2-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf

PDF 109 KB Posted

Attached to
1121 Horsham Road Demolition (26-01054)
Solicitation number
US.258594
Issued by
Pennsylvania

About this file

This is a Material and Equipment specification section (01 60 00) for a demolition project at 1121 Horsham Road in Pennsylvania involving the removal of an existing residential home. The specification establishes requirements for all products and equipment to be used on the project, including provisions for transportation, handling, storage, and protection. The document addresses product sourcing options, ranging from materials meeting reference standards to specifically named manufacturers, and establishes procedures for requesting substitutions when products become unavailable or equivalent alternatives are proposed. Key requirements include inspecting shipments upon receipt to verify compliance and condition, storing products according to manufacturer instructions with seals and labels intact, providing weather-tight and climate-controlled storage for sensitive materials, and arranging storage to permit periodic inspection and access for quality assurance.

The specification prohibits the use of materials and equipment removed from existing premises except as specifically permitted in the contract documents and requires interchangeable components to be from the same manufacturer when replacing existing equipment. Substitution requests are subject to restrictions outlined in the Instructions to Bidders document, and the contractor must submit three copies of each request with supporting documentation including shop drawings, product data, and certified test results demonstrating equivalence. Substitutions become void if indicated on shop drawings without separate written request or if acceptance would require revision to contract documents. The Engineer reserves the right to require use of specifically listed equipment manufacturers identified on the bid form, and the contractor assumes all risk and cost associated with substitutions, including reimbursement for any required review or redesign services.

View the file

Other files

File Type Posted
10-Sec 01 56 39. - LANDSCAPE PROTECTION.pdf PDF
12-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
41-Doc 00 73 00 02 - Appendix A - cover sht.pdf PDF
56-Horsham Road Demo Plans 2026-11-03.pdf PDF
15-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
1-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
54-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
20-Doc 00 52 00 - AGREEMENT.pdf PDF
52-x1 - Horsham Road Demo Plans 2026-10-14.pdf PDF
27-Doc 00 91 13 - ADDENDA.pdf PDF
44-Doc 00 73 00 08 - Appendix D - cover sht.pdf PDF
33-Doc 00 62 76 - Application for Payment.pdf PDF
43-Doc 00 73 00 06 - Appendix C - cover sht.pdf PDF
34-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
26-Doc 00 41 00 - BID FORM - EBID.pdf PDF
47-Doc 00 73 00 10 - Appendix E - cover sht.pdf PDF
17-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
9-Doc 00 21 13.1-Instr for Electronic Bidding.pdf PDF
46-Doc 00 73 00 04 - Appendix B - cover sht.pdf PDF
42-Doc 00 73 00 05 - Appendix B - Public Works Employment Verification Form.pdf PDF
24-Doc 00 65 19.16 - SUBCONTRACTORS RELEASE OF LIENS.pdf PDF
40-Doc 00 11 13 - ADVERTISEMENT FOR BIDS - 1121 Horsham Road Demo.pdf PDF
48-Doc 00 73 00 07 - Appendix C - ACM Survey Rpt final.pdf PDF
38-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
49-Doc 00 73 00 09 - Appendix D - lead rpt final.pdf PDF
8-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
31-Sec 02 41 16 - DEMOLITION.pdf PDF
5-Sec 01 33 00 - SUBMITTALS.pdf PDF
6-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
29-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
32-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
18-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
4-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
25-Sec 31 23 33 - Excavation, Backfill and Compaction.pdf PDF
21-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
13-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
7-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
3-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
28-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
51-Doc 00 73 00 03 - Appendix A - Prevailing Wage Determination (SN 26-09095).pdf PDF
37-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
19-Doc 00 63 63 - Change Order.pdf PDF
22-Doc 00 43 13 - BID BOND.pdf PDF
50-Doc 00 73 00 01 - SUPPLEMENTARY CONDITIONS.pdf PDF
36-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
45-Doc 00 73 00 11 - Appendix E - Universal Waste Report final.pdf PDF
35-Doc 00 65 19.13 - SUBCONTRACTORS AFFIDAVIT.pdf PDF
55-Attendance List.pdf PDF
53-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
Show 40 more

Latest 50 of 55 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MATERIAL AND EQUIPMENT

01 60 00-1

SECTION 01 60 00

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Products.

2. Transportation and handling.

3. Storage and protection.

4. Product options.

5. Substitutions.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Document 00 21 13: Instructions to Bidders.

2. Section 01 40 00: Quality Control.

1.03 PRODUCTS

A. Do not use materials and equipment removed from existing premises, except as specifically permitted by the Contract Documents.

B. Provide interchangeable components of the same manufacturer for components being replaced.

1.04 TRANSPORTATION AND HANDLING

A. Transport and handle Products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to assure that Products comply with requirements, quantities are correct, and Products are undamaged.

C. Provide equipment and personnel to handle Products by methods to prevent soiling, disfigurement, or damage.

1.05 STORAGE AND PROTECTION

A. Store and protect Products in accordance with manufacturers’ instructions.

B. Store with seals and labels intact and legible.

C. Store sensitive Products in weather tight, climate controlled, enclosures in an environment favorable to Product.

D. For exterior storage of fabricated Products, place on sloped supports above ground.

E. Provide off-site storage and protection when site does not permit on-site storage or protection.

F. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of Products.

G. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.

H. Provide equipment and personnel to store Products by methods to prevent soiling, disfigurement, or damage.

01 60 00-2

I. Arrange storage of Products to permit access for inspection. Periodically inspect to assure Products are undamaged and are maintained under acceptable condition.

1.06 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions:

Submit a request for substitution for any manufacturer not named in accordance with the following Article.

1.07 SUBSTITUTIONS

A. Instructions to Bidders specify time restrictions for submitting requests for Substitutions during the bidding period to requirements specified in this section.

B. Substitutions may be considered when a Product becomes unavailable through no fault of the Contractor.

C. Document each request with complete data substantiating compliance of proposed Substitution with Contract Documents.

D. A request constitutes a representation that Contractor:

1. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.

2. Will provide the same warranty for the Substitution as for the specified Product.

3. Will coordinate installation and make changes to other Work which may be required for the Work to be complete with no additional cost to Owner.

4. Waives claims for additional costs or time extension which may subsequently become apparent.

5. Will reimburse Owner and Engineer for review or redesign services associated with re-approval by authorities.

E. Substitutions will not be considered when they are indicated or implied on shop drawing or Product data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.

F. Substitution Submittal Procedure:

1. Submit three copies of request for Substitution for consideration. Limit each request to one (1) proposed Substitution.

2. Submit Shop Drawings, Product data, and certified test results attesting to the proposed Product equivalence. Burden of proof is on proposer.

3. Engineer will notify Contractor in writing of decision to accept or reject request.

G. For each equipment item in which the manufacturer was listed on the Bid Form, Engineer reserves the right to require Contractor to use the equipment item of the listed manufacturer.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION