Dallas PPI - 1.pdf
PDF 115 KB Posted
- Attached to
- Y1PC--Dallas National Cemetery Solicitation
- Solicitation number
- 36C10F20R0056
About this file
This document contains a solicitation for Phase 4 expansion of the Dallas Fort Worth National Cemetery along with questions and answers from potential offerors. The solicitation seeks a contractor to construct additional gravesites and improvements to the existing cemetery over 900 calendar days. The scope of work includes development of approximately 56 acres of land, construction of over 12,000 pre-placed crypt gravesites and 600 traditional gravesites, 3,000 in-ground cremains sites, a 300-grave Hybrid Natural Burial Section, and associated earthwork, drainage, fencing, roads, parking, utilities and a new irrigation system. The magnitude of construction cost is between $20-50 million. The solicitation is set aside for 100% SDVOSB and proposals are due August 8, 2020. The questions and answers provide clarification on excess soil disposal, soft subgrade compensation, crypt installation costs, and extension of the RFI and proposal deadlines.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Dallas PPI - 2.pdf | ||
| DNC Pre-Bid Sign-In Sheet 15 July 2020.jpeg | JPEG file | |
| CS-Sheets 1 of 3.pdf | ||
| Final Dallas 36C10F20R0056_3 (7-9-2020).pdf | ||
| Dallas-Fort Worth National Cemetery Cx Plan - V1 - 3-27-2020.pdf | ||
| 000 Base Bid Submittal Register.pdf | ||
| Pre-Functional Checklists.pdf | ||
| BID DOCUMENTS SWPPP DFW VA CEM PH4.pdf | ||
| V-Sheets.pdf | ||
| X-Sheets.pdf | ||
| CG-Sheets 1 of 2.pdf | ||
| CP-Sheets.pdf | ||
| LP-Sheets.pdf | ||
| G-Sheets.pdf | ||
| T-Sheets.pdf | ||
| A-Sheets.pdf | ||
| DALLAS WAGE RATES.pdf | ||
| F-Sheets.pdf | ||
| I-Sheets.pdf | ||
| E-Sheets.pdf | ||
| CS-Sheets 2 of 3.pdf | ||
| S-Sheets.pdf | ||
| ATTACHMENT 2_PAST PERF QUEST.docx | DOCX document | |
| Final Dallas 36C10F20R0056_3 (7-9-2020).pdf | ||
| M-Sheets.pdf | ||
| Base Bid Specification Package.pdf | ||
| CG-Sheets 2 of 2.pdf | ||
| B-Sheets.pdf | ||
| P-Sheets.pdf | ||
| CS-Sheets 3 of 3.pdf | ||
| CD-Sheets.pdf | ||
| LI-Sheets.pdf | ||
| CU-Sheets.pdf | ||
| ATTACHMENT 3 - Dallas Pre-Proposal Inquiry (PPI) Form.docx | DOCX document |
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI SUBMISSSION LOG
SOLICITATION NUMBER 36C10F200056
PRE- PROPOSAL INQUIRY (PPI) FORM
DALLAS FORT WORTH NATIONAL CEMETERY PHASE 4 EXPANSION
Question No.
Reference (Sect/Para/Page) QUESTION GOVERNMENT RESPONSE
Solicitation Section 4.2
Independent CPM Consultant
This Specification requires a third party for construction schedule preparation. If the Contractor has these resources in-house, can they be used in lieu of the third-party Independent CPM Consultant?
Yes, but please make sure in-house resources have extensive Primavera P6 qualifications.
Provide qualifications in the proposal.
Drawing G-003 General
Notes14 & 17;
Grading Note 3
The notes referenced here indicate a different disposition of excess soil material. Will excess soil material be allowed to stay on-site in a stockpile (Grading Note 3) or must it be removed from the site (General Notes 14 & 17)?
Excess soil material will be permitted to remain on site.
Soil spoils area is shown on sheet CS100 and CG101.
General notes will be revised.
Drawing G-003
Compaction Note 1
If soft or unstable areas of the subgrade are detected after excavation to design depths, scarified and compaction, and proof rolled are completed per specification, how will the Contractor be compensated for removal of the soft areas and replacement with select backfill?
As with any Federal Government contract, Contractors have many contract provisions that address changes o but r differing site conditions, as applicable.
Geotechnical report should also be contained in the Specifications.
4 Proposal Form
CLIN 002
The last sentence of this CLIN Description is unclear if the cost of installation of the crypts is included in CLIN 001 or CLIN 002. Please clarify.
Cost of installation of crypts is in CLIN 001. Cost of manufacturing, delivery, inspection, and storage of crypts are in CLIN 002.
5 SF 1442
Please extend the Question Deadline so Contractors have more time to submit issues found during the proposal preparation for clarification.
RFI deadline will extend from July 22, 2020 to July 24, 2020.
6 SF 1442
Please extend the Request for Proposal deadline for three weeks to allow Contractors the time required to fully understand this project, solicit subcontractor involvement, and prepare a compliant proposal.
Currently, the Proposal deadline cannot extend and remains August 7, 2020.
7 SF 1442 Please clarify if the project has an Early Turnover date.
The project does not have early Turnover date. The project duration is 900 calendar days from Notice to Proceed.