This document is a Summary of Work (Section 01 11 13) for the 1121 Horsham Road Demolition project in Pennsylvania, prepared by a local township jurisdiction. The project scope involves the complete demolition of an existing residential home located on Horsham Road, with associated utility abandonment and site restoration work. The contractor must abandon existing water service and sanitary service connections at the mains, grade all disturbed areas to match surrounding topography, and permanently stabilize the site. The Township Engineer will obtain the required PennDOT HOP permit for utility abandonment work, while PECO will coordinate power disconnection and removal of meters and service lines. The contractor is required to submit a complete construction schedule prior to commencing work and must provide at least forty-eight hours' notice to all affected property owners and residents before beginning construction operations.

The contractor shall maintain access to one existing driveway, roadway, and utilities during demolition activities while coordinating with private property owners who remain on-site. All work must comply with OSHA Construction Workplace Safety Standards, and the contractor is responsible for locating all existing utilities in accordance with Pennsylvania Act 287 (1974) as amended by Act 121 (2008), protecting against service disruption. The project is to be completed without owner occupancy of the site during the work period. No owner-supplied products or future work are included in this contract, and no pricing terms, set-asides, or funding information are specified in this summary document.

View the file

Other files

File Type Posted
10-Sec 01 56 39. - LANDSCAPE PROTECTION.pdf PDF
12-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
41-Doc 00 73 00 02 - Appendix A - cover sht.pdf PDF
56-Horsham Road Demo Plans 2026-11-03.pdf PDF
15-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
1-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
54-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
20-Doc 00 52 00 - AGREEMENT.pdf PDF
52-x1 - Horsham Road Demo Plans 2026-10-14.pdf PDF
27-Doc 00 91 13 - ADDENDA.pdf PDF
44-Doc 00 73 00 08 - Appendix D - cover sht.pdf PDF
33-Doc 00 62 76 - Application for Payment.pdf PDF
43-Doc 00 73 00 06 - Appendix C - cover sht.pdf PDF
34-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
26-Doc 00 41 00 - BID FORM - EBID.pdf PDF
47-Doc 00 73 00 10 - Appendix E - cover sht.pdf PDF
17-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
9-Doc 00 21 13.1-Instr for Electronic Bidding.pdf PDF
46-Doc 00 73 00 04 - Appendix B - cover sht.pdf PDF
42-Doc 00 73 00 05 - Appendix B - Public Works Employment Verification Form.pdf PDF
24-Doc 00 65 19.16 - SUBCONTRACTORS RELEASE OF LIENS.pdf PDF
40-Doc 00 11 13 - ADVERTISEMENT FOR BIDS - 1121 Horsham Road Demo.pdf PDF
48-Doc 00 73 00 07 - Appendix C - ACM Survey Rpt final.pdf PDF
38-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
49-Doc 00 73 00 09 - Appendix D - lead rpt final.pdf PDF
8-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
31-Sec 02 41 16 - DEMOLITION.pdf PDF
5-Sec 01 33 00 - SUBMITTALS.pdf PDF
6-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
29-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
32-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
18-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
4-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
25-Sec 31 23 33 - Excavation, Backfill and Compaction.pdf PDF
21-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
13-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
2-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
7-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
28-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
51-Doc 00 73 00 03 - Appendix A - Prevailing Wage Determination (SN 26-09095).pdf PDF
37-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
19-Doc 00 63 63 - Change Order.pdf PDF
22-Doc 00 43 13 - BID BOND.pdf PDF
50-Doc 00 73 00 01 - SUPPLEMENTARY CONDITIONS.pdf PDF
36-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
45-Doc 00 73 00 11 - Appendix E - Universal Waste Report final.pdf PDF
35-Doc 00 65 19.13 - SUBCONTRACTORS AFFIDAVIT.pdf PDF
55-Attendance List.pdf PDF
53-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
Show 40 more

Latest 50 of 55 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY OF WORK

01 11 13-1

SECTION 01 11 13

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Description of Work.

2. Work by Owner.

3. Work by other parties.

4. Owner supplied Products.

5. Contractor use of site [and premises].

6. Future work.

7. Work sequence of construction.

8. Owner occupancy.

1.02 DESCRIPTION OF WORK

A. This project involves demolition of an existing residential home. Existing water service and sanitary service will need to be abandoned at the mains. All disturbed areas are to be graded to match the surrounding topography and permanently stabilized.

1.03 WORK BY OWNER

A. No work by the Owners.

1.04 WORK BY OTHER PARTIES

A. The Township Engineer will be obtaining a PennDOT HOP permit for the abandonment of the water service and sanitary lateral at the mains within Horsham Road. Work to be performed by the awarded contractor.

B. The Township will coordinate the power disconnection and removal of the meters and service lines with PECO.

1.05 OWNER SUPPLIED PRODUCTS

A. No Products are to be supplied and paid for by Owner.

1.06 CONTRACTOR USE OF SITE AND PREMISES

A. The Work under this contract must be accomplished while one existing driveway access, roadway and utilities are in use. The work that is involved with the existing roadway and utilities must be done so that system operations will not be jeopardized. The remainder of the property is in use by the private owners. Their use and operation of the site shall be coordinated with the demolition efforts.

B. Contractor shall take all necessary precautions to protect all existing water, gas, electric, communications, sanitary sewer, storm sewer, or other facilities encountered during the course of his operations, to guard against disruption of service. Before beginning Work, Contractor shall determine the location of each facility which is questionable. The location of utilities shown on the Drawings represents the best information available; however, it is the responsibility of Contractor to establish the exact location in accordance with the requirements of Pennsylvania Act 287 (1974) as last amended by Act 121 (2008). A Utility User's List is noted on the Drawings.

01 11 13-2

C. Contractor will be responsible to notify all property owners and residents at least forty-eight

(48) hours prior to the start of construction on or near their properties.

D. Contractor shall conduct all Work in strict compliance with OSHA Construction Workplace

Safety Standards.

1.07 FUTURE WORK

A. No future work is proposed as part of this contract.

1.08 WORK SEQUENCE OF CONSTRUCTION

A. The contractor shall submit a complete construction schedule prior to the start of any work.

1.09 OWNER OCCUPANCY

A. Owner will not occupy the site and premises during the period of the work.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION