01 00 01

GENERAL REQUIREMENTS

1.1 GENERAL INTENTION

A. Contractor shall prepare portions of the existing cemetery site for additional cemetery operations, that includes but is not limited to, demolition and removal of existing improvements, clearing and grubbing, erosion control, and furnish labor and materials and perform work for the construction that includes but is not limited to new roadways, repair of existing roadways, building renovations, drainage improvements, columbaria, committal shelters, pre-placed crypts, cremains, memorial wall, landscaping, irrigation, GPS/GIS work and utilities as required by drawings and specifications. See Article 1.2 for a descriptive breakdown of the Base Bid work and Additive Items.

B. Visits to the site by Bidders may be made only by appointment with the Cemetery Director, Mr. Thomas Yokes.

Tahoma National Cemetery

18600 SE 240th St

Kent, WA 98042.

425-413-9614

C. Offices of Anderson Engineering of Minnesota, as Consulting

Architect-Engineers for the Government, will render certain technical services to the Government during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Resident Engineer

(RE) or duly authorized Contracting Officer Representative (COR).

Where the terms COR/SRE or RE/COR or COTR or similar are used within this specification they shall be considered synonymous and refer to the Department of Veterans Affairs Contracting Officers

GENERAL REQUIREMENTS 010001 - 2

Representative and/or Resident Engineer staff that may be assigned to the project.

D. All Testing Laboratory services will be retained and paid for by the Contractor (see Spec. Section 01 45 29 Testing Laboratory

Services). However, the Department of Veterans Affairs may elect to retain its own Testing Laboratory for any purpose. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the general contractor shall notify the RE/COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall not be less than three working days unless otherwise designated by the RE/COR.

E. RE/COR shall be notified at least two weeks prior to any work being permanently covered up.

F. All employees of general contractor and subcontractors shall comply with VA security management program.

G. Prior to commencing work, general contractor shall provide proof that a OSHA certified “competent person” (CP) (29 CFR

1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.

H. Training:

1. All employees of general contractor or subcontractors having supervisory responsibilities shall have the 30-hour OSHA certified Construction Safety course and/or other relevant competency training, as determined by VA CP. All other employees of general contractor or subcontractors shall have the 10-hour OSHA certified Construction Safety course and/or other relevant competency training, as determined by VA CP.

2. Submit training records of all such employees to RE/COR for approval before the start of work.

GENERAL REQUIREMENTS 010001 - 3

3. Contractor will submit an injury and illness report, monthly, in a format approved by the RE/COR to include but not limited to: number of man-hours worked for the month, cumulative man-hours worked during the year, any injuries reported.

1.2 STATEMENT OF BID ITEM(S)

A. CLIN 001 – GENERAL CONSTRUCTION, BASE BID: Work includes but is not limited to general construction, alterations, site preparation, mass excavation and earthwork, roads, walks, grading, drainage, electrical work, water and irrigation, landscaping, installation of 1600 pre-placed double-depth crypts, 400 pre-placed double-depth oversized crypts, construction of 18,532 niche columbaria, construction of 7,430 cremains gravesites, 288 traditional gravesites, 300 green burial gravesites, 2 memorial walls, GPS

Base unit and appurtenant items and create GIS network (the scope of which is detailed in the Specifications), including work inside of the Administration Building that is part of this system, physical security improvements required to make the facility current to VA PACS standards, HVAC improvements, construct new temp. committal service shelter, repair and upgrade three existing committal service shelters, Public Information

Center (PIC), Administration Building improvements, roadway and building site improvements.

B. CLIN 002, CRYPTS – Manufacture, delivery, and off-loading at site of 1,600 double-depth crypts, 400 double-depth oversized crypts.

C. CLIN 003, ADDITIVE ITEM 1 – This includes the construction of

Honor Guard Building and all associated enabling and utilities works as indicated in the construction documents and specifications.

D. CLIN 004, ADDITIVE ITEM 2 – This includes the construction of

Satellite Restroom Building and all associated enabling and utilities works as indicated in the construction documents and specifications.

GENERAL REQUIREMENTS 010001 - 4

E. CLIN 005, ADDITIVE ITEM 3 – This includes the replacement of the existing mainline irrigation piping, associated sub-mainline piping, valves, and controls, and associated enabling and utilities works as indicated in the construction documents and specifications.

F. CLIN 006, ADDITIVE ITEM 4 – This includes a Defined Construction

Period (DCP) of 18 months or less for the Admin Building Area additions and renovations as indicated in the construction documents and specifications.

G. CLIN 007, ADDITIVE ITEM 5 – This includes the replacement of Base

Bid (CLIN 001) construction items within limits of Additive Item

5. Construct Green Burial section as shown on Additive Item 5 plan sheets and specification. This includes, but is not limited to, site clearing, preservation of significant trees, earthwork, walks, paths, irrigation and site restoration.

