About this file
This document is a Notice of Intent to Award from the Oregon Department of Transportation (ODOT) Procurement Office, specifically related to Request for Application (RFA) #35613 (S-73000-00009423) for Personal Services. The notice indicates that Vitu, Inc. has been selected as the top-ranked firm for contract negotiations, with the intent to award a contract for unspecified personal services. The document outlines a detailed negotiation schedule, including establishing a work session to discuss the Statement of Work (SOW) within 5-10 days, with subsequent steps for SOW refinement, Breakdown of Costs (BOC) submission, and contract execution. The protest period for competing proposers is set to close on May 22, 2025, at 4:00 p.m., with specific requirements for filing a protest.
The notice includes provisions for contract negotiation, with Linda Beuckens designated as the ODOT Project Manager who will initiate contact and lead negotiations. The document specifies that no work is authorized until the contract is executed and a written Notice to Proceed (NTP) is issued. Attachment 1 lists required submittal items, including Billing Rate Information, Cost Disclosure Questionnaire, Breakdown of Costs, Certificates of Insurance, and an option for Direct Deposit via Automated Clearing House (ACH). The procurement process emphasizes collaborative negotiation, with provisions for mutual agreement on timeline extensions if negotiations are conducted in good faith, and the potential to move to the next highest-ranked firm if an agreement cannot be reached.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 35613 RFA_Attachment_3_Tax_Compliance_Affidavit_Final.DOCX | DOCX document | |
| S-73000-00009423 _QA 1_Final.docx | DOCX document | |
| Insurance Requirements.pdf | ||
| 35613 Attachment 4_Disclosure Exemption Certification_Final.doc | DOC document | |
| S-73000-00009423 _Addendum 1.docx | DOCX document | |
| 35613 RFA_Attachment_A_Application Cover Sheet_Final.doc | DOC document | |
| 35613 Sample Contract_Final.docx | DOCX document | |
| 35613 EVR 2.0 SOW_Final.docx | DOCX document | |
| 35613 RFA_Final.docx | DOCX document | |
| 35613_EvaluationScoreMatrix_Final.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Transportation Procurement Office 355 Capitol St NE, MS#3-3 Salem, OR, 97301 Phone: (503) 986-2710 Fax: (503) 986-5790
OREGON DEPARTMENT OF TRANSPORTATION
Notice of Intent to Award
| DATE: | 05/15/2025 |
| TO: | RFA #35613 (S-73000-00009423) Proposers |
SUBJECT: Intent to Award Vitu, Inc. is the top ranked firm currently selected for negotiations of a contract to provide Personal Services as specified in the above referenced RFA. The scores and rankings of all Proposers are shown in the score matrix accompanying this notice. The award submittal requirements stated in the Mini-Solicitation / RFP are summarized on Attachment 1 of this notice.
For those firms currently not selected for an award, please be on the lookout in the event the ODOT Project Manager re-opens the RFA opportunity to award to additional firms (see RFA Section 4.4 subsection j. for more information). The ODOT Project Manager will have more information at that time if they intend to re-open the RFA opportunity or not.
Linda Beuckens will be the ODOT Project Manager (PM) for this Project. ODOT’s PM will initiate contact with Consultant and will be the primary contact for negotiation of the statement of work (SOW), schedule of performance and costs under the contract. Following discussion and agreement on the SOW, a Breakdown of Costs (BOC) must be completed (using the BOC, BOC-CPFF or BOC-NBR as applicable) and submitted to ODOT’s PM. To set expectations for the contracting phase, listed below is a schedule for completing the SOW, preparing a BOC, completing negotiations, and securing approvals for both the Consultant and ODOT to follow:
| Activity |
| Responsible Party |
| Business Days |
| Negotiations |
| Establish work session to discuss the SOW with Consultant |
| ODOT PM |
| Within 5-10 days of this notice (days depend on size and complexity of the project) |
| Respond to work session with comments/edits to SOW |
| Consultant |
| Within 5 days of work session |
| Respond to SOW comments/edits |
| ODOT PM / OPO |
| Within 3 days of receipt of Consultant comments/edits |
| Submission of BOC / Billing Rates |
| Consultant |
| Within 5-10 days of final ODOT scope (days depend on size and complexity of the project) |
Respond to BOC, billing rates, negotiate, and
Submit for legal sufficiency
ODOT PM / OPO
OPO
Within 5-10 days of Consultant submission of the BOC (days depend on the size and complexity of the project)
| Legal Sufficiency |
| OPO, ODOT PM, and DOJ |
| Within 15 (Mini-Solicitation) & 20 (Formal) days of submission by ODOT PM |
| Signature routing and execution |
| OPO, Consultant, and ODOT Expenditure Authority (if required) |
| Within 6-8 days from initial routing |
| Issue Notice to Proceed (NTP) |
| ODOT PM |
| 1 day after execution |
Negotiations are anticipated to be completed (ready to submit to for legal sufficiency) within the schedule set forth in this notice.
If the schedule for negotiations cannot be met and the Consultant and ODOT are negotiating in good faith, additional time may be mutually agreed upon.
If agreement on costs, tasks, or other WOC requirements cannot be reached within this time frame, ODOT may terminate the negotiations and begin negotiations with the next highest ranked firm as provided in the solicitation and governing Oregon Administrative Rules (OARs).
Note that no work is authorized until the contract is executed and Consultant has received a written NTP from the ODOT PM.
Because this notice is being posted on OregonBuys, the date of this notice will start the protest period for competing proposers to submit a written selection protest (REF Section 1.4 of the RFA). Any proposer who claims to have been adversely affected or aggrieved by the selection of a higher ranked proposer must deliver a written selection protest to my attention and received at the email address below no later than 4:00 p.m. on May 22, 2025. ODOT shall not consider a selection protest submitted after the deadline established herein. To be adversely affected or aggrieved, a protestor must demonstrate that the protester was ranked higher than other selected proposers and that higher ranked proposers are ineligible for selection.
ODOT would like to thank each Proposer for your time and efforts in preparing a response to this solicitation.
Sincerely, Respectfully, David Brudnok ODOT Procurement Office | Contract Coordinator | OPBC ODOT Procurement Office, MS#2-2 355 Capitol ST NE, Salem OR 97302-1166 Phone: 503-871-7881|: david.brudnok@odot.oregon.gov
OPO Purpose: “OPO provides Procurement solutions with integrity by fostering collaborative experiences that advance the transportation system.”
OPO Vision: “We are a trusted partner dedicated to consistently optimizing procurement expertise and resources with a proactive, results-oriented approach.”
Attachment 1 – Award Submittal Requirements Please email to me, the Contract Coordinator, the following items if applicable (see detailed requirements and due date for each item in Section 4.4 of the RFA).
· Billing Rate Information
· Cost Disclosure Questionnaire
· Breakdown of Costs
· Certificates of Insurance
Direct Deposit via Automated Clearing House (ACH). For Consultants that receive ongoing monthly payments from Agency on one or more contracts or work orders, Agency prefers making Consultant payments via ACH direct deposit. While not required, if Consultant has not previously authorized ACH direct deposit and would prefer ACH to expedite transfer of payments after invoices are approved, Consultant must complete a Vendor ACH Authorization form and submit to Agency per the instructions on the form. To expedite Consultant’s payments to its subcontractors, if applicable, Consultant should make reasonable efforts to offer ACH direct deposit payments.