About this file
This is a Design Criteria and Facility Standards Manual document issued by the University of Maryland, College Park (UMCP) establishing electrical controls standards for campus facility projects, effective July 10, 2009. The manual specifies requirements for the design, selection, and installation of automatic transfer switch systems, switchgear gateways, generator monitoring systems, and lighting control systems. Key product and service requirements include heavy-duty oil-tight control switches and stations manufactured to NEMA ICS 2 standards with Class A150 contact ratings; photocell switches with gasketed cast feralloy enclosures; magnetic control relays (Class A300) and time-delay relays (Class A600) rated at 120 volts, 60 Hz single phase; clock timers with 24-hour, 7-day astronomical dials; and control device enclosures fabricated and wired to NEMA ICS 1 specifications. All submittals must include shop drawings with control device enclosure wiring diagrams and panel layouts, product data for each control device, and operating and maintenance instructions. Installation requirements mandate compliance with manufacturer instructions and proper connection to systems controlled to achieve specified operation, with adjustments made to time delay relays and clock timers as necessary.
The manual establishes integration requirements for generator and automatic transfer switch monitoring systems, electrical switchgear gateways, and building automation system connectivity. Generator monitoring system gateways must transmit battery voltage, oil pressure, oil temperature, coolant temperature, fuel level/rate, engine start/stop status, total kilowatt-hours, and frequency data to the building automation system. Automatic transfer switch monitoring gateways must provide utility source availability, generator source availability, voltage and current readings for both utility and generator phases, and frequency information. Electrical switchgear gateway integration for trip units requires transmission of apparent energy, active energy totals, breaker status, and protective device settings including long time pick up, short time pick up, instantaneous, and ground fault parameters. All control device enclosures for interior applications must use NEMA Type 1 enclosures, while exterior applications require NEMA Type 4 enclosures with terminal blocks compliant to ANSI/NEMA ICS 4 standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 3 Page.pdf | ||
| 26 09 00.pdf | ||
| 26 40 00.pdf | ||
| Attachment 4.pdf | ||
| 26 32 00.pdf | ||
| 33 71 00.pdf | ||
| Additional Drawings.zip | ZIP file | |
| 26 56 00.pdf | ||
| AMENDMENT 002- RFP 00042061.pdf | ||
| Attachment 7.pdf | ||
| Questions RFP No. 00042061.pdf | ||
| AMENDMENT 001 - RFP 00042061.pdf | ||
| 26 05 01.pdf | ||
| AMENDMENT 004- RFP 00042061.pdf | ||
| AMENDMENT 003- RFP 00042061.pdf | ||
| Attachment 5.pdf | ||
| Attachment 6.pdf | ||
| 26 05 00.pdf | ||
| 26 29 23.pdf | ||
| RFP No. 00042061 Rooftop solar PV v2.pdf | ||
| Attachment 7- Proposer Submission Checklist (3).xlsx | XLSX spreadsheet | |
| 33_00_00.pdf | ||
| Attachment2.pdf | ||
| 26 01 00.pdf | ||
| 26 51 00.pdf | ||
| Attachment 1.pdf | ||
| 26 56 00.pdf | ||
| 33 71 00.pdf | ||
| 33_00_00.pdf | ||
| 26 05 00.pdf | ||
| 26 01 00.pdf | ||
| 26 51 00.pdf | ||
| 26 05 01.pdf | ||
| 26 29 23.pdf | ||
| 26 40 00.pdf | ||
| 26 32 00.pdf |
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Electrical Controls 26.09.00
Design Criteria/Facility Standards Manual Page 1 University of Maryland, College Park
Description:
The purpose of the section is to highlight the current applicable UMCP Design Standards for the design, selection and installation of Automatic Transfer Switch systems, switchgear gateways, generator monitoring systems and lighting control systems.
Related Sections:
● TBD
Effective Date:
● July 10, 2009
Applicable Standards:
● NEMA ICS 2
● ANSI/NEMA ICS 4
● NEMA ICS 6
General Requirements:
1. Required Submittals:
● Shop Drawings: Indicate control device enclosure wiring diagrams and panel layout drawings
● Product Data: Provide data on each control device specified
● Operating and Maintenance Instructions: Include instructions on adjusting, repairing, cleaning, and lubricating each control device specified
2. Lighting Control Product Requirements:
● Control Switches and Stations
● Description: Heavy duty, oil-tight control switches and stations manufactured to NEMA ICS 2
● Contact Ratings: Class A150
● Photocells Switch
● Description: Photocell switch manufactured to NEMA ICS 2
● Ratings: Contact Ratings: Class A150
● Enclosure: Gasketed, cast feralloy box with conduit hub
● Relays
● Description: Relays manufactured to NEMA ICS 2
● Magnetic Control Relay: Class A300
● Time-Delay Relay: Class A600
● Ratings:
● Contact Ratings: Minimum Class A150
● Coil Voltage: 120 volts, 60 Hz., Single Phase
● Enclosure: NEMA Type 1 for interior and NEMA type 4 for exterior use
● Time Switch
● Description: Clock timer manufactured to NEMA ICS 2, with astronomical dial
● Ratings:
● Contact Ratings: Class A150; SPST
● Coil Voltage: 120 volts, 60 Hz., Single Phase
● Dial Time: 24 hours, 7 days
● Enclosure: NEMA Type 1 for indoor applications, and NEMA Type 4 for outdoor applications
Electrical Controls 26.09.00
Design Criteria/Facility Standards Manual Page 2 University of Maryland, College Park
● Control Device Enclosures
● Description: Shop, fabricate and wire control device enclosures to NEMA ICS 1, for groupings of more than one device
● Use hinged cover enclosures under provisions of 26.05.00
● Terminal Blocks: ANSI/NEMA ICS 4
● Fabrication: Shop assemble to NEMA ICS 6 - Use plastic wiring through to route internal wiring
● Installation Requirements
● Install control devices in accordance with manufacturer’s instructions
● Install individual components in enclosures
● Connect control devices to systems controlled, to achieve proper system operation
● Adjustments
● Adjust time delay relays and clock timers to achieve specified system operation.
3. Generator and Automatic Transfer Switch Building Automation Integration:
● Connection shall be made to the generators monitoring system gateway to establish communication to the building automation system; If available by manufacturer, the following points shall be brought out to the building automation system:
● Battery Voltage
● Oil Pressure
● Oil Temperature
● Coolant Temperature
● Fuel Level/Rate
● Engine Start
● Engine Stop
● Total kWH
● Frequency
● Connection shall be made the Automatic Transfer Switch monitoring system gateway to establish communication to the building automation system. The Following points shall be brough out:
● Utility Source Availability
● Generator Source Availability
● Utility Average Voltage (Phase to Phase)
● Utility Average Current
● Utility Frequency
● Generator Average Voltage (Phase to Phase)
● Generator Average Current
● Generator Frequency
● Electrical Switchgear Gateway Integration for Trip Units Connection shall be made to the buildings main switchgear monitoring system gateway to establish communication to the building automation system. The following points shall be brought out for each breaker:
● Apparent Energy
● Active Energy
● Active Energy Total
● Breaker Status (Open/Closed)
● Long Time Pick Up (Ir)
● Short Time Pick Up (Isd)
● Instantaneous (Ii)
● Ground Fault (lg)
| Description: |
| Related Sections: |
| Effective Date: |