33330226RF0010002 Amendment 00004.pdf
PDF 1 MB Posted
- Solicitation number
- 33330226RF0010002
- Issued by
-
Smithsonian Institution
About this file
This is Amendment Four to a solicitation (33330226RF0010002) issued by the Smithsonian Institution for the upgrade of sanitary and storm systems at the National Museum of Natural History (NMNH) located in Washington, DC. The amendment was issued on March 12, 2026, with an effective date of May 7, 2026, and extends the proposal due date to May 20, 2026, at 3:00 PM EST.
The amendment attaches a presentation explaining the project scope, which involves replacing failing storm and sanitary piping systems throughout the main building, east wing, and west wing; renovating select restrooms with modernization and accessibility improvements; and implementing erosion and sediment control measures. The project includes new piping within existing tunnel systems, rerouting to avoid exhibit halls, tie-in of existing exterior infrastructure, and roof scupper inspection and replacement. The presentation includes a suggested phasing plan divided into Phase 01A (Mobilization), Phase 01B through 01G (Main Building sub-phases by section), Phase 02 (West Wing), and Phase 03 (East Wing), with detailed implementation diagrams showing top-down replacement approaches for storm stacks and restrooms. The presentation explicitly states that the suggested phasing is not mandatory and offerors may propose alternate sequencing or phasing approaches provided all contract requirements are satisfied, with the Smithsonian reserving the right to evaluate the feasibility and risk of any proposed approach. Offerors are required to acknowledge receipt of all amendments signed and dated and submit them with their proposals.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
33330226RF0010002
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
OCON
Washington DC 20013-7012 PO Box 37012
MRC 1200
OCON
OCON
Washington DC 20013-7012 PO Box 37012
MRC 1200
SMITHSONIAN INSTITUTION
05/07/20260004
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
03/12/2026
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
A. The Solicitation Number cited above, to upgrade Sanitary and Storm Systems at the
National Museum of Natural History (NMNH), located in Washington, DC, is hereby amended as follows:
A.1. Attached hereto and made part of this Amendment Four is the presentation for the NMNH
Upgrade San and Stormwater solicitation, provided to help explain the concepts reflected in the drawings.
A.1.1. The presentation includes a suggested phasing plan for informational purposes only.
The suggested phasing is not mandatory. Offerors may propose alternate sequencing or phasing approaches, provided the proposed approach satisfies all contract requirements.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Thomas Dempsey
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 14
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
33330226RF0010002/0004
Smithsonian reserves the right to evaluate the feasibility and risk associated with any proposed phasing approach.
A.2. Offerors shall acknowledge receipt of all amendments to this solicitation signed and dated and submit with proposal.
B. The Due Date for Receipt of Proposals is May
20, 2026, at 3:00 PM EST.
Except as provided herein, all other provisions, terms and conditions of the Solicitation remain unchanged.
END OF AMENDMENT FOUR
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
NMNH UPGRADE SANITARY &
STORM SYSTEM 23 APRIL 2026 (DRAFT)
BUILDING
BACKGROUND
• MAIN BUILDING ORIGINALLY OPENED IN 1910.
• THE EAST & WEST WINGS WERE CONSTRUCTED IN THE 1960s.
• MAIN BUILDING WEST COURTYARD WAS PARTIALLY INFILLED IN
1970s, FULLY INFILLED IN 1990, AND REVITALIZED IN 2017.
• MAIN BUILDING EAST COURTYARD WAS INFILLED IN 1990s.
• CHILLER PLANT AND WING PENTHOUSES WERE CONSTRUCTED IN
1990s.
• THE FACILITY HOUSES MILLIONS OF SPECIMENS AND ARTIFACTS.
• PUBLIC EXHIBITS ARE LOCATED ACROSS 30 GALLERIES IN THE 1910
MAIN BUILDING.
SCOPE OF
RENOVATION
NEED
• STORM & SANITARY PIPING SYSTEMS ARE FAILING IN THE MAIN BUILDING,
EAST WING, WEST WING.
• PIPING SYSTEMS ARE LEAKING AND AT END OF LIFE, INTRODUCING RISK
TO COLLECTIONS AND EXHIBITIONS. FULL PIPING REPLACEMENT (IN LIEU
OF REPAIR) IS NEEDED TO ELIMINATE THIS RISK.
• EXISTING PIPING SYSTEMS ARE LOCATED IN SENSITIVE AREAS, IN
COLLECTION STORAGE AREAS, AND BEHIND EXHIBIT WALLS.
• RESTROOM FACILITES IN THE WINGS HAVE NOT BEEN UPDATED SINCE
THEY WERE BUILT IN THE 1960s. IN ADDITION, MISCELLANOUS
RESTROOMS THROUGH OUT THE FACILITY CURRENTLY HAVE FAILING
PLUMBING.
• THE PROPOSED DESIGN CAREFULLY CONSIDERED IMPACTS TO THE
BUILDING AND DEVELOPED SOLUTIONS AND PATHWAYS TO REDUCE THE
INVASIVE NATURE OF THIS TYPE OF INFRASTRUCTURE REPLACEMENT.
PROJECT
GOALS
• REPLACE THE FAILING SANITARY & STORM PIPING SYSTEMS IN THE MAIN
BUILDING, EAST WING, WEST WING.
• RENOVATE SELECT RESTROOMS IN THE WINGS AND MAIN BUILDING,
INCLUDING MODERNIZATION AND ACCESSIBILITY IMPROVEMENTS.
