This document is a submittal schedule for a federal contract opportunity to repair the High Temperature Hot Water (HTHW) system at Malmstrom Air Force Base. The contract is a 5-year indefinite delivery, indefinite quantity (IDIQ) firm-fixed price contract with a total not-to-exceed value of $4,999,999.99. It is a 100% small business set-aside under NAICS code 238220. The work includes excavating, repairing, and/or replacing HTHW system components such as service lines, distribution lines, sump pumps, and valves. The submittal schedule lists numerous deliverables required from the contractor, such as shop drawings, product data, quality control plans, schedules, permits, and test reports, with due dates ranging from 7 days to 45 days. The federal agency is the Department of the Air Force Global Strike Command.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIALS SUBMITTALS | Project Number | Project Title: | Solicitation/Contract No. | ||||||||||||||||||
| 1123678 | Repair HTHW Sump Pumps | ||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR | ||||||||||||||||||||
| Number of Copies Required | |||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | NOTIFICATION | OTHER | REQUIRED SUBMISSION DATE (BY CONTRACTOR) | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |
| APPROVED | DIS- APPROVED | ||||||||||||||||||||
| DIVISION 01 - GENERAL REQUIREMENTS | |||||||||||||||||||||
| 1 | 01 00 00 General Requirements - 3.5 As-Built Field Data | 2 | 3 -d PTFI | ||||||||||||||||||
| 2 | 01 00 00 General Requirements - 3.5.F Final As-Built Drawings | 1 | 30-d AFI | AutoCAD CD | |||||||||||||||||
| 3 | 01 00 00 General Requirements - 3.7 Operation and Maintance Instructions | 1 | 2 | 1d- ATT & PPC | 1 Hardcopy, 2 CDs | ||||||||||||||||
| 4 | 01 00 00 General Requirements - 3.8 Contractor Furnished Equipment Data | 1 | 10-d PTFI | Equipment List and Guarantees | |||||||||||||||||
| 5 | 01 00 00 General Requirements - 3.11 Start of Work Notification | 1 | 21-d PTSW | ||||||||||||||||||
| 6 | 01 00 00 General Requirements - 3.12 Notice of Pre-Final and Final Inspections | 1 | 14-d PTE | Red line “As-Built” dwgs shall be provided by the Contractor at final inspection. | |||||||||||||||||
| 7 | 01 00 00 General Requirements - 3.13 Construction Near Utility Systems - Form AF103 | 14-d PTSW | AF Form 103: Work Clearance | ||||||||||||||||||
| 8 | 01 00 00 General Requirements - 3.14 Utility Outages | 14-d PTE | Schedule submitted to Construction Management for Approval | ||||||||||||||||||
| 9 | 01 00 00 General Requirements - 3.15 Submittals - AF Form 66 | 3 | |||||||||||||||||||
| 10 | 01 00 00 General Requirements - 3.18 Quality Control Plan | 3 | 10-d ANP and PTSW | Quality Control Plan must be acceptable to the Government before construction can begin. | |||||||||||||||||
| 11 | 01 00 00 General Requirements - 3.19 Contract Progress Schedule and Report | ANP - AFI | Project Scheudle Form 3064-1st and 15th of each month: Progress Report Form 3065 -every 2 weeks | ||||||||||||||||||
| 12 | 01 00 00 General Requirements - 3.20 1354 Checklist - Property Inventory Checklist | 10-d PTFI | |||||||||||||||||||
| 13 | 01 00 00 General Requirements - 3.22 Nuclear Densometers | 3 | 30d - PTSW | ||||||||||||||||||
| 14 | 01 10 00 - Security Requirements - 1.3.2 Entry Authoirty List (EAL) | 14-d PTSW | Electronic CEAL submittal | ||||||||||||||||||
| 15 | 01 36 00 - Environmental Protection - 2.0 Permits and Fees 2.3 Environmental Deliverables | 5 | PTSW | All appliable environmental permits, forms, plans, etc. | |||||||||||||||||
| 16 | 01 36 00 - Environmental Protection - 4.0 Water Resources and Storm Water Discharge 4.1.2 MDEQ General Permit Coverage | 10-d PTE | If permit required, NOI package to CES/CEIE for review prior to submitall to MDEQ | ||||||||||||||||||
| 17 | 01 36 00 - Environmental Protection - 8.0 Hazardous Materials 8.2 HAZMAT Inventory Submittal | ANP, 30-d PTSW | Form Template in Attachment 2-01 36 00 | ||||||||||||||||||
| 18 | 01 36 00 - Environmental Protection - 8.0 Hazardous Materials 8.5 HAZMAT Closeout Report | 1 | 10-d PTFI | ||||||||||||||||||
| 19 | 01 36 00 - Environmental Protection - 10.0 Hazardous Waste 10.1 Waste Manifest | 45-d PTE | Submit to CESCEIE 731-6163 | ||||||||||||||||||
| 20 | 01 36 00 - Environmental Protection - 11 Solid Waste 11.5.2 Summary of Solid Waste Disposal and Diversion | 10th Each Month | Attachment 1-01 36 00 | ||||||||||||||||||
| 21 | 01 70 00 Execution and Closeout Requirements - 1.3A Demolition Plan | 3 | 30D PSW | ||||||||||||||||||
| 22 | 01 70 00 Execution and Closeout Requirements - 1.3B Cutting and Patching: work clearance | 3 | 30D PSW | ||||||||||||||||||
| 23 | 01 70 00 Execution and Closeout Requirements - 1.3C Project Record Documents | 3 | 30D PPC | ||||||||||||||||||
| 24 | |||||||||||||||||||||
| 25 | DIVISION 02 - EXISTING CONDITIONS | ||||||||||||||||||||
| 26 | 02 41 00 Demolition - 1.4A Site Plan | 3 | 30D PSW | ||||||||||||||||||
| 27 | 02 41 00 Demolition - 1.4B Demolition Plan | 3 | 30D PSW | ||||||||||||||||||
| 28 | 02 41 00 Demolition - 1.4C Project Record Documents | ||||||||||||||||||||
| 29 | |||||||||||||||||||||
| 30 | DIVISION 03 - CONCRETE | ||||||||||||||||||||
| 31 | Section 03 30 00 Cast-in-Place-Concrete 1.3.A Submittals - Concrete Mix Design | 30-PTSW | Submit written reports for each proposed mix for each class of concrete | ||||||||||||||||||
| 32 | 03 30 00 Cast-in-Place Concrete - 1.3A Concrete Mix Design | 3 | 30d - BBCW | ||||||||||||||||||
| 33 | 03 30 00 Cast-in-Place Concrete - 1.3B Product Data | 2 | 2 | 30d - BBCW | |||||||||||||||||
| 34 | 03 30 00 Cast-in-Place Concrete - 1.3C Shop Drawings | 2 | 30d BBCW | ||||||||||||||||||
| 35 | 03 30 00 Cast-in-Place Concrete - 1.3D Cold Weather Placing Plan | 2 | 30d BBCW | ||||||||||||||||||
| 36 | 03 30 00 Cast-in-Place Concrete - 1.3E Hot Weather Placing Plan | 2 | 30d BBCW | ||||||||||||||||||
| 37 | 03 30 00 Cast-in-Place Concrete - 1.3F Batch Tickets | 1 | TD | ||||||||||||||||||
| 38 | 03 30 00 Cast-in-Place Concrete - 1.4 Quality Control | 1 | Submit to the Contracting Officer for Approval in accordance with ACI 121R. | ||||||||||||||||||
