This document is a Schedule of Items for the Pony Express Trail Bridge Repairs project on the Placerville Ranger District of the Eldorado National Forest. The project requires the fabrication, construction, and installation of four wooden trail bridges of varying lengths, including the Clubhouse, Fred's Place, Aspen, and Huckleberry bridges. The scope includes removing any existing logs used for waterway crossings and installing the new bridges to the Forest Service's standard trail bridge design. Minimum dimensions are specified, and the contractor must supply all necessary lumber, concrete, hardware, and appurtenances. The construction of the bridge footings/foundations must be completed at least three weeks prior to the superstructure installation to allow for curing. The project cost is estimated between $250,000 and $500,000, with a period of performance from August 15, 2024 to November 15, 2025. A pre-bid site visit is scheduled for May 16, 2024, and requests for information are due by May 23, 2024.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITEM
NUMBER DESCRIPTION UNIT QUANTITY
0001 15101 Mobilization LS 1 0002 15701 Sediment Control LS 1
0003 60101 Minor Concrete Structures (8 = 2 for each bridge) CUYD 4
0004 55702 Structural Timber and Lumber Treated Pedestrian Bridge 6' wide x 22' long "Aspen" LS 1
0005 55702 Structural Timber and Lumber Treated Pedestrian Bridge 6' wide X 19' long "Clubhouse" LS 1
0006 55702 Structural Timber and Lumber Treated Pedestrian Bridge 6' wide X 25' long "Fred's Place" LS 1
0007 55702 Structural Timber and Lumber Treated Pedestrian Bridge 6' wide X 20' long "Huckleberry" LS 1
0008 20416 Approach Trail Soil Fill & Water/Sediment Diversion LS 1
SCHEDULE OF ITEMS
SCHEDULE OF ITEMS
Placerville Ranger District/Eldorado National Forest/Trail Bridge Construction
PROJECT TITLE: Pony Express Trail Bridge Repairs
WORKPLAN ACQUISITION PLAN/REQUISITION NO: 684297
Period of Performance (Required for Services and A&E)
Anticipated Delivery Date (Required for Supply and Construction) 6/1/2024 - 11/15/2025