This is a Scope of Work specification document for the City of Tallahassee, Florida, detailing the conversion of two existing hard surface tennis courts (Courts 17 & 18) at Forestmeadows Park into clay hydro courts. The project, located at 4750 N. Meridian Road in Tallahassee, requires the selected contractor to furnish all labor, materials, and equipment necessary for the complete conversion, including the installation of a subgrade irrigation system. Work includes demolition limited to removal of the existing subsurface sprinkler irrigation system, net posts and footers, center anchors, and existing curbing; reconstruction of curbing to meet United States Tennis Association (USTA) and American Sport Builders Association (ASBA) regulations; and installation of new infrastructure including 20 Mil HDPE liners, hydro-blend surface material (Har-Tru brand), perimeter curbing with solid pavers, irrigation control boxes with shut-off valves, net post footings and sleeves, center anchors, three divider net posts with cables, and regulation herringbone playing line tapes. The contractor is responsible for obtaining all required permits prior to commencing work and must coordinate with the City Project Manager throughout the project. A pre-construction meeting is encouraged to occur at least two weeks before work begins to discuss project phases, scheduling, and site staging.
The contractor must ensure all installations meet USTA, ASBA, and Har-Tru specifications with a minimum 95 percent soil compaction rate verified through testing reports submitted to the City Project Manager for approval. The selected contractor must be certified by the manufacturer for the surfacing system installation and demonstrate a minimum of five years of experience in tennis court surfacing applications. All work is subject to inspection and approval by USTA representatives and the City's Project Manager before acceptance. The contractor shall provide Har-Tru representatives' approval letters upon project completion and deliver maintenance manuals and warranties to the City. A two-year warranty against defective materials or workmanship is required, during which time the contractor must make necessary surface repairs at no cost to the City, excluding vandalism or abuse. The contractor is responsible for all site preparation, dust abatement, debris removal, erosion control, protection of existing infrastructure and vegetation, weather-related work stoppages and repairs, and restoration of surrounding areas. Final inspection will occur within ten days of the contractor's notification that work is substantially complete, with the warranty period commencing on the date the City Project Manager determines full compliance with contract requirements.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Forestmeadows Park Tennis Courts (17 & 18) Scope of Work Conversion of Courts (17 & 18) into HydroCourts
(4750 N. Meridian Road, Tallahassee, FL)
SCOPE OF WORK
The project is for the conversion of existing two (2) hard surface Tennis Courts (17 & 18) into clay hydro courts at Forestmeadows Park, Tallahassee, FL, including the installation of subgrade irrigation system. Work shall consist of all labor, materials, and equipment necessary to complete the job as specified. The selected Contractor shall be responsible to apply for, pay and obtain all required permits prior to the commencement of work. Work on this project shall be limited to Courts (17 & 18).
The proposed HydroCourt system shall be installed atop the existing materials on the Courts (17 & 18). Demolishment shall be limited to the removal of existing sub-surface sprinkler irrigation system beneath the courts, net posts and their footers, center anchors and their footers, any existing posts within Courts (17 & 18) and their footers, and any existing curbing border bricks or concrete blocks necessary to remove and re-construct to re-establish new correct elevation. All extracted materials shall be removed off premises (as soon as practical) and be disposed of in accordance with local, State and Federal regulations. Given that the existing slopes may not meet the United States Tennis Association (USTA) Regulations, a new curbing border shall be installed (by removing all existing curbs and re-constructing new curbs) or be constructed atop the existing curbs to establish new elevations that meet USTA, ASBA, and Har-Tru Guidelines. All new installations, slopes, methodology, and/or construction of the converted courts (17 & 18) shall meet the American Sport Builders Association and the US Tennis Association Regulations. Selected Contractor shall adhere to and be responsible to comply with the ASBA and USTA Regulations. No work will be accepted or approved by the owner until all completed work has been reviewed, inspected, and approved by USTA representatives and/or the City’s Project Manager.
Contractor shall examine all surface materials on the Tennis Courts (17 & 18) to ensure suitability to be re-used for the proposed HydroCourts. Contractor, at Contractor’s expense and as a part of the work, shall compact the existing surfaces. Contractor may bring in new fill-material (lime rock) to be added to or be mixed with existing surface-materials in order to compact and reach a compaction rate of 95% or higher. The Contractor shall provide reports of soil testing to the City Project Manager for review and approval prior to proceeding with further work.
The finish product for the construction of the new courts shall be Har-Tru, and work must be in accordance with Har-Tru specifications (see ATTACHMENT 5). Contractor, at the completion stage of the project, shall provide the City Project Manager with an approval letter of materials and installation from Har-Tru representatives.
The newly converted/constructed courts shall include:
1. New sub-surface liner and irrigation system (for cell irrigation) and all its components including separate control valves for each tennis court.
2. New footers for net posts, and center anchors.
3. New net posts, cranks and PVC sleeves, and center anchors.
4. New concrete curbs. Contractor has the choice to install the new curb securely atop the existing curbs, remove existing curbs and install new, or cast-in-place. If concrete block curbs are used, they shall measure 16” long x 8” wide x 4” deep.