| 39 | 3 30 00 Cast-in-Place Concrete - 3.14 Concrete Tests - Compressive Strength, Slump, Air Content, Temperature | 2 | 7d - ATT | ||||||||||||||||||
| 40 | DIVISION 26 - ELECTRICAL | ||||||||||||||||||||
| 41 | 26 00 00 General Provisions for Electrical Work - 1.2.A. Qualifications | 3 | 30 D ANP | ||||||||||||||||||
| 42 | 26 00 00 General Provisions for Electrical Work - 1.3 Codes, Regulations and Permits | ANP | Obtain and arrange for all permits and approvals required for work | ||||||||||||||||||
| 43 | 26 05 19 Low-Voltage Electrical Power Conductors and Cables - 1.3.A. Product Data | 3 | 30 D ANP | ||||||||||||||||||
| 44 | 26 05 19 Low-Voltage Electrical Power Conductors and Cables - 1.4.A. Informational Submittals - Qualification data | 3 | 30 D ANP | ||||||||||||||||||
| 45 | 26 05 19 Low-Voltage Electrical Power Conductors and Cables - 1.4.B. Field Quality Control Test Reports | 3 | 7 D ATT | ||||||||||||||||||
| 46 | 26 05 26 Grounding and Bonding for Electrical Systems - 1.3A. Product Data | 3 | 30 D ANP | ||||||||||||||||||
| 47 | 26 05 26 Grounding and Bonding for Electrical Systems - 1.3B. Wiring Diagrams | 3 | 30 D ANP | ||||||||||||||||||
| 48 | 26 05 26 Grounding and Bonding for Electrical Systems - 1.3C. Test Reports | 3 | 7 D ATT | ||||||||||||||||||
| 49 | 26 05 26 Grounding and Bonding for Electrical Systems - 1.4A. Manufacturer's Qualifications | 3 | 30 D ANP | ||||||||||||||||||
| 50 | 26 05 26 Grounding and Bonding for Electrical Systems - 1.4B. Installer Qualifications | 3 | 30 D ANP | ||||||||||||||||||
| 51 | 26 05 29 Hangers and Supports for Electrical Systems - 1.4A. Product Data | 3 | 30 D ANP | ||||||||||||||||||
| 52 | 26 05 29 Hangers and Supports for Electrical Systems - 1.4B. Shop Drawings | 3 | 30 D ANP | ||||||||||||||||||
| 53 | 26 05 43 Underground Ducts and Raceways for Electrical Systems - 1.4A. Product Data | 3 | 30 D ANP | ||||||||||||||||||
| 54 | 26 05 53 Identification for Electrical Systems - 1.3. Product Data | 3 | 30 D ANP | ||||||||||||||||||
| 55 | 26 22 00 Low-Voltage Transformers - 1.3A. Product Data | 3 | 30 D ANP | ||||||||||||||||||
| 56 | 26 22 00 Low-Voltage Transformers - 1.3B. Shop Drawings | 3 | 30 D ANP | ||||||||||||||||||
| 57 | 26 22 00 Low-Voltage Transformers - 1.3.B.1 Shop Drawings - Wiring Diagrams | 3 | 30 D ANP | ||||||||||||||||||
| 58 | |||||||||||||||||||||
| 59 | DIVISION 31 - EARTHWORK | ||||||||||||||||||||
| 60 | 31 23 33 Trench Excavation and Backfill for Pipelines and Appurtenant Structures - 1.8 Protection of Existing Properties and Utilities Notices | 21D PTSW | |||||||||||||||||||
| 61 | |||||||||||||||||||||
| 62 | DIVISION 32 - EXTERIOR IMPROVEMENTS | ||||||||||||||||||||
| 63 | 32 10 00 Asphaltic Concrete Pavement - 1.1A Submittals, Crushed Gravel Material Properties | 3 | 30D PSW | ||||||||||||||||||
| 64 | 32 10 00 Asphaltic Concrete Pavement - 1.1B Submittals, Plant Mix Gravel | 3 | 30D PSW | ||||||||||||||||||
| 65 | 32 10 00 Asphaltic Concrete Pavement - 1.1C Submittals, Asphalt Cement | 3 | 30D PSW | ||||||||||||||||||
| 66 | 32 10 00 Asphaltic Concrete Pavement - 1.1D Submittals, Tack Coat | 3 | 30D PSW | ||||||||||||||||||