1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Contract documents will be provided to the contractor in PDF electronic format. The contractor is responsible for printing hardcopies of the contract documents. The contractor, at a minimum, shall have two full-size sets of contract documents, including Specifications and Amendments (if any) and Change

Orders (if any), at the jobsite at all times.

1.4 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project. The security plan shall be submitted to the VA for review no later than 15 days after notice to proceed.

GENERAL REQUIREMENTS 010001 - 5

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without an appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. For working outside the “regular hours” defined as 8:00 AM to

4:30 PM, The General Contractor shall give 3 days notice to the RE/COR so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA employees or their vehicles is allowed without written permission of the RE/COR.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the

RE/COR.

C. Guards:

1. The General Contract shall provide unarmed guards at the project site if deemed necessary because of vandalism or theft within the contract work areas.

2. The guard shall have communication devices to report events as directed by Local Police Department and VA police.

3. Secure the project site, work in progress, materials, tools, equipment and any other materials within the project site that are not under operational control of the Cemetery staff. The use of guards is a Contractor responsibility, if deemed

GENERAL REQUIREMENTS 010001 - 6

necessary because of ongoing theft and/or vandalism within the project work area. Coordinate the use of guards with the RE following input from the Cemetery Operations through the RE.

Any guards provided shall be able to communicate with the local police.

D. Key Control:

1. Provide duplicate keys and lock combinations to the RE/COR for the purpose of security inspections of every area of project, to take any emergency action(s), for general access, and inspections, to remain in RE/COR possession.

2. Install permanent lock cylinders one day prior to the VA final inspection or on a date chosen by the SRE. The Contractor shall coordinate the lock cylinder and key system work and shall provide the devices required to comply with the facility security system. See Section 08 71 00, DOOR HARDWARE and coordinate.

E. Document Control:

1. Before starting any work, submit an electronic security memorandum, from the Contractor and each Subcontractor describing the actions to be performed to achieve the goals of maintaining confidentiality of “sensitive information”.

2. Perform safekeeping procedures for all drawings, project manual and other project information. The information from these shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or

“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the RE/COR upon request.

GENERAL REQUIREMENTS 010001 - 7

4. These security documents shall not be removed or transmitted from the project site without the written approval of the

RE/COR.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the

VA.

6. Notify RE/COR immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in a specified location following VA standards and procedures using an

Engineering Document Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

F. Motor Vehicle Restrictions

1. All motor vehicles shall follow designated access routes and are not to interfere with Cemetery operations or visitor access. Parking will be restricted to designated areas.

1.5 FIRE SAFETY

A. Applicable Publications: Publications listed below form part of this Article to the extent referenced. Publications are referenced in text by basic designations only.

1. American Society for Testing and Materials (ASTM):

E84-2013...........Surface Burning Characteristics of Building

Materials

GENERAL REQUIREMENTS 010001 - 8

2. National Fire Protection Association (NFPA):

10-2013............Standard for Portable Fire Extinguishers

30-2012............Flammable and Combustible Liquids Code

51B-2014...........Standard for Fire Prevention During

Welding, Cutting and Other Hot Work

70-2011............National Electrical Code

241-2013...........Standard for Safeguarding Construction, Alteration, and Demolition Operations

3. Occupational Safety and Health Administration (OSHA):

29 CFR 1926........Safety and Health Regulations for

Construction

B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to RE/COR/Cemetery

Director for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND

SAMPLES. The Fire Safety Plan may be incorporated into the

Accident Prevention Plan required per Specification Section 01 35

26, Safety Requirements. Prior to any worker for the contractor or subcontractor’s beginning work, they shall undergo a safety briefing provided by the General Contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of NCA equipment, etc. Documentation shall be provided to the RE/COR that individuals have undergone the Contractor’s safety briefing.

C. Site and Building Access: Maintain free and unobstructed access to emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.

GENERAL REQUIREMENTS 010001 - 9

D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m

(10 feet).

E. Temporary Construction Partitions:

1. Install and maintain temporary construction partitions to provide smoke-tight separations between construction areas that are described in sequencing requirements and adjoining areas. Construct partitions of gypsum board or treated plywood

(flame spread rating of 25 or less in accordance with ASTM

E84) on both sides of fire retardant treated wood or metal steel studs. Extend the partitions through suspended ceilings to floor slab deck or roof. Seal joints and penetrations to maintain negative air pressure within the work areas. At door openings, install Class C, ¾ hour fire/smoke rated doors with self-closing devices.