5. New Schedule 40, 4” Dia.X15’ Long steel posts, installed in concrete footers for divider nets. See locations on attached drawing.
6. New tennis posts, nets, and cables.
DESCRIPTION
A. COORDINATION - Contractor will be required to coordinate work with the City Project
Manager. Work will be done under the general supervision of the City Project Manager. The presence or absence of the City’s representative shall in no way relieve the Contractor of their responsibility to complete the work in accordance with the contract documents or lessen their obligation to correct unsatisfactory work. Contractor shall take instructions and adhere to construction-related matters conveyed to the Contractor only by the City Project Manager.
Contractor shall be held responsible for deviation from this requirement and shall risk lack of reimbursement for any work not pre-authorized by the City Project Manager.
B. PRE-CONSTRUCTION MEETING – At least two weeks prior to commencement of work, the Contractor shall arrange for an onsite meeting with potential sub-contractors and the City Project Manager to discuss all aspects of the project and to also provide the sub-contractors the opportunity to request clarification on any project related matters.
This pre-construction meeting is not mandatory but very encouraged. At the pre-construction meeting, the Contractor should submit a schedule to the City Project Manager indicating the intended starting date of the work, the separate phases and timetable if possible, and the intended date of completion. Staging at the site as well as safety implementation techniques will be an important topic of discussion during this meeting.
C. SEQUENCE OF WORK – Work shall be scheduled to provide a continuous and uninterrupted flow of all work items in a logical sequence. Contractor must not interrupt or negatively impact the daily function of Forestmeadows Compound. Prior arrangements with staff must be coordinated prior to any disruption of daily operations.
CONTRACTOR’S RESPONSIBILITIES PRIOR TO COMMENCEMENT OF WORK
It is the Contractor’s responsibility to become familiar with the Scope of Work for the project, locate all underground utilities prior to digging, maintain a clean and safe work site and environment.
Further, the Contractor shall:
1. Solely be responsible for all construction means, methods, techniques, sequences, and procedures, and for coordination of all portions of the work. Unless specifically noted, the Contractor shall provide and pay for all labor, materials, equipment, tools, construction machinery, and transportation necessary for proper execution and completion of the work.
2. Throughout all phases of construction, the Contractor shall keep the work site safe, clean and free from rubbish, debris and dust. Any dust nuisance affecting adjacent tennis courts, road and parking areas shall be abated by cleaning, sweeping or washing with water at no additional cost to the City.
3. Locate portable sanitary facilities on isolated portion of the site in coordination with the City Project Manager.
4. Provide the City Project Manager with emergency phone numbers for all key personnel associated with the project.
5. Furnish, erect, and maintain all signs, lights, barricades to the extent required by law or reasonably necessary before any work is started and remove items promptly when construction is completed.
6. Maintain adequate protection of the City’s property from loss arising in connection with this contract. Contractor shall protect from damage all existing improvement and utilities. Contractor shall make good any such damage or loss occurring in the course of work except if such damage or loss is directly caused by employees of the City.
7. Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs and grass) on or adjacent to the work site.
8. Vehicles used for the project must follow construction entrances that are deemed usable by the City Project Manager. Vehicles shall not be loaded beyond the loading capacity of tennis courts, driveways, or roads recommended by the manufacturer or as prescribed by Federal, State, or local law or USTA Regulation.
9. Stop work during adverse or severe weather and suitably protect work site plus make any repairs to the work damaged by adverse weather.
10. At job completion, restore to its original condition any areas surrounding the job site damaged by the Contractor.
11. Contractor shall adhere to the specifications laid out by the American Sport Builders Association – “Tennis Courts – A Construction & Maintenance Manual”, US Tennis Association, and any special specifications laid out by the City of Tallahassee. All work on this project shall be in accordance with the Regulations of the American Sports Builders Association, the US Tennis Association, and Har-Tru Specifications. Contractor shall use Laser-Leveling System to Accomplish Required Finish Elevation. Further, the Contractor shall adhere to the following:
a. Remove and re-construct, as needed, existing chain link fencing for specified demolition and re-building of the proposed Tennis Courts (17 & 18). As part of the work, all 90-degree fence corners on Courts (17 & 18) shall be converted into diagonal corners, measuring approximately 10 feet x 10 feet x 14 feet. Include in your bid the removal of wires at the bottom of fence and replace with schedule 40, 1-5/8-inch diameter bottom rails wherever bottom rails are missing on Courts (17 & 18). Proposed bottom rails shall have no more than ¾-inch clearance from courts’ surfaces. Attach bottom of fence to the newly installed bottom rails.
b. Temporarily remove existing shelters, if any, between the courts to complete the proposed work within the courts and reinstall at the completion of work.
c. Create construction staging area at the North side of courts (17 & 18) and any needed storage in the vicinity of the project. Coordinate exact location with City Project Manager.
d. Keep an orderly construction site during the performance of the project.
e. Clear the existing two tennis courts (17 & 18) and remove existing net posts and netting, and store safely onsite.
f. Demolition, removal, and hauling of specified court materials, net posts, existing irrigation system, footers, and center anchor is limited to Courts (17 & 18). Promptly notify the City Project Manager of any sub-surface or latent physical conditions at the site that differ materially from what is indicated in the site layout or what the conditions are expected to be.
g. Remove and discard of existing protruding fence between Courts (17 & 18).
h. Remove and discard of existing mesh and hardware atop the fence at the South side of
Courts (17 & 18).
i. Establish elevations and perform compaction. Contractor may bring in new fill-material
(lime rock) to be added to or be mixed with existing surface court-materials in order to compact and reach a compaction rate of 95% or higher. Test for compaction to achieve 95% compaction and provide the City Project Manager with the results to obtain approval before resuming further work. Contractor will provide all compaction test result reports to the City Project Manager. Please see ATTACHMENT 5.
j. Install new perimeter curbing. Use solid pavers at the inside perimeters of the Courts 17 &
18. Please see ATTACHMENT 5.
k. Install new sub-surface (hydro) courts irrigation system on Courts (17 & 18) to include 20
Mil HDPE liners, stone screening layer, and hydro-blend surface, and irrigation control boxes in accordance with ASBA, USTA and Har-Tru (see ATTACHMENT 5). Gang irrigation control boxes for each tennis court shall include a shut-off ball valve to be installed on the water supply line behind the boxes. Install an aboveground hose bib next to the gang irrigation control boxes. Installation of the irrigation control boxes, shut-off ball valve and hose bib shall be similar to the existing system onsite. All proposed drainage systems shall be tied into the Facility’s existing master drainage system and all water connections to supply the new courts shall be tied into the existing water lines.
l. Charge, activate, and test new sub-surface irrigation systems prior to backfilling.
m. Supply and install all new base screening material as per the specifications laid out by
ASBA, and Sub Surface Court System manufacturer. Screening material shall be washed screening or granite screening and shall be no less than 5 ½ inch thick.
n. The surfacing material shall be Har-Tru “Hydro Blend” with a compacted, uniform thickness of no less than 1”, and shall be installed and laser graded to proper slope (see
ATTACHMENT 5).
o. Install net post sleeves of 3” inner diameter PVC in concrete square footing foundation of a minimum size of 18” x 36” x 42”. New net posts shall be installed to meet or exceed USTA and ASBA net post specifications. Install a new center anchor in concrete footer 12” x 15” x 16” so as to finish flush with new surface. Refer to ATTACHMENTS 2, 3 & 4 – Tennis Courts Construction Manual - Chapter 13 for additional information and reference – Net Posts & Nets.
p. Install 3, 4 inch diameter schedule 40, 15-feet long steel posts and cranks between Courts (17 & 18). Posts to be placed in 48-inch-deep footers (SEE ATTACHMENT 1). Install 3/8-inch dia. Nylon coated Stainless Steel cable atop the 4-inch posts, operated via crank.
Proposed cables shall be similar to the existing onsite nets.
q. Apply regulation herringbone playing line tapes with 3” aluminum nails per USTA rules and regulations as described by ASBA.
r. Train City staff on how to maintain and service the new watering system. Provide all needed maintenance manuals and warranties to the City Project Manager.
s. Reinstall or repair all fencing upon completion of the project where fence was taken down for construction access. Maintain gates’ location.
t. Guarantee respective work against defective materials or workmanship for a period of two
(2) years. Anytime during this two-year period, the Contractor shall make necessary repairs to the surface without cost to the City. Acts of vandalism or other abuse will be the City’s responsibility.
u. Responsible for the supervision and direction of the work. Authorized staff and/or subcontractors should be directed as deemed necessary and consistent with good construction practice.
v. Limit onsite stockpiling for excavated material and protect against erosion and migration of substances. Onsite stockpiling shall be extremely limited and of a short duration means only.
A. QUALITY ASSURANCE - Qualifications of Installer: Installer shall be certified by the manufacturer for the installation of the surfacing system and should provide written proof of having a minimum of 5-years of experience in the application of tennis court surfacing systems with bid response.
B. LAYOUT OF WORK- The work should be laid out to true lines and grades as per the USTA and ASBA.
C. INSPECTION – All material and workmanship shall be inspected by the City Project Manager prior to covering of work. Contractor shall call for such inspections well ahead of covering.
D. DEFECTIVE MATERIAL – The City shall have the right to reject defective material and workmanship that does not conform to terms of the Contract.
Rejected workmanship or materials shall be satisfactorily corrected or replaced with proper material without charge to the City.
E. FINAL INSPECTION – When work in the opinion of the Contractor is substantially completed, the Contractor shall notify the City Project Manager at least five (5) days in advance that the work will be ready for final inspection on a specified date.
If such inspection reveals the work is not performed in accordance with the requirements of the contract or work is uncompleted, the Contractor shall be notified of deficient work in writing and shall promptly perform the work required. Contractor shall request a re-inspection, which will be made within ten (10) days after notice of deficient work. When the City Project Manager has determined that the work is completed in accordance with the requirements of the contract, the date of completion will be fixed as the last day of such re-inspection, and the start of warranty date.