26-ITB-018_FIN_ATCT_Rehab_Abbreviated_Design_Criteria_Package.pdf
PDF 12 MB Posted
- Attached to
- Air Traffic Control Tower Rehabilitation
- Solicitation number
- 26-ITB-018
- Issued by
- Glades County, Brownsville CDP, Florida
About this file
This is a Design Criteria Package (DCP) for the Air Traffic Control Tower (ATCT) Rehabilitation project at Flagler Executive Airport in Florida. The document serves as the primary design guide for the invitation to bid and contains directives, specifications, and technical details necessary for contractors to provide accurate pricing. The project encompasses comprehensive rehabilitation of the ATCT structure and supporting infrastructure, including building envelope repair and repainting, structural repairs and improvements to the tower structure and catwalk, tower cab interior upgrades (carpet, cabinets, countertops, and ceiling repairs), replacement of roof hatches, installation of new air conditioning systems (7 package terminal air conditioners and 2 rooftop units), interior painting of the tower cab and vestibule, and consolidation of access control systems (vehicular gate, tower entry door, and elevator) under a unified card-based security system. Additional scope items contingent upon funding availability include handrail upgrades, exterior tower up-lighting, vehicular gate operator replacement, bollard repainting, and asphalt seal coating and re-striping within the ATCT security-fenced parking area.
The Design Criteria Package provides the specifications and technical requirements that form the basis for contractor proposals and pricing submissions. As the primary design document for the solicitation, the DCP establishes the standards and scope parameters that guide all bidding activity. The document does not indicate specific response deadlines, site visit requirements, or bidders' conference information within the abbreviated package. Funding sources, contract award timelines, and contract term details are to be determined through the formal bidding process and subsequent invitation to bid documentation.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABBREVIATED DESIGN CRITERIA PACKAGE (ADCP)
CONFORMED DOCUMENTS FOR CONSTRUCTION
AVCON PROJECT #: 2026.0355.03
For
FLAGLER EXECUTIVE AIRPORT (FIN):
AIR TRAFFIC CONTROL TOWER
REHABILITATION
201 Airport Road Palm Coast, Florida 32164
JULY 24, 2026
Prepared By:
KMA Design Group, LLC.
P.O. Box 140201
Orlando, Florida 32814
(407) 810-2606
TABLE OF CONTENTS
Title Section Pages
1. General Requirements 1-3
2. Structural Narrative 4-8
3. Architectural /Building Envelope Narrative 9-20
4. Mechanical Narrative 21-34
5. Electrical Narrative 35-41
6. Plumbing Narrative 42-43
7. Supplemental Product Specifications APPENDIX A
GENERAL REQUIREMENTS
Existing Campus Background
The Flagler Executive Airport (FIN) is a county-owned, public use, general aviation airport operated and maintained under the Flagler County Board of County Commissioners. The airport accommodates more than 175,000 general aviation takeoffs and landings each year. There are no scheduled airlines providing service to the airport.
Located on the east side of Flagler County on State Road 100, the airport sits at the gateway to natural attractions, golf courses, and pristine beaches just four miles away. The airport comprises over 1,465 acres, bordering the City of Palm Coast. It is a towered field with two intersecting runways -- Runway 11-29 (5,500' x 100') and Runway 6-24 (5,000' x 100') -- and a water runway, Runway 18W-36W (3,000' x 500'), on Gore Lake within the airport property.
Existing Air Traffic Control Tower (ATCT)
The existing Air Traffic Control Tower is a seven (7) story facility of approximately 4,375 GSF and is a 25FT-by- 25FT precast concrete structure (4-sided) with a 6-sided cab floor at the top for air traffic control crew members to observe the 360 degree view of the airport. Floors are poured concrete, exterior walls are painted concrete tilt-wall panels, and the roof is a trapezoidal panel, standing seam mansard metal roof system with a modified bitumen membrane roofing system over tapered insulation board system. Other features include laminated double glazing within a storefront frame around the cab level, a concrete catwalk (flush metal panel system over steel beams below) with galvanized steel guard railing and metal wall panels at the top of the cab.
Definitions
• Certified General Contractor (CGC): A Florida licensed General Contractor who has been certified in accordance with Florida Statutes, Section 489.
• Abbreviated Design Criteria Package (ADCP): The package of performance criteria, existing as-built drawings, and specifications to be used by the CGC to correct and construct the project, and as further defined under Florida Statutes, Section 287.055.
• Guaranteed Maximum Price (GMP): CGC final contract price to perform all work specified in this ADCP.
CGC Requirements
• This project will be bid and awarded based on company qualifications and price. The selected CGC will bear full responsibility for any permitting requirements, construction and meeting all applicable Code requirements, Flagler Executive Airport Standards and Guidelines and Design Review Committee (DRC) requirements.
• During the performance of this contract, the CGC shall comply with all federal, state, and local environmental laws, regulations, policies, Flagler Executive Airport standards and other standards as required.
• The project shall retain the services of a CGC, licensed in the State of Florida, for the remedial efforts of the renovation. The CGC shall acquire material and products from reputable vendors and comply fully with the manufacturer’s recommendations, training, and installation and application instructions.
• During construction, the CGC shall keep an up-to-date annotated set of as-built drawings on site. At completion of the construction phase, original documents shall be updated/documented to the most current as-built condition and shall be provided to Flagler Executive Airport in CD or thumb drive format.
• The CGC shall be responsible for identifying and securing all necessary permits required for the project. The CGC shall pay for all required permit fees applicable to the project.
• CGC shall reference the existing as-built drawings (July 2008) to be provided by Flagler Executive Airport for reference to the original design intent as the ADCP shall indicate all known remedial requirements that were requested by Flagler Executive Airport.
Special Conditions
• The CGC shall be advised that the ATCT parking and other site areas will remain vacant and available to the CGC during the duration of the construction period. The CGC shall coordinate with Flagler Executive Airport to obtain direct access into the facility as required.
• For anyone accessing the site, the CGC must meet all Flagler Executive Airport security requirements and be properly badged or be escorted by a badged individual.
Existing Site Information
• The CGC shall be thoroughly familiar with all existing site conditions prior to construction. Investigate all existing site components and include any modifications, removal, or re-location necessary to accommodate the building façade renovations described herein.
• If necessary, temporary hook up of utilities shall be coordinated at a source location directed by Flagler Executive Airport. All temporary hook-ups and tie-ins shall comply with all local codes and requirements and shall be the responsibility of the CGC. All temporary tie-ins to the building water system shall be provided with proper backflow prevention devices.
• Vehicle parking for CGC personnel, subcontractors and other project-related vehicles and equipment is available on site.
• The CGC shall be responsible for any security measures, including fencing, required to secure their materials and protect members of the public from access to hazards during construction.
• CGC shall fence the area out of the Air Operations Area (AOA) and meet the Homeland Security requirements for fencing.
• In the event the CGC encounters on-site material believed to be hazardous material, such as asbestos or polychlorinated biphenyl (PCB), the CGC shall immediately stop work in the area affected and verbally report the condition to Flagler Executive Airport followed by notification in writing. The work in the affected area shall not thereafter be resumed except by written agreement between Flagler Executive Airport and the CGC if in fact the material is hazardous and has not been rendered harmless. The work in the affected area shall be resumed if the material is not hazardous, or if it has been rendered harmless, by the written agreement of Flagler Executive Airport and the CGC.
• The CGC shall follow the Airport requirements as indicated below regarding site-related procedures:
o Interior – Cover and prep when working around any and all equipment. The CGC shall not disrupt services, operations, or utilities without obtaining the Airport’s approval and instruction in each case.
o Exterior – The CGC shall always keep the premises free of accumulation of waste materials or rubbish caused by his operations or the operations of any other subcontractors within the area of work.
Methods for such removal must be agreeable to the Airport.
• The CGC shall comply with all the rules and regulations of the building as to hours of availability of elevators, loading areas, etc., for the purpose of delivery and the manner of handling materials, equipment, and debris, to avoid conflict or interference with normal building operations. After-hours work shall be coordinated with the Airport Director.
Existing Utilities
The CGC shall provide any utility service modifications necessary to accomplish the work. The names and points of contact for the utilities at the Airport consisting of FAA, Flagler Executive Airport and local utility companies shall be provided and shared between all stakeholders.
Validity of Information Provided
The CGC will, at their own expense, verify and accept as their own, all information provided by Flagler Executive Airport.
In addition, the CGC shall provide any additional items that may be further required and need remedial efforts, etc., that are necessary to supplement the available information to provide a complete, professionally constructed project consistent with the intent of the ADCP.
Project Information
• Project Location: The site for the project is located at 1050 Fin Way, Palm Coast, FL 32164; Flagler Executive Airport (FIN ATCT).
• Project Description: This project consists of providing remedial and corrective design intent for the ATCT through this ADCP (written narratives and supplemental specifications) for a CGC to build; all while referencing the original as-built drawings and specifications as no other construction documents are to be provided.
• There is no Leadership in Energy and Environmental Design (LEED) or Green Globe requirements, however, this project shall apply sustainability principles throughout the construction process.
• It is the intent of these project requirements that the CGC deliver to Flagler Executive Airport a complete, finished, and restored facility.
• Materials shall be durable, permanent, vandal-resistant, easily maintained, and within the limits set by budget, function, and code.
• The local permitting agency with authority over this project is the Flagler County Building Department, 1769 E.
Moody Blvd., Building 2, Bunnell, Florida 32110.
Warranties
General: The required final constructed product shall be a completely warranted and guaranteed project both in terms of materials provided and the installation, labor, equipment, tools, and methods used.
Products and Substitutions
A product proposed as an “equal” shall be such that all its salient characteristics conform to those of the initially proposed brand name product. These salient characteristics may include, but are not limited to:
design, function, size, quality, durability, color, style, texture, and other attributes which, given the nature of the project, may significantly affect its acceptability as a substitute for the listed product.
Certifications
Upon completion of the work, the CGC and their subcontractors shall certify the installation according to their recommendations and instructions and issue warranties and guarantees as a condition of project close-out and final payment.
STRUCTURAL
General Requirements
The air control tower structure was constructed with precast concrete wall panels. The cab was constructed with steel framing. The floor beams of the tower consisted of wide-flange steel beams that cantilevered off the main tower concrete walls to support the catwalk. The catwalk was constructed with galvanized steel deck and a reinforced concrete slab. The catwalk perimeter had steel guardrails.
Existing Conditions
The steel wide-flange beams that supported the perimeter of the catwalk, and the main support beams that cantilevered off the tower walls, had multiple areas that were severely corroded with section loss, delaminated steel, and were structurally compromised. The corrosion appeared generally limited to the area underneath the catwalk, as the steel framing underneath the tower was partially protected by spray-on fireproofing.
It is our opinion that the catwalk steel framing was in very poor condition and unsafe. All the steel framing extending outward from the tower will need to be removed and replaced. It is our recommendation that a different catwalk design be considered, consisting of aluminum beams bolted to the existing steel moment connections, fiberglass or aluminum structural grating, and aluminum guardrails. This design greatly lightens the dead load by eliminating the concrete slab, which will also reduce construction costs. Aluminum offers far superior resistance to corrosion than steel, and the open grating would allow water to freely drain and also allow for drying of the aluminum framing.
Scope of work items are listed in RED.
Photo #1: Aerial view of the tower and arrow indicating the northeast corner. Reference Photo #2.
Photo #2: Reference Photo #1. View of the northeast corner of the top of the tower concrete walls. The concrete was cracked and spalled. Remove all cracked, spalled, and unsound concrete and inspect rebar for corrosion. Clean rebar and replace/repair as required. Replace concrete with approved patching compound by Sika or similar.
Photo #3: Typical view of the steel framing along the perimeter of the catwalk. Steel was severely corroded throughout the perimeter of the catwalk and at multiple locations underneath the catwalk. The entire catwalk is considered structurally unsound and beyond repair and will have to be completely replaced with a similar system, though we recommend consideration of aluminum framing.
Photo #4: Typical view of a removed section of corroded and delaminated steel from the catwalk framing.
Photo #5: Typical view of the underside of the catwalk and the steel framing. The steel framing directly underneath the tower generally exhibited signs of minor corrosion, with some areas of more advanced corrosion. It appeared that spray-on fireproofing had protected much of the steel framing underneath the tower. Clean off all corrosion with wire brush or other method and reinspect steel framing.
Photo #6: View of the underside of the southwest corner of the catwalk and the steel framing. This condition was observed at several locations, where there was severe corrosion and delamination of the main support beams. The cantilevered beams were bolted at the tower walls and appeared they could be removed and replaced with aluminum or steel, reference Photo #7.
Photo #7: Reference Photo #6. It appeared the cantilevered support beam was connected underneath the tower via a moment connection. The cantilevered beams were bolted at the tower walls and appeared they could be removed and replaced with aluminum or steel.
Photo #8: Underside of the southwest catwalk, moderate level of corrosion observed on the steel framing on top of the tower walls. Clean off all corrosion with wire brush or other method and reinspect steel framing. Relatively minor repairs such as welding on additional steel may be required.
Photo #9: Underside of the northwest corner of the catwalk, moderate level of corrosion observed on the steel framing and deck. Clean off all corrosion with wire brush or other method and reinspect steel deck. Relatively minor repairs such as welding on additional steel deck may be required, beam indicated by left arrow to be replaced.
ARCHITECTURAL / BUILDING ENVELOPE
General Requirements
The project shall be constructed in accordance with the current editions of all applicable state and local codes, standards, design parameters, or regulations. In the event of conflict between codes, standards, or regulations, the most stringent requirement shall apply.
• 2023 Florida Building Code, 8th Edition
• 2023 Florida Building Code – Mechanical, 8th Edition
• 2020 National Electrical Code (NEC)
• 2023 Florida Fire Prevention Code
• 2021 Life Safety Code (NFPA 101) Florida
• UL, Inc. Fire Resistance Directory – Latest Edition
• Florida Department of Transportation (FDOT) Standards
• Federal. Aviation Administration (FAA)
Existing Conditions
Scope of work items are listed in RED.
ROOF:
The existing roof system on the Control Tower is a granule surfaced, modified bitumen roof system manufactured by Siplast. This roof system was installed over rigid insulation and a metal deck.
• Remove and replace the existing roof system including insulation (install a new roof system using FiberTite XT 50 membrane over tapered insulation over 4” polysio roof insulation over a 1/2” coverboard).
• Install new drain strainers and inspect the clamping rings. Replace any broken drain clamping rings and tap any broken roof drain bolts. Replace new bolts with stainless steel fasteners.
• Install new lightning protection.
PARAPET WALL PANELS:
The walls are metal framed structures covered with metal wall panels (front side and back side). Parapet tops are covered with coping metal, cleated in the front and a mechanically attached to the rear face.
• Remove and replace metal wall panel system (backside only), using Pac-Clad (Flush Wall Panels). Final color to be selected by Owner from the standard choice options. The current exiting color close match would be “Slate Gray.” Contractor shall maintain the metal plates for existing equipment connections with S.S. Unistrut.
• Remove and replace the existing metal coping.
• Retain the metal mansard panels outside the wall panels.
ROOF TOP CURBS, HATCH, LADDER:
There are two air conditioner units mounted on the roof, the curbs are in fair condition. There is one access hatch to the cab roof area. The hatch should be replaced with a new one at the time of roofing.
• Replace the roof hatch and ladder.
• Remove the HVAC curbs and install new curbs in coordination with the mechanical contractor.
CATWALK:
The surrounding catwalk area is deteriorated and shows signs of corrosion and damage. The recommendation is:
• Provide new aluminum beams bolted to the existing steel moment connections.
• Provide new aluminum structural grating and new aluminum decorative guardrails.
• Provide new catwalk access door with new door hardware and paint and replace metal panel(s) adjacent.
EXTERIOR CONCRETE WALLS:
The exterior structure is a 7-story cast panel system. The concrete panels have been sealed with a urethane sealant that is beginning to age and craze. The concrete panels have been painted, and the paint is aging and in need of re-painting.
• Cut out the old control joint sealant and backer rod. Install new backer rod and seal with DOWSIL 790 Sealant.
• Prep, prime, and paint the exterior precast concrete walls with DOWSIL ALLGUARD Silicone Elastomeric Coating.
• Replace both exterior hollow metal doors and door hardware. Paint new hollow metal doors and existing hollow metal frames.
FIXED FRAME WINDOWS IN THE EXTERIOR CONCRETE WALL PANELS:
There are aluminum fixed framed windows in the Tilt-Wall panels. These windows appear to be functioning. The urethane sealant around the windows is beginning to crack and craze and in need of replacement.
• Cut out the old sealant and install new Dowsil 795 sealant.
WINDOWS AT THE TOP FLOOR OF THE CONTROL TOWER:
• Remove all cracked/shrunken window gaskets.
• Clean all joints, removing all foreign matter and contaminants such as grease, oil, dust, water, frost, surface dirt, old sealants or glazing compounds and protective coatings.
• Install backing material or joint filler, setting blocks, spacer shims, and tapes. Mask areas adjacent to joints to ensure neat sealant lines. Primer is generally not required on nonporous surfaces but may be necessary for optimal sealing of certain porous surfaces. A test placement is always recommended.
Apply DOWSIL™ 795 Silicone Building Sealant in a continuous operation using positive pressure. (The sealant can be applied using many types of air-operated guns and most types of bulk dispensing equipment.)
Before a skin forms (typically within 15 minutes), tool the sealant with light pressure to spread the sealant against the backing material and joint surfaces. Remove masking tape as soon as the bead is tooled.
• Provide a 20-year manufacturer warranty.
• Provide Contractors’ 5-year leak free warranty.
EXTERIOR PAINT COLORS:
All colors shall be Sherwin Williams (Pro Industrial DTM Acrylic Coating). The colors shall be the following Basis of design:
Main Building: SW 7030 Anew Gray Catwalk/Guardrail/H.M. Doors/Frames: SW 7068 Grizzle Gray
*The contractor shall provide three (3) varying shades (tone on tone) of each color as listed above for “drawdowns” on the building for the airport director to see in full sunlight prior to making the final approved selection.
INTERIOR REMEDIATION
• Replace ACT/grid in the control tower cab area (black).
• Contractor shall replace the pull-down access ladder from the cab to the roof (B.O.D.: Louisville Ladder).
• Contractor to replace all carpet in the control tower cab.
• Contractor to paint the entire interior of the control tower cab and at the ground entry vestibule.
• Where the current countertop/break area is located within the control tower cab, contractor shall remove the existing countertop, sink, and support brackets and replace with new millwork (including countertop, lower cabinets and new sink with faucet and adjustable controls).
• At all new PTAC unit installations, contractor shall make sure the drywall is properly sealed/caulked to the unit and painted to match the wall color for each floor.
ROOF:
Photo #10: Existing modified bitumen membrane system. Replace with FiberTite XT 50 membrane.
Photo #11: Existing internal roof drain strainer to be replaced and reroute the RTU condensate piping below.
PARAPET WALL:
Photo #12: Remove the flush metal wall panel system in its entirety and replace them with new metal wall panels.
Photo #13: Remove and replace existing coping cap.
Photo #14: Existing metal roof panel to remain.
ROOF TOP CURBS, HATCH, LADDER:
Photo #15: Remove the existing HVAC curbs and install new curbs. Remove and replace the existing roof access hatch.
CATWALK:
Photo #16: Remove and replace catwalk access door, door hardware, and paint. Also remove and replace the adjacent metal wall panels to eliminate the seam and associated patchwork.
EXTERIOR CONCRETE WALLS:
Photo #17: Existing stucco on the tilt-wall panel system reflects staining. This shall be cleaned, primed, and painted.
Photo #18: Cut out and install new backer rod and seal with DOWSIL 790 Sealant.
Photo #19: Replace exterior hollow metal door and door hardware. Paint door and existing H.M. Frame.
WINDOWS AT THE TOP FLOOR OF THE CONTROL TOWER:
Photo #20: Remove and replace sealant with DOWSIL 795 Silicone at the cab windows.
Photo #21: Remove and replace sealant with DOWSIL 795 Silicone at the cab windows.
INTERIOR REMEDIATION:
Photo #22: Existing access ladder is in poor condition. Contractor shall replace one for one and install per Manufacturer’s recommendations (B.O.D.: Louisville Ladder 7’-8” x 22.5” x 3” Insulated or similar to fit).
Photo #23: All existing ACT shall be removed and replaced with new ACT.
Photo #24: Existing carpet to be removed and replaced. Also, countertop, sink and support brackets are to be removed and replaced with new millwork (including countertop, lower cabinets, and new sink).
Photo #25: At all new PTAC unit installations, contractor shall make sure the drywall is properly sealed/caulked to the unit and painted to match the wall color for each floor.
Outline Specifications
Below are the following technical sections anticipated to be included in the scope of work for the project:
DIVISION 07: THERMAL & MOISTURE
07 01 91 - Joint Sealant Rehabilitation and Replacement (Basis of Design: DOWSIL™ 790 and DOWSIL™ 795 Silicone Building Sealant) Refer to APPENDIX A for both.
DIVISION 9: FINISHES
09 50 00 – Acoustical Ceiling Tile (2’x2’ black, 15/16” tegular edge) Refer to APPENDIX A.
09 80 00 – Elastomeric Coatings for DOWSIL ALLGUARD Silicone Elastomeric Coating Refer to APPENDIX A.
MECHANICAL SYSTEMS
Applicable Design Codes & Standards A complete mechanical design will be provided for this project in accordance with the standards in the latest editions of the following listed applicable codes, ordinances, laws, and regulations.
Among them are the latest adopted editions of:
• 2023 Florida Mechanical Code
• 2023 Florida Energy Efficiency Code
• Florida Fire Prevention Code
• American Society of Heating, Refrigeration, and Air Conditioning Engineers (ASHRAE) Standards
• NFPA 90A, Installation of Air Conditioning and Ventilating Systems
• National Fire Code (NFC)
• SMACNA Standards
• Flagler Executive Airport Standards and Guidelines
HVAC
Below are the existing HVAC systems and recommendations. Scope of work items are listed in RED. A schematic is also provided visually indicating the anticipated scope (See Schematic “A”).
• The existing five (8) story air traffic control tower at the Flagler airport is currently served by a combination of rooftop units, packaged terminal air conditioning units (PTACs) and a wall mounted mini split (electrical room).
o The first floor contains storage, elevator equipment, electrical and a fire pump room. This floor has one (1-ton) existing mini split in the electrical room.
▪ One (1) (1-ton) mini split AHU and CU shall be replaced, one for one, with similar units in electrical room. Unit shall be equal to LG KSUAB121A / KNUAB121A, 208V 1ph, Heat pump, 12a/15a MCA/MOCP.
• Coordinate with electrical contractor on the reuse of the existing equipment circuit.
Contractor shall upgrade circuit and breaker as required to accommodate new unit.
• Mount all unit high on wall in room and provided with integral condensate pump.
Route 1” PVC condensate from room to exterior and terminate a min of 8” above greenery or shrubbery.
• Mount on a 6” turned down exterior concrete pad utilizing hurricane condensing unit clips to meet all hurricane wind loading requirements. Contractor shall bid new but may reuse the existing condensing unit pad if approved by owner.
o The second through seventh floor contains office, storage, and equipment areas. Floor’s 2,3,4,5, & 7 are served by one (1) 15,000btu/h (1.25 ton) PTAC. Floor 6 is served by two (2) 15,000btu/h (1.25 ton) PTAC’s. These units each contain a 2KW heater and are 208V/1ph units.
▪ PTAC units were replaced approximately in 2020 with Gree Units. Flagler Control Tower personnel have voiced concern with the cooling capacity of these units. Engineer observed that the PTAC’s could not produce a comfort cooling level and that the space’s maintained hot areas even with a set temperature of 70 degrees.
▪ PTAC’s shall be replaced, one for one, with a (1) 15,000btu/h (1.25 ton) PTAC. Units shall be equal to Friedrich 105MBH PDE15K5SGR3 with 2.5kW heater; 208V 1ph, 14a/20a MCA/MOCP.
• Coordinate with electrical contractor on the reuse of the existing equipment circuits.
Contractor shall upgrade circuit and breaker as required to accommodate new unit.
• Balance units to match existing outside airflow rates.
o The Control tower level is served by two (2) Trane 36,000 btu/h (3 ton) nominal capacity packed roof top units (RTUs) mounted on the cab roof. Each unit is straight cool with electric heat and are 208V/3ph units.
▪ RTU’s RTU shall be replaced, one for one, with two (2) new Lennox LCX036S5D, 208V 3ph, 7.5 KW heat, 24a/25a MCA/MOCP or equal.
• Coordinate with electrical contractor on the reuse of the existing equipment circuit.
Contractor shall upgrade circuit and breaker as required to accommodate new unit.
• Contractor shall reconnect new condensate line to existing condensate infrastructure.
• Provide curb adaptor and re-mount as required to meet all wind loading requirements.
• Balance units to match existing outside airflow rates.
▪ The Cab acoustic ceiling tile and air terminal devices mounted withing (diffuser and return grilles) shall be replaced one for one. Contractor shall connect new lay-in ceiling devices into existing ductwork, matching existing style and size (face and neck size). Contractor shall replace any ductwork that cannot be reused.
• General Scope Notes:
o The contractor shall verify that no campus controls system is used for monitoring or control of the HVAC systems serving this building. If so, contractor shall tie all new equipment into existing controls system.
▪ Provide new controls (thermostats or other) for all new equipment.
o Contractor shall budget all demo work into the scope of work along with full removal and disposal costs of all demolished equipment. Though, contractor shall offer salvage rights to the owner on any equipment removed.
o Prior to bid the contractor shall visit the site to establish existing conditions. Prior to construction, the contractor shall verify all equipment sizes, quantities, and power requirements for coordination with new work.
o Contractor shall budget any ancillary repair work required for the scope of work described. This may include, but is not limited to, paint, drywall, concrete, piping, and other accessories.
o Where required, a full test and balance exercise and report shall be provided to the owner for any new HVAC system.
Photo #26: First floor mini split.
Photo #27: First floor mini-split.
Photo #28: First floor mini-split.
Photo #29: Second floor PTAC.
Photo #30: Second floor PTAC.
Photo #31: Third floor PTAC.
Photo #32: Third floor PTAC.
Photo #33: Fourth floor PTAC.
Photo #34: Fourth floor PTAC.
Photo #35: Fifth floor PTAC.
Photo #36: Fifth floor PTAC.
Photo #37: Sixth floor PTAC.
Photo #38: Sixth floor PTAC.
Photo #39: Sixth floor PTAC.
Photo #40: Sixth floor PTAC.
Photo #41: Seventh floor PTAC.
Photo #42: Control Tower RCP.
Photo #43: Control Tower RCP.
Photo #44: Control Tower RTUs.
Photo #45: Control Tower RTU data.
Photo #46: Control Tower RTU data.
ELECTRICAL SYSTEMS
All electrical work completed shall be by a licensed electrician and in accordance with all local, state, and national codes and standards. Among them are the latest adopted editions of:
• American with Disabilities Act (ADA)
• American National Standards Institute (ANSI)
• 20203Florida Building Code
• National Electrical Safety Code (IEEE-C2)
• National Electrical Manufacturers Association (NEMA)
• National Electrical Code 2020 (NFPA 70)
• National Fire Alarm Code (NFPA 72)
• Florida Fire Prevention Code NFPA 1
• NFPA 101 Life Safety Code
• Standard for Emergency and Standby Power Systems
(NFPA 110)
• Standard for the Installation of Lightning Protection Systems
(NFPA 780)
• The Occupational Safety and Health Act (OSHA)
• Underwriters’ Laboratories, Inc. (UL)
The electrical scope of work for this project is depicted below. Scope specific items are listed in RED.
Electrical Service and Power Distribution System Existing power
• Overall, this air traffic control tower building is served by a 120/208V 3ph, 400a service. This service is backed up by a 170KW generator with automatic transfer switch for backup power. A fire pump is also powered from this service. A one-line power riser diagram is shown below for reference as taken from the “New Air Traffic Control Tower” construction document set by RS&H, Inc. Dated 07/01/08.
EXISTING ELECTRICAL POWER RISER DIAGRAM (FOR REFERENCE ONLY)
• All existing power switchgear, devices, conduit, and conductors appear in good condition and shall remain as is.
• Contractor shall perform function testing of the generator to confirm it is in good working condition. If deficiencies are found, the contractor shall present a remedial action proposal to the owner for approval.
• The electrical contractor shall budget refeeding all existing mechanical units listed in the mechanical DCP narrative.
▪ Mechanical circuits provided shall be via new copper conductors in EMT conduit. All new circuiting shall be sized and routed in accordance with the procured manufacturer’s recommended circuit and MOCP sizing. All sizes shall account for max FBC voltage drop (5%) and be sized in accordance with NEC.
▪ In general, the units to be replaced shall be confirmed on site and with the mechanical contractor, but will include:
• Seven (7) packaged terminal units (PTACs).
• Two (2) packaged roof top units (RTUs).
• One (1) wall mounted mini-split unit.
▪ If found acceptable for reuse, existing circuiting may be reused to feed replaced equipment.
Though, the contractor shall verify existing breaker and conductor sizes are adequate for the new units and modify as required.
Lighting
• Exterior
• The two (2) existing exterior light fixtures on building shall be replaced, one for one, with new LED equivalent.
• There were mentions of additional grade mounted light fixtures, splashing up lighting on the building.
Owner to confirm. (Contractor shall provide new LED equivalent light fixtures)
• All interior lighting appears to be in working condition. Though:
• All existing light fixtures to be replaced, one for one, with new LED equivalent.
▪ Contractor may reuse existing circuits and control, modifying only as required to accommodate the new light fixtures.
• See below existing lighting plans as taken from the “New Air Traffic Control Tower” construction document set by RS&H, Inc. Dated 07/01/08. These are provided for reference only and all bidding shall be predicated on field verified conditions, fixture types and quantities found.
EXISTING ELECTRICAL LIGHTING PLANS (FOR REFERENCE ONLY)
Access Control
• Exterior
• The contractor shall provide a new gate control system. The system shall be congruent with the Flagler Airport access control standards, manufacturer, model, and specifications.
• The contactor shall replace the existing access control at the building’s main entrance door and elevator door. The system shall be congruent with the Flagler Airport access control standards, manufacturer, model, and specifications.
• Coordinate all access control scope and associated requirements with the owner directly and their preferred access control vendor.
Raceways and Conductors If required to replace damaged or undersized conduit/conductor, any new conduits and conductors will be as follows:
• Service entrance conductors – Schedule 40 PVC buried 36” below grade.
• Panelboard feeders – Electrical Metallic Tubing were run concealed and above grade. Rigid galvanized steel were run exposed and above grade.
• All branch conductors shall copper. Conductors feeding panels and larger than #1 may be aluminum where required.
• Modular wiring systems will not be allowed.
• MC cable may be allowed only as approved by the owner.
Fire Alarm System The building is served by an existing fire alarm system. This fire alarm system is assumed to be in good working condition and shall remain as is.
Lightning Protection
• An existing lightning protection system is provided to the building. The contractor shall repair and/or replace any arrestors or wiring to recertify the lighting protection systems. A rooftop UL Master Label lightning protection system will be required to cover all building areas. Where mechanical equipment or other external components on the roof where existing lighting protection arrestor equipment is mounted, the arrestors/equipment shall be remounted to the new equipment. All new air terminals, bonds to rooftop equipment and other metallic items, down conductors, buried counterpoise conductors and ground rods, all as per NFPA 780 and UL 96A. The system will be modified only by an LPI approved installation contractor.
Photo #47: Existing switchgear. Photo #48: Existing switchgear.
Photo #49: Existing switchgear. Photo #50: Existing switchgear.
Photo #51: Existing Control Tower lighting.
Photo #52: Existing exterior building lighting.
Photo #53: Existing exterior building access control. Photo #54: Existing exterior building access control.
Bollards shall be painted.
Photo #55: Existing exterior building access control. Photo #56: Existing exterior building access control.
Bollards shall be painted.
PLUMBING SYSTEMS
A complete plumbing design will be provided for this project in accordance with the standards in the latest editions of the following listed applicable codes, ordinances, laws, and regulations.
Among them are the latest adopted editions of:
• 2023 Florida Plumbing Code.
• 2023 Florida Energy Efficiency Code.
• Florida Fire Prevention Code.
• American Society of Heating, Refrigeration, and Air Conditioning Engineers (ASHRAE) Standards
• American Society of Plumbing Engineers (ASPE)
• NFPA 90A, Installation of Air Conditioning and Ventilating Systems
• National Fire Code (NFC)
• Flagler Executive Airport Standards and Guidelines.
Plumbing Below are the existing plumbing systems and recommendations. Scope of work items are listed in RED.
• The existing building plumbing system shall remain as is outside of other renovation work coordination.
Specifically:
o Coordinate with catwalk renovation works. Route drainage piping tight to control tower exterior surface, through catwalk structure, and along the underside of the catwalk framing to the designated perimeter discharge edge. This alignment optimizes architectural aesthetics and mitigates visual impact.
Photo #57: Roof drain piping shall be rerouted as described in plumbing section.
Photo #58: Roof drain piping shall be rerouted as described in plumbing section.
APPENDIX A
Technical Data Sheet
DOWSIL™ 790 Silicone Building Sealant
®™Trademark of The Dow Chemical Company (“Dow”) or an affiliated company of Dow
Page 1 of 4 © 2019–2020 The Dow Chemical Company. All rights reserved. Form No. 62-2147-01-0220 S2D
Ultra-low-modulus sealant for sensitive natural stone, porous stone, masonry and concrete façades
Features & Benefits
• Low-staining and plasticizer free, suitable for porous substrates
• Excellent performance even in building joints that experience extreme movement
• Extension/compression capability of +100/-50 percent
• Conforms to ISO 11600F-25LM
• Excellent weathering properties and resistance to sunlight, rain, snow, and temperature extremes
• Excellent unprimed adhesion to masonry, concrete and natural stone substrates
• Easy application over a wide temperature range
Composition
• One-part, neutral-cure silicone sealant
Applications
• Sealing of joints between natural stone
• Sealing of curtainwall joints and mullion joints
• Sealing of expansion and control joints
• Sealing of precast concrete panel joints and many other construction joints
Typical Properties Specification Writers: These values are not intended for use in preparing specifications.
Test Property Unit Result
As Supplied
CTM1 98 Skin-over Time (23°C, 50% R.H.) min 9
CTM 95 Tack-Free Time (23°C, 50% R.H.) min 31
CTM 663 Cure Rate (23°C, 50% R.H.)