| 67 | 32 10 00 Asphaltic Concrete Pavement - 1.1E Submittals, Asphaltic Mix Design | 3 | 30D PSW | ||||||||||||||||||
| 68 | 32 10 00 Asphaltic Concrete Pavement - 1.1F Submittals, Quality Control Test Results | 3 | 7D ATT | ||||||||||||||||||
| 69 | 32 92 00 Seeding and Sodding - 1.2A Sod Composition Certification | 3 | 30D PSW | ||||||||||||||||||
| 70 | 32 92 00 Seeding and Sodding - 1.2B Grass Seed Mixture | 3 | 30D PSW | ||||||||||||||||||
| 71 | 32 92 00 Seeding and Sodding - 1.2C Topsoil | 3 | 30D PSW | ||||||||||||||||||
| 72 | 32 92 00 Seeding and Sodding - 1.2D Fiber Mulch | 3 | 30D PSW | ||||||||||||||||||
| 73 | |||||||||||||||||||||
| 74 | DIVISION 33 - UTILITIES | ||||||||||||||||||||
| 75 | 33 05 23.13 Utility Horizontal Directional Drilling - 1.2A Preconstruction: Qualifications, HDD Plan | 3 | 3 | 30D ANP | |||||||||||||||||
| 76 | 33 05 23.13 Utility Horizontal Directional Drilling - 1.2B Product Data: Pipe | 3 | 30D ANP | ||||||||||||||||||
| 77 | 33 05 23.13 Utility Horizontal Directional Drilling - 1.2B Certificates: Drill Rod | 3 | 30D ANP | ||||||||||||||||||
| 78 | 33 05 23.13 Utility Horizontal Directional Drilling - 1.2B Closeout: Record Drawings, Work Logs | 3 | 30D PPC | ||||||||||||||||||
| 79 | 33 14 33 Packaged Pumping Systems for Water Utility Service - 1.3B Product Data | 3 | 30D ANP | ||||||||||||||||||
| 80 | 33 14 33 Packaged Pumping Systems for Water Utility Service - 1.3C Shop Drawings | 3 | 30D ANP | ||||||||||||||||||
| 81 | 33 14 33 Packaged Pumping Systems for Water Utility Service - 1.3D Source QC reports | 3 | 30D PSW | ||||||||||||||||||
| 82 | 33 14 33 Packaged Pumping Systems for Water Utility Service - 1.3E Manf Qualifications Statement | 3 | 30D ANP | ||||||||||||||||||
| 83 | 33 14 33 Packaged Pumping Systems for Water Utility Service - 1.3F Field QC Reports | 3 | 7D ATT | ||||||||||||||||||
| 84 | 33 14 33 Packaged Pumping Systems for Water Utility Service - 1.3G O&M Data | 3 | 30D PPC | ||||||||||||||||||
| 85 | 33 14 33 Packaged Pumping Systems for Water Utility Service - 1.3H Warranty | 3 | 30D PPC | ||||||||||||||||||
| 86 | 33 14 33 Packaged Pumping Systems for Water Utility Service - 1.3.5 System Commissioning | 3 | 30D PPC | Comssioning Report, Level Setpoint Redlines | |||||||||||||||||
| 87 | |||||||||||||||||||||
| Schedule of Abbreviations: | |||||||||||||||||||||
| AFI = | After Final Inspection | PTE= Prior to Event | |||||||||||||||||||
| ANP= | After Notice to Proceed | PTFI= Prior to Final Inspection | |||||||||||||||||||
| ATT= | After Test Taken | PTSW = Prior to Start of Work | |||||||||||||||||||
| BBCW= | Before Beginning Concrete Work | PPC = Prior to Project Completion | |||||||||||||||||||
| BD= | Before Delivery | TD = Time of Delivery |
&"Times New Roman,Regular"&12MALMSTROM AFB, MONTANA &"Times New Roman,Regular"&12
&"Times New Roman,Regular"&12AF Form 66 Repair HTHW Sump Pumps Schedule-&D &"Times New Roman,Regular"&12 01330a-&P
REQUIRED TECHNICAL SUBMITTALS
File details come from the government source that posted it. Updated .