3-Sec 01 11 13 - SUMMARY OF WORK.pdf
PDF 90 KB Posted
- Attached to
- 1121 Horsham Road Demolition (26-01054)
- Solicitation number
- US.258594
- Issued by
- Pennsylvania
About this file
This document is a Summary of Work (Section 01 11 13) for the 1121 Horsham Road Demolition project in Pennsylvania, prepared by a local township jurisdiction. The project scope involves the complete demolition of an existing residential home located on Horsham Road, with associated utility abandonment and site restoration work. The contractor must abandon existing water service and sanitary service connections at the mains, grade all disturbed areas to match surrounding topography, and permanently stabilize the site. The Township Engineer will obtain the required PennDOT HOP permit for utility abandonment work, while PECO will coordinate power disconnection and removal of meters and service lines. The contractor is required to submit a complete construction schedule prior to commencing work and must provide at least forty-eight hours' notice to all affected property owners and residents before beginning construction operations.
The contractor shall maintain access to one existing driveway, roadway, and utilities during demolition activities while coordinating with private property owners who remain on-site. All work must comply with OSHA Construction Workplace Safety Standards, and the contractor is responsible for locating all existing utilities in accordance with Pennsylvania Act 287 (1974) as amended by Act 121 (2008), protecting against service disruption. The project is to be completed without owner occupancy of the site during the work period. No owner-supplied products or future work are included in this contract, and no pricing terms, set-asides, or funding information are specified in this summary document.
View the file
Other files
Show 40 more
Latest 50 of 55 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY OF WORK
01 11 13-1
SECTION 01 11 13
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Description of Work.
2. Work by Owner.
3. Work by other parties.
4. Owner supplied Products.
5. Contractor use of site [and premises].
6. Future work.
7. Work sequence of construction.
8. Owner occupancy.
1.02 DESCRIPTION OF WORK
A. This project involves demolition of an existing residential home. Existing water service and sanitary service will need to be abandoned at the mains. All disturbed areas are to be graded to match the surrounding topography and permanently stabilized.
1.03 WORK BY OWNER
A. No work by the Owners.
1.04 WORK BY OTHER PARTIES
A. The Township Engineer will be obtaining a PennDOT HOP permit for the abandonment of the water service and sanitary lateral at the mains within Horsham Road. Work to be performed by the awarded contractor.
B. The Township will coordinate the power disconnection and removal of the meters and service lines with PECO.
1.05 OWNER SUPPLIED PRODUCTS
A. No Products are to be supplied and paid for by Owner.
1.06 CONTRACTOR USE OF SITE AND PREMISES
A. The Work under this contract must be accomplished while one existing driveway access, roadway and utilities are in use. The work that is involved with the existing roadway and utilities must be done so that system operations will not be jeopardized. The remainder of the property is in use by the private owners. Their use and operation of the site shall be coordinated with the demolition efforts.
B. Contractor shall take all necessary precautions to protect all existing water, gas, electric, communications, sanitary sewer, storm sewer, or other facilities encountered during the course of his operations, to guard against disruption of service. Before beginning Work, Contractor shall determine the location of each facility which is questionable. The location of utilities shown on the Drawings represents the best information available; however, it is the responsibility of Contractor to establish the exact location in accordance with the requirements of Pennsylvania Act 287 (1974) as last amended by Act 121 (2008). A Utility User's List is noted on the Drawings.
01 11 13-2
C. Contractor will be responsible to notify all property owners and residents at least forty-eight
(48) hours prior to the start of construction on or near their properties.
D. Contractor shall conduct all Work in strict compliance with OSHA Construction Workplace
Safety Standards.
1.07 FUTURE WORK
A. No future work is proposed as part of this contract.
1.08 WORK SEQUENCE OF CONSTRUCTION
A. The contractor shall submit a complete construction schedule prior to the start of any work.
1.09 OWNER OCCUPANCY
A. Owner will not occupy the site and premises during the period of the work.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION