26_009_LH 2025 Paving the Way Project 1_IFB.pdf
PDF 407 KB Posted
- Attached to
- 26-009-LH Paving the Way Project 1 (10/2/25)
- Solicitation number
- PE-61100-NONST-2026-000000086
- Issued by
- Bibb County, Georgia
About this file
This Invitation for Bids (IFB) document is issued by Macon-Bibb County, Georgia for the Paving the Way Project 1, a roadway repair and resurfacing initiative for the county's Engineering Department. The project encompasses approximately 9.53 miles of roadway across seven streets including Fulton Mill Road, Dixon Road, and Rogers Road. Work includes milling (10,146.7 tons), bituminous tack application (7,379.39 gallons), roadway patching (12,298.98 square yards), asphalt placement (10,146.7 tons of 12.5mm and 9.5mm Superpave), manhole and water valve installations and adjustments, striping and pavement markings, and shoulder maintenance. Sealed bids are due by 12:00 noon on Thursday, October 2, 2025, with a mandatory pre-bid conference scheduled for 10:00 a.m. on Wednesday, September 10, 2025, in the Macon County Board of Commissioners Chamber. The deadline for submission of bid questions is Friday, September 12, 2025, at 3:00 p.m. The contractor must commence work within 10 calendar days of the notice to proceed and complete all work within 150 calendar days from receipt of necessary railroad permits. A one-year warranty on all labor and workmanship is required from the completion date.
Award of the contract will be based on the lowest total bid price in accordance with Georgia Official Code Section 36-10-2.2. Bidders must submit a bid bond equal to 5% of the total base bid, and the successful contractor must provide Performance and Payment Bonds each equal to 100% of the contract price from surety companies rated B+ or better by A.M. Best and licensed to do business in Georgia. Required insurance coverage includes Workers' Compensation (statutory), General Liability ($1,000,000 combined single limit with $5,000 maximum deductible), and Automobile Liability ($1,000,000 combined single limit with $5,000 maximum deductible). The contract includes a 10% retainage on each payment until final payment, with liquidated damages assessed at $75 per day for project delays beyond the contract completion date. Minority, Women-Owned, and Disadvantaged Business Enterprises are encouraged to participate, and contractors must submit quarterly Subcontractor/Supplier Participation Reports. Macon-Bibb County reserves the right to reject any or all bids and to award to other than the lowest bidder if deemed in the county's best interest.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Macon-Bibb County, Georgia
INVITATION FOR BIDS
FOR
PAVING THE WAY PROJECT-1
745-02 745-21 745-65 755-35 755-30
BID NUMBER: 26-009-LH
ISSUED: 9/2/25
BIDS DUE NO LATER THAN 12:00 NOON ON THURSDAY, OCTOBER 2, 2025
Macon-Bibb County Procurement Department 700 Poplar Street
Suite 308 Government Center
Macon, Georgia 31201
TABLE OF CONTENTS
I. GENERAL
A. INVITATION
B. BID DOCUMENTS
C. PRE-BID
D. BID BOND
E. SEALED BIDS
F. VALIDITY
G. CONTRACT AWARD
H. SURETY
I. PAYMENT CONDITIONS
J. EXCISE TAXES
K. INSURANCE
II. INSTRUCTIONS TO BIDDERS
A. DEFINITIONS
B. RELATED DOCUMENTS
C. BIDDER’S REPRESENTATION
D. DOCUMENT DISCREPANCIES
E. SUBMITTALS
F. RESERVATIONS
G. SURETY AND INSURANCE COMPANIES
III. SPECIAL CONDITIONS
A. GENERAL
B. PERMITS AND LICENSES
C. LAYOUT OF WORK
D. WORK AREA
E. UNDERGROUND UTILITIES
F. TRAFFIC CONTROL
G. EROSION CONTROL
H. VANDALISM
I. MATERIAL DISPOSAL
J. EXTENSION OF TIME
K. LIQUIDATED DAMAGES
L. INSPECTION
IV. EXECUTION
A. GENERAL
B. SPECIFICATIONS
C. SCHEDULE
V. WARRANTY
VI. OPEN RECORDS….…………………………………………………………………………...……………….. 8
FORMS PROVIDED:
BID FORM
BIDDER QUALIFICATION FORM
FINANCIAL & LEGAL STABILITY STATEMENT
LIST OF SUB-CONTRACTORS
BIDDER MINORITY PARTICIPATION GOAL
GEORGIA SECURITY AND IMMIGRATION COMPLIANCE ACT (E-VERIFY) AFFIDAVIT
ATTACHMENTS:
A – REQUIRED SUBMITTAL DOCUMENTS W/ BID SCHEDULE & BID PRICE FORM
B – QUANTITY WORKSHEET
C - FREQUENTLY
END OF TABLE OF CONTENTS
PAVING THE WAY PROJECT 1
I. GENERAL
A. Invitation
1. Notice is hereby given that the Macon-Bibb County Board of Commissioners will receive sealed bids (1 original and Flash Drive) in the Procurement Department, Suite
308, Macon-Bibb City Hall, 700 Poplar Street, Macon, Georgia 31201, until
12:00 o’clock NOON at the time legally prevailing in Macon, Georgia on Thursday, October 2, 2025, for Paving The Way Project 1 for the Macon-Bibb County
Engineering Department, Macon, Bibb County, Georgia.