2. Install temporary construction partitions as required for sequencing requirements shown on drawings and maintain integrity of existing exit passageways, fire-rated enclosures of hazardous areas, horizontal exits, smoke barriers, and opening enclosures.

3. Close openings in smoke barriers and fire-rated construction to maintain fire ratings. Seal penetrations with listed through-penetration firestop materials in accordance with

Section 07 84 00, FIRESTOPPING.

F. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA

70.

GENERAL REQUIREMENTS 010001 - 10

G. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with RE/COR/Cemetery Director.

H. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to RE/COR.

I. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with

29 CFR 1926, NFPA 241 and NFPA 10.

J. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.

K. Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections. Request interruptions in accordance with Article, OPERATIONS AND STORAGE AREAS, and coordinate with RE/COR. All existing or temporary fire protection systems (fire alarms) located in construction areas shall be tested as coordinated with the cemetery. Parameters for the testing and results of any tests performed shall be recorded by the Cemetery and copies provided to the RE/COR.

L. Smoke Detectors: Prevent accidental operation. Remove temporary covers at end of work operations each day. Coordinate with

RE/COR.

M. Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B. Notify RE/COR of any hot work at least 48 hours in advance. Designate Contractor’s responsible project-site fire prevention program manager to permit hot work.

N. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with, and report findings and corrective actions weekly to RE/COR.

GENERAL REQUIREMENTS 010001 - 11

O. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and new buildings under construction. Smoking is prohibited except in designated smoking rest areas.

P. Dispose of waste and debris in accordance with NFPA 241 and

Construction Waste Management Plan required under Section 01 74

19, CONSTRUCTION WASTE MANAGEMENT. Remove from buildings daily.

Q. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the RE/COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor’s performance.

B. Temporary buildings (e.g., storage trailers, office trailers) and utilities may be erected by the Contractor only with the approval of the RE/COR and shall be built with labor and materials furnished by the Contractor without expense to the Government.

The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. The buildings and/or utilities may be abandoned and not be removed only with the written consent of the RE/COR in the form of a contract modification.

C. The Contractor shall, under regulations prescribed by the RE/COR, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the

RE/COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by

GENERAL REQUIREMENTS 010001 - 12

any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads. (FAR

52.236-10)

D. Working space and space available for storing materials shall be as shown on the drawings.

E. Workmen are subject to rules of the Cemetery applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Cemetery as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.

1. Do not store materials and equipment in other than assigned areas.

2. Provide unobstructed access to the Cemetery areas required to remain in operation.

G. Construction Sequencing: To insure such executions, furnish the

RE/COR with a schedule of sequencing start dates and durations for which the Contractor intends to accomplish work in each specific area of site, CLIN and building or portion thereof.

1. Within 45 calendar days after receipt of Notice to Proceed, the Contractor shall submit for the RE/COR review; three copies of the complete Construction Sequencing Plan and an electronic file in accordance with Section 01 33 23, Shop

Drawings, Product Data, and Samples.

2. Within 30 calendar days after receipt of the complete project

Construction Sequencing Plan, the RE/COR or his representative, will do one or both of the following:

GENERAL REQUIREMENTS 010001 - 13

a. Notify the Contractor concerning his actions, opinions, and objections.

b. A meeting with the Contractor at or near the job site for joint review, correction or adjustment of the proposed plan will be scheduled if required. Within 14 calendar days after the joint review, the Contractor shall revise and shall submit three copies of the revised Construction

Sequencing Plan, and a revised electronic file. The revised submission will be reviewed by the RE/COR or his representative and, if found to be as previously agreed upon, will be approved.

3. In addition, provide a work plan showing the specific rea of work, any necessary signage, safety requirements, stormwater controls, fencing, and other information the Contractor deems necessary to the RE/COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive and/or concurrent sequencing as is mutually agreeable to the Cemetery Director, RE/COR and the Work Restrictions noted in the Construction

Documents.

I. Construction Fence: Before construction operations begin, the

Contractor shall provide a chain link construction fence around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom tension wires with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 50mm (two inches) above grade. Remove the fence when directed by RE/COR.

J. Utilities Services: Maintain existing utility services for the

Cemetery at all times. Provide temporary facilities, labor, GENERAL REQUIREMENTS 010001 - 14 materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, sewer, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by

RE/COR.

1. No utility service such as water, gas, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of RE/COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the RE/COR, and Cemetery Director’s prior knowledge and written approval. Refer to specification

Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28

05 11, REQUIREMENTS FOR ELECTRONIC SAFETY AND SECURITY

INSTALLATIONS for additional requirements.

2. The Contractor shall submit a request to interrupt any such services to RE/COR, and Cemetery Director, in writing, 15 calendar days in advance of proposed…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .