2B_Submittal Schedule Service Lines 1464.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
High Temperature Hot Water System Repair Federal contract opportunity
Solicitation number
FA462624R0009
Issued by
Department of the Air Force Global Strike Command

About this file

This document is a Schedule of Materials Submittals for a contract to Replace HTHW Service Lines at Building 1464 under Solicitation/Contract No. 24-0018. The schedule lists various submittal requirements including as-built drawings, operations and maintenance manuals, quality control plans, contaminated work plans, and material and equipment submittals across different specification sections such as concrete, HVAC, and plumbing. It specifies the number of copies required, the submittal type (e.g. shop drawings, samples, catalog data), the required submission date, and the review and approval process.

The related federal contract opportunity is for a 5-year Indefinite Delivery Indefinite Quantity (IDIQ) contract to perform High Temperature Hot Water (HTHW) System Repair requirements at Malmstrom AFB, MT. The total aggregate contract amount shall not exceed $4,999,999.99. This is a 100% Small Business set-aside under NAICS code 238220 with a $19,000,000 size standard. The contract will include excavating, repairing, and/or replacing HTHW service lines, distribution lines, sump pumps, and valves.

View the file

Other files for this federal contract opportunity

Other files attached to High Temperature Hot Water System Repair, newest first.
File Type Posted
13_QA_13 Aug 2024 (Amend 3).xlsx XLSX spreadsheet
0_Solicitation - FA462624R00090003 Amend 03.pdf PDF
16_M17.3 AMENDED (Amend 2).pdf PDF
0_Solicitation - FA462624R00090002 Amend 02.pdf PDF
14_ME1.3 AMENDED (Amend 2).pdf PDF
11_ME0.4 AMENDED (Amend 2).pdf PDF
5_Blank Bid Sch (Amend 2).xlsx XLSX spreadsheet
6_MT20240066_ 02 Aug 24_Heavy (Amend 2).pdf PDF
13_QA_6 Aug 2024 (Amend 2).xlsx XLSX spreadsheet
15_ME1.2 AMENDED (Amend 2).pdf PDF
7_Sections L and M - HTHW Requirements (updated 072924 Amend 1).pdf PDF
11_ME0.4 AMENDED (Amend 1).pdf PDF
12_M17.4 AMENDED (Amend 1).pdf PDF
13_QA_29 Jul 2024 (Amend 1).xlsx XLSX spreadsheet
10_C1.2 AMENDED (Amend 1).pdf PDF
0_Solicitation - FA462624R0009 Amend 01.pdf PDF
9_Subcontractor Consent (Amend 1).pdf PDF
7_Sections L and M - HTHW Requirements.pdf PDF
4A_Sheet Index - Service Lines Bldg 1464.pdf PDF
0_Solicitation - FA462624R0009.pdf PDF
8_Past Performance Questionaire.pdf PDF
3B_DRAWINGS - Sump Pumps.pdf PDF
3A_Sheet Index - Sump Pumps.pdf PDF
2A_Submittal Schedule HTHW Sumps.xlsx XLSX spreadsheet
1B_SPECS Service Lines BLDG 1464.pdf PDF
1A_SPECS - Sump Pumps.pdf PDF
6_MT20240066 27 Jun 2024_Heavy.pdf PDF
5_Blank Bid Sch.xlsx XLSX spreadsheet
4B_DRAWINGS - Service Lines BLDG 1464.pdf PDF
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SCHEDULE OF MATERIALS SUBMITTALSProject NumberProject Title:Solicitation/Contract No.
24-0018Replace HTHW Service Lines, Bldg 1464
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR
Number of Copies Required
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONSMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSNOTIFICATIONOTHERREQUIRED SUBMISSION DATE (BY CONTRACTOR)DATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDIS- APPROVED
DIVISION 1 - GENERAL REQUIREMENTS
101000.3.5.B As-Built Drawings4**3d PTFI
201000.3.5.B Corrected As-Built Drawings4**10d after received back from CE, if needed
301000.3.5.D Final As-Built submittal4**30d PTFP
401000.3.5.F List of Equipment-In-Place4**PTFI
501000.3.7.A Four (4) Complete Sets Operations & Maintenance4**PTFI
601000.3.8.A.1 Itemized Equipment List4**10d PTFI
701000.3.8.A.2 Guarantees for Equipment items list4**10d PTFI
801000 3.18.4 Quality Control Report - Daily4**EWD
901000 3.18.5 Quality Control Plan4**PTSW
1001000.3.19.A Property Inventory Checklist4**10d PTFI
11List of Employees 01001. 1.1.A.1
12Entry Authorization List 01001. 3.1.C.5.1
13Environmental Protection & Waste Management Plan 01360, 11.6. & 1360-A, Attachment 11**10d PTFA
14Recovered Materials Written Determination Form 1360-B, Attachment 21**10d PTFA
15Recycled Material Use Report 01360, 12.3 & From 1360-C, Attachment 31**10d PTFA
16Selective Demolition Qualifications Data 01732, 1.544
17Trench Excavation Backfill Soil & Bedding Samples and Test Data 02221 1.3.A & B14**3d AWC
18Contaminated Work Area Plan 02222, 3.2.A.4**21d PTSW
19Contaminated Areas Project Report, 02222, 3.34**15d PTFI
20SSHP , 02222, 5.3.B4**21d PTSW
21Logs, Reports & Record Keeping 02222, 5.3.C.4**AWC
22Notification for Excavation in Roads & Parking Lots 02300 1.1A.3.c.1**10d PTSW
23Backfill Compaction Test Results 02300 3.1.A.4**3d AWC
24Submittals 02511, 1.3 Hot-Mix Asphalt444**15d ANTP
25Quality Assurance 02511, 1.4 Qualifications4**15d ANTP
26Submittals 02570, 1.2.A Pre-Cast Manholes44**15d ANTP
27Submittals 02570, 1.2.B Test Reports444*3d AWC
28Field Quality Control 02511 3.11 Test Reports444*3d AWC
29Submittal 02800, 1.2.A. Lab analysis4**15d ANTP
30Dryland Grass Seed Product Data, 02912, 1.4.A.4444**15d PTSW
31Submittals 03300, 1.4.A. Notification of Placement1**18 hours SN
32Submittals 03300, 1.4.B. Product Data & Instructions444**15d ANTP
33Submittals 03300, 1.4.C. Product Samples1**3d AWC
34Submittals 03300, 1.4.D. Mix Design4**21d PTSW
35Submittals 03300, 1.4.E. Test Results4**36 hours AWC
36Submittals 15027, 1.3.C.1 Shop Drawings4444**15d ANTP
37Submittals 15027, 1.3.C.2 Test Reports4*AWC
38Submittals 15090, 1.4 B Equipment Submittals4444*15d ANTP
39Submittals 15090, 1.4 C Seismic Drawings4444*15d ANTP
40Submittals 15100, 1.3 Shop Drawings44444**15d ANTP
41Submittals 15250, 1.2.B. Shop Drawings4**15d ANTP
42Submittals 15702, 1.4.B Shop Drawings44**15d ANTP
43Submittals 15702, 1.4.C Welder Certifications4**PTSW
44Submittals 15702, 1.4.D Test Results4**AWC
45Submittals 15702, 3.6.B Cleaning Procedures4**14d PTSW
Schedule of Abbreviations:
AWC
PTSW
AFA= After Work CompletedBMF=Before Material Delivery
PTO= Prior to Starting WorkSN=Advance Notification
PTNT= After Final AcceptanceSRO=After Each Occurrence
ANTP= Prior to OutagePTFI=Prior to Final Inspection
EWD= Prior to Notice to ProceedPTFP=Prior to Final Payment
PTFA= After Notice to ProceedPTCW=Prior to Completing Work
ACA= Each work day AF Form 3000 not requiredAFI=After Final Inspection
= Prior to Final AcceptancePT=Prior To
= After Contract AwardPSS=Per Submittal Schedule

&"Times New Roman,Regular"&12Attachment 2 &"Times New Roman,Regular"&12HTHW SERVICE LINES IDIQ &"Times New Roman,Regular"&12FA4626-xx-R-xxxx

&"Times New Roman,Regular"&12AF Form 66 02:

&F-&D &"Times New Roman,Regular"&12 SS-&P

REQUIRED TECHNICAL SUBMITTALS