This document consists of questions and answers related to a federal contract opportunity for the fabrication, construction, and installation of four trail bridges on the Pony Express trail between Kyburz and Echo Summit in the Eldorado National Forest.

The key details are:

  • The contract scope includes removing existing logs that served as waterway crossings, and constructing the trail bridges to Forest Service standard design specifications, with minimum dimensions of 72" width and 42" top railing height.
  • Two of the bridge sites are located within 150 feet of a dirt road/staging area, while the other two are 2/3 mile and 1/2 mile from the staging areas.
  • The contract value is between $250,000 and $500,000. A pre-bid site visit is scheduled for May 22, 2024. Proposals are due by May 23, 2024.
  • The NAICS code is 237310 (Other Heavy and Civil Engineering Construction) with a $45M size standard. Bonds are required for projects valued at $35,000 or more. Davis-Bacon wages apply.

View the file

Other files

File Type Posted
A10 1124263 SAM.gov Q&A.pdf PDF
A10 1124263 SAM.gov Q&A.pdf PDF
A10 1124263 SAM.gov Q&A.pdf PDF
A10 1124263 SAM.gov Q&A.pdf PDF
A10 1124263 SAM.gov Q&A.pdf PDF
CaldorTrailBridgeRelief_2.pdf PDF
CaldorTrailBridgeRelief_1.pdf PDF
8. Forest Service Supplemental Specifications.pdf PDF
5. Drawings - Sheet 2.pdf PDF
9. Specs FP-14.pdf PDF
6. NRE_Construction_RFP.pdf PDF
2. Scope of Work.pdf PDF
4. Drawings - Sheet 1.pdf PDF
1. SF 1442_12970224R0029.pdf PDF
10. Davis-Bacon Act WD# CA20240007(El Dorado County).txt TXT text file
3. Schedule of Items.pdf PDF
7. Evaluation Factors.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions Received Answers Could you clarify who’s doing the final design? the highlighted lines attached below seem to conflict.

Is a geotechnical engineer required; will the government approve subgrade? There is not a need for a geotechnical engineer and the subgrade will be inspected by the project COR.

Could you provide the site visit date / time? A pre-bid site visit will be held May 22, 2024 :

Contractors will meet Forest Service (FS) personnel at 9:00 AM (local time) at the staging area of the lowest elevation bridge, which would be "Clubhouse". This would be found on the left (west) side of map Caldor Trail Bridge Relief #1. Traveling eastbound on Hwy. 50, and less than a mile east of the town of Kyburz is FS Road # 11N43, where a sharp left turn is required. This road is not signed on Hwy.50 nor is there a left-hand turn lane. It is unknown how long it will take the group to hike in, assess, and hike out, so it would be best if perspective offerors and FS personnel caravan to the other bridge sites together after the first one.

Can you provide the small business qualifications to bid on this project? The size standard for NAICS 237310 Highway, Street, and Bridge Construction is $45.0M.

Is there still a possibility of a site visit? I just saw this on Sam.gov but it looks like it is already past the site visit date.

A pre-bid site visit will be held May 22, 2024 :

Contractors will meet Forest Service (FS) personnel at 9:00 AM (local time) at the staging area of the lowest elevation bridge, which would be "Clubhouse". This would be found on the left (west) side of map Caldor Trail Bridge Relief #1. Traveling eastbound on Hwy. 50, and less than a mile east of the town of Kyburz is FS Road # 11N43, where a sharp left turn is required. This road is not signed on Hwy.50 nor is there a left-hand turn lane. It is unknown how long it will take the group to hike in, assess, and hike out, so it would be best if perspective offerors and FS personnel caravan to the other bridge sites together after the first one.

It is stated that the government would like to see the bridges assembled I the fewest possible pieces. Is is possible to get a crane or a lift of some sort to the bridge locations?

The sites are remote, and it could be challenging to get heavy equipment on site. Please attend the site visit will allow you to make that determination on which equipment is appropriate.

Is there any boding required to submit the bid? I.e. will I have to tie up the bonding that I have in order to only submit the bid?

I understand the conflict. “H” would supersede “A” since R-1739-01 (Plan & Elevation) and R-1739-02 (Abutment & Railing Details) have both been approved and signed by the USFS Regional Engineer, Leonard Job upon recommendation of the USFS Regional Bridge Engineer, Darrell Pereira.