• MINIMIZE NEW PIPING ROUTED IN EXHIBITS, AND LOCATE IN SERVICE
SPACES
• SAFEGUARD MUSEUM’S COLLECTIONS, VISITORS, AND STAFF BY
ADDRESSING FAILING SYSTEMS.
• MITIGATE THE AMOUNT OF INVASIVE WORK IN SENSITIVE MUSEUM AREAS.
• REDUCE RISKS TO THE COLLECTIONS & EXHIBITS.
• MAINTAIN PUBLIC PROGRAMS DURING CONSTRUCTION.
• MINIMIZE DISRUPTION TO THE MUSEUM’S OPERATIONS.
• PROVIDE FLEXIBILITY TO ADAPT TO FUNDING CHANGES.
MAJOR
ELEMENTS OF
WORK
• NEW PIPING WITHIN EXISTING TUNNELS SYSTEM
• NEW PIPING IN MAIN BUILDING, EAST WING & WEST WING
• REROUTE PIPING TO AVOID EXHIBIT HALLS (MAIN BUILDING)
• TIE-IN EXISTING EXTERIOR INFRASTRUCTURE WITHIN SI
PROPERTY
• IMPLEMENT EROSION AND SEDIMENT CONTROL WITHIN SI
PROPERTY
• INSPECT, ASSESS, REMOVE AND REPLACE ROOF SCUPPERS
CONSTRUCTION PHASING
PHASING
GOALS
• REDUCE IMPACTS TO BUILDING-WIDE OPERATION BY SEQUENCING
IMPROVEMENTS BY BUILDING SECTION (MAIN BUILDING, WEST
WING, EAST WING).
• PHASING DIAGRAMS INCLUDED TO DESCRIBE SYSTEMATIC
REPLACEMENT OF VERTICAL RISERS, ONE RISER/FLOOR AT A TIME.
• PHASING DIAGRAMS INCLUDED TO UPGRADE RESTROOM PIPING,
FLOOR BY FLOOR FOR STACKED FACILITIES.
• LIMIT NORTH LOBBY RESTROOM WORK TO NON-PEAK VISITOR
SEASONS.
• CONTRACTOR REQUIRED TO SUBMIT FORMAL PHASING SCHEDULE &
CONTINGENCY PLAN FOR SI APPROVAL.
SUGGESTED PHASING
PHASE 01A - MOBILIZATION
PHASE 01B – MAIN BUILDING WEST HALL
PHASE 01C- MAIN BUILDING ROTUNDA
PHASE 01D – MAIN BUILDING EAST HALL
PHASE 01E – MAIN BUILDING NORTH HALL
PHASE 01F – MAIN BUILDING EAST RANGE
PHASE 01G – MAIN BUILDING WEST RANGE
PHASE 02 – WEST WING
PHASE 03 – EAST WING
01G
Plan Diagram Illustrating Phases of Work Relating to Section of Building Note: Phase 01 Main Building is Divided into Sub Phases
West Court No Major
Replacement
East Court No Major
Replacement
Chiller Plant No Major Replacement
Note: General Series Sheets provide direction on overall project phasing. Plumbing General Sheets provide direction on working from the top down to implement various parts of the project (Risers, Stacked Bathrooms, Etc.)
CROSS-SECTION FACING NORTH
Main Bldg.
Phase 1
Main Bldg.
Phase 1
Main Bldg.
Phase 1
East Wing Phase 3
West Wing Phase 2
Phases include work in distinct sections of the building
East Court No Major
Replacement
West Court No Major
Replacement
Section Illustrating Phases of Work
Piping Replacement starts at the top and works down in Each
Phase
Note: General Series Sheets provide direction on overall project phasing. Plumbing General Sheets provide direction on working from the top down to implement various parts of the project (Risers, Stacked Bathrooms, Etc.)
WORKING VERTICALLY IN THE BUILDING
The Plumbing section of the documents include direction on Storm Stack Replacement in kind. The drawings indicate a top-down replacement approach. Steps 1-4 of 7 total steps are shown above
Storm Stack Implementation Diagrams
Step 1 Step 2 Step 3 Step 4Existing
WORKING VERTICALLY IN THE BUILDING
The Plumbing section of the documents include direction on replacement of restrooms, which are stacked in various parts of the building.
The drawings indicate a top-down replacement approach. Steps 1-3 of 7 total steps are shown above.
Restroom Renovation Implementation Diagrams
Step 1 Step 2 Step 3Existing
TYPICAL CONSTRUCTION LOGISTICS PLANS
The construction documents include several typical logistics plans illustrating different scenarios where work is performed. The intent of these plans are to isolate work areas and protect adjacent spaces from construction activities. These plans indicate protection requirements as well as collection removal when needed. In total (20) Logistics Plans have been developed for the project and are located in the General Series.
Sample Logistic Plans from Documents
| NMNH UPGRADE SS SYSTEM CONSTRUCTION LOGISTICS 2026.05.05.pdf |
| NMNH UPGRADE SS SYSTEM CONSTRUCTION LOGISTICS 2026.05.05 |
| NMNH UPGRADE SANITARY & STORM SYSTEM |
| BUILDING�BACKGROUND |
| SCOPE OF RENOVATION NEED |
| PROJECT GOALS |
| MAJOR ELEMENTS OF WORK |
| CONSTRUCTION PHASING |
| PHASING GOALS |
| SUGGESTED PHASING |
| CROSS-SECTION FACING NORTH |
| WORKING VERTICALLY IN THE BUILDING |
| WORKING VERTICALLY IN THE BUILDING |
| TYPICAL CONSTRUCTION LOGISTICS PLANS |