1 Day 3 Days mm mm
2.8 5.8
As Cured – After 28 Days at 23°C and 50% RH
CTM 99 Durometer Hardness, Shore A 11
ISO2 8339 Modulus 100% MPa 0.08
ISO 8339 Elongation at Break % 840
1. CTMs: Corporate Test Methods. Copies of CTMs are available upon request.
2. ISO: International Standardization Organization
Page 2 of 4 © 2019–2020 The Dow Chemical Company. All rights reserved. Form No. 62-2147-01-0220 S2D
Typical Properties (Cont.)
ISO 7389 Elastic Recovery % 78
ASTM3 C 719 Joint Movement Capabilities According to ASTM Standard Extension/Compression
% +100/-50
ISO 9047 Joint Movement Capability According to ISO Standard % ±25 (highest category)
ASTM C 1248 Staining, Various Substrates None
3. ASTM: American Society for Testing and Materials.
Description Ultra-low-modulus sealant for masonry, concrete and natural stone façades. DOWSIL™ 790
Silicone Building Sealant provides excellent performance, even in building joints that experience extreme movement. It places a low stress on the sealant/substrate bond line to minimize failures in moving joints.
DOWSIL™ 790 Silicone Building Sealant is available in black and gray.
Approvals/ Specifications
This sealant meets or exceeds the requirements of:
• ISO 11600F 25LM
• EN15651 – CE MARK
• ASTM Specification C 920, Type S, Grade NS, Class 100/50, Use T, NT, M, G, A, and
O
How to Use Surface Preparation Ensure that surfaces to be sealed are clean, dry, sound and grease-free. Porous substrates such as concrete, brickwork, mortar, etc. must be mechanically cleaned of loose particles using a steel brush, sanding disc or any similar means. Clean non-porous surface with DOWSIL™ R-40 Universal Cleaner, dry thoroughly with a clean, lint-free cloth and wait for at least half an hour before application of sealant.
Note: When using any solvent, always provide adequate ventilation. Avoid heat, sparks and open flames. Use solvent resistant gloves. Observe and follow all precautions listed on solvent container label.
Masking Areas adjacent to the joints should be masked with tape to prevent contamination of the substrates and to ensure a neat sealant line. Masking tape should be removed immediately after tooling.
Priming Primers are not usually required on stone, concrete and masonry substrates. On non-porous substrates such as anodized aluminum, priming might be needed. It is recommended to carry out test on such substrates to assess the need for priming. A suitable primer on non-porous substrates is DOWSIL™ 1200 OS Primer. Allow at least half an hour between priming and sealant application. Please contact Dow’s technical service in case of doubt.
Page 3 of 4 © 2019–2020 The Dow Chemical Company. All rights reserved. Form No. 62-2147-01-0220 S2D
How to Use (Cont.) Back-up Materials Where back-up material is required, open cell backer rod is recommended. Back-up materials provide back pressure and avoid three sided adhesion that limits sealant movement capability.
Finishing The joint should be tooled within 5 minutes of application to ensure good contact between the sealant and the substrate. Tooling of the sealant also gives a smooth, professional finish.
Clean-Up If sealant is misapplied to porous substrates, it should be left until it is just cured and then removed by peeling, cutting or other mechanical means. Care should be taken not to damage plastic or coated surfaces.
Joint Design The sealant joint width should be designed to accommodate the movement capability of the sealant. When designing joints using DOWSIL™ 790 Silicone Building Sealant, the minimum width should be 6 mm. For joints between 6–12 mm wide, a seal depth of 6 mm is required. For joints above 12 mm wide, a width to depth ratio of 2:1 should be used. As the sealant joint width becomes larger than 25 mm, the depth should be held at approximately 9 mm to 12 mm. In situations where fillet joints are needed, a minimum of 6 mm sealant bite to each substrate is recommended. For joint dimensions with a width greater than 25 mm or a depth greater than 15 mm, please contact your regional service centers for technical assistance.
Handling Precautions
PRODUCT SAFETY INFORMATION REQUIRED FOR SAFE USE IS NOT INCLUDED IN
THIS DOCUMENT. BEFORE HANDLING, READ PRODUCT AND SAFETY DATA SHEETS
AND CONTAINER LABELS FOR SAFE USE, PHYSICAL AND HEALTH HAZARD
INFORMATION. THE SAFETY DATA SHEET IS AVAILABLE ON THE DOW WEBSITE AT
DOW.COM, OR FROM YOUR DOW SALES APPLICATION ENGINEER, OR
DISTRIBUTOR, OR BY CALLING DOW CUSTOMER SERVICE.
Usable Life and Storage
When stored at or below 32°C, DOWSIL™ 790 Silicone Building Sealant has a shelf life of 12 months from date of manufacture. Refer to product packaging for “Use By” date.
Limitations DOWSIL™ 790 Silicone Building Sealant should not be applied:
• In structural applications.
• Below grade or to materials that outgas, which can cause bubbling in curing sealant.
• On brass or copper or other similar material that can be corroded.
• To surfaces that are continuously immersed in water.
• For use as an interior penetration firestop sealing system.
• To building materials that bleed oils, plasticizers, or solvents – materials such as impregnated wood, oil based caulks, green or partially vulcanized rubber gaskets, or tapes or bituminous below-grade waterproofing and asphalt-impregnated fiberboard.
• In totally confined spaces because the sealant requires atmospheric moisture for cure.
• To surfaces that will be painted after application. The paint film will not stretch with the extension of the sealant and may crack and peel and most likely will not adhere to the sealant.
• To surfaces in direct or indirect contact with food.
Page 4 of 4 ®Trademark of The Dow Chemical Company Form No. 62-2147-01-0220 S2D
Limitations (Cont.) • To wet or frost-laden surfaces.
• In applications where solvents or primers are not fully dried prior to sealant application.
Uncured sealant is very sensitive to many solvents, primers, and cleaning agents; these may cause the sealant to remain uncured or tacky.
This product is neither tested nor represented as suitable for medical or pharmaceutical uses.
Health and Environmental Information
To support customers in their product safety needs, Dow has an extensive Product Stewardship organization and a team of product safety and regulatory compliance specialists available in each area.
For further information, please see our website, dow.com or consult your local Dow representative.
Disposal Considerations
Dispose in accordance with all local, state (provincial) and federal regulations. Empty containers may contain hazardous residues. This material and its container must be disposed in a safe and legal manner.
It is the user’s responsibility to verify that treatment and disposal procedures comply with local, state (provincial) and federal regulations. Contact your Dow Technical Representative for more information.
Product Stewardship
Dow has a fundamental concern for all who make, distribute, and use its products, and for the environment in which we live. This concern is the basis for our product stewardship philosophy by which we assess the safety, health, and environmental information on our products and then take appropriate steps to protect employee and public health and our environment. The success of our product stewardship program rests with each and every individual involved with Dow products - from the initial concept and research, to manufacture, use, sale, disposal, and recycle of each product.
Customer Notice
Dow strongly encourages its customers to review both their manufacturing processes and their applications of Dow products from the standpoint of human health and environmental quality to ensure that Dow products are not used in ways for which they are not intended or tested. Dow personnel are available to answer your questions and to provide reasonable technical support. Dow product literature, including safety data sheets, should be consulted prior to use of Dow products. Current safety data sheets are available from Dow.
dow.com NOTICE: No freedom from infringement of any patent owned by Dow or others is to be inferred. Because use conditions and applicable laws may differ from one location to another and may change with time, Customer is responsible for determining whether products and the information in this document are appropriate for Customer's use and for ensuring that Customer's workplace and disposal practices are in compliance with applicable laws and other government enactments. The product shown in this literature may not be available for sale and/or available in all geographies where Dow is represented. The claims made may not have been approved for use in all countries. Dow assumes no obligation or liability for the information in this document.
References to "Dow" or the "Company" mean the Dow legal entity selling the products to Customer unless otherwise expressly noted. NO WARRANTIES ARE GIVEN; ALL IMPLIED WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A
PARTICULAR PURPOSE ARE EXPRESSLY EXCLUDED.
DOWSIL™ 795 Silicone Building Sealant
Page 1 of 4 © 2017–2025 The Dow Chemical Company. All rights reserved. Form No. 61-885-01-0325 S2D
Description
Neutral, one part silicone sealant
Sustainability Attribute:
Uses / Applications
Structural and nonstructural glazing Structural attachment of many panel systems Panel stiffener applications Weather sealing of most common construction materials including glass, aluminum, steel, painted metal, EIFS, granite and other stone, concrete, brick and plastics
Composition
One–part, neutral cure, RTV silicone sealant
Suitable for most new construction and remedial sealing applications Versatile – high performance structural glazing and weather sealing from a single product Available in 15 standard colors; custom colors also available Excellent weatherability virtually unaffected by sunlight, rain, snow, ozone and temperature extremes of -40°F (-40°C) to 300°F (149°C) Excellent unprimed adhesion to a wide variety of construction materials and building components, including anodized, alodined, most coated and many Kynar painted aluminums
Ease of application – ready to use as supplied Ease of use – all temperature gunnability, easy tooling and low-odor cure byproduct Meets global standards (Americas, Asia and Europe)
Test1 Property Unit Result
As Supplied
ASTM C 679 Tack Free Time, 50% RH hours 3
Curing Time at 25°C (77°F) and 50% RH days 7–14
Full Adhesion days 14–21
ASTM C 639 Flow, Sag or Slump inches (mm) 0.1 (2.54)
Working Time minutes 20–30
1. ASTM: American Society for Testing and Materials.
Page 2 of 4 © 2017–2025 The Dow Chemical Company. All rights reserved. Form No. 61-885-01-0325 S2D
VOC Content2 g/L 30
As Cured After 21 Days at 25°C (77°F) and 50% RH
ASTM D 2240 Durometer Hardness, Shore A points 35
ASTM C 794 Peel Strength lb/in (kg/cm) 32 (5.7)
ASTM C 1135 Tension Adhesion Strength At 25% Extension At 50% Extension psi (MPa)
45 (0.310) 60 (0.414)
ASTM C 719 Joint Movement Capability percent ±50
ASTM C 1248 Staining (Granite, Marble, Limestone, Brick and Concrete) None
As Cured After 21 Days at 25°C (77°F) and 50% RH Followed by 10,000 Hours in a QUV Weatherometer, ASTM G 53
ASTM C 1135 Tension Adhesion Strength At 25% Extension At 50% Extension
35 (0.241) 50 (0.345)
2. Based on South Coast Air Quality Management District of California. Maximum VOC is listed both inclusive and exclusive of water and exempt compounds.
Description DOWSIL™ 795 Silicone Building Sealant is a one-part, neutral-cure, architectural-grade sealant that easily extrudes in any weather and cures quickly at room temperature. This cold-applied, non-sagging silicone material cures to a medium modulus silicone rubber upon exposure to atmospheric moisture. The cured sealant is durable and flexible enough to accommodate ± 50 percent movement of original joint dimension when installed in a properly designed weather seal joint. In a properly designed structurally glazed joint, the sealant is strong enough to support glass and other panel materials under high wind load.
Approvals/ Specifications
DOWSIL™ 795 Silicone Building Sealant meets the requirements of:
Federal Specification TT-S 001 543A (COM-NBS) Class A for silicone building sealants Federal Specification TT-S-00230C (COM-NBS) Class A for one-part building sealants ASTM Specification C 920 Type S, Grade NS, Class 50, Use NT, G, A and O ASTM Specification C 1184 for structural silicone sealants Canadian Specification CAN2-19.13- M82
Page 3 of 4 © 2017–2025 The Dow Chemical Company. All rights reserved. Form No. 61-885-01-0325 S2D
Colors DOWSIL™ 795 Silicone…
This is the start of the file's text. The full file is on GovTribe.