2. NO BIDS WILL BE ACCEPTED AFTER THIS DESIGNATED TIME.
3. Bids will be publicly opened in the Macon-Bibb County Board of Commissioner
Chamber on Thursday October 2, 2024, at 2:00 pm.
4. Minority, Women Owned, and other Disadvantaged Business Enterprises are encouraged to participate in the solicitation process. Additionally, respondents are encouraged to use M/W/DBE subcontractors where possible. Small and other disadvantaged businesses requiring assistance with the competitive process can contact
Charise Stephens, Director of Small Business Affairs at (478) 300-2297 or
Cstephens2@maconbibb.us .
B. Bid Documents
1. Bid documents may be examined and obtained at the Macon-Bibb County Procurement
Department, Suite 308, City Hall, 700 Poplar Street, Macon, Georgia 31201, by calling
(478) 803-0550, or may be viewed and downloaded from one of the links included below:
Georgia Procurement Registry website http://ssl.doas.state.ga.us/PRSapp/PR_custom_index.jsp?agency=61100
Macon-Bibb County Procurement Page www.maconbibb.us/purchasing
C. Pre-Bid
A Pre-bid conference is scheduled for 10:00 o’clock a.m., Wednesday, September 10, 2025, in the Macon County Board of Commissioners Chamber located at 700 Poplar Street, Macon, GA 31201. This Pre-bid is not mandatory.
Deadline for submission of questions is Friday, September 12, 2025, at 3:00 p.m.
standard eastern time. Questions must be submitted via email to
Lhardwick@maconbibb.us
D. Bid Bond
1. Bids, in order to be considered, shall be accompanied by a bid bond, payable to the
Owner, in amount not less than five percent (5%) of the total base bid.
a) This bid security shall become payable to the Owner only if the bidder, to whom award is made, should fail to execute a contract with the Owner and furnish bond and insurance in accordance with terms of the contract within ten
(10) days after notification of award.
E. Sealed Bids
1. Envelopes shall be identified on the outside as
“Bid 26-009-LH – “Paving the Way Project 1”
And delivered by hand or mailed to:
Macon-Bibb County Procurement Department
700 Poplar Street, Suite 308
Macon, Georgia 31201 mailto:Cstephens2@maconbibb.us http://ssl.doas.state.ga.us/PRSapp/PR_custom_index.jsp?agency=61100 http://www.maconbibb.us/purchasing
F. Validity
1. No bid may be withdrawn for a period of sixty (60) days after time has been called on date of bid opening.
G. Contract Award
1. The contract, if awarded, will be based on Total Bid Price.
2. Guidelines in the award of this contract will be Section 36-10-2.2, Official Code of
Georgia Annotated.
3. Upon award of the Contract, a pre-construction meeting will be held to discuss the project and to establish a schedule of work.
H. Surety
1. Whereas the anticipated contracted price exceeds $5,000, the bidder to whom award is made shall submit a Payment Bond and a Performance Bond, both in amount of one hundred percent (100%) of the contract price.
a) Bonding company/Surety shall be:
(1) Rated B+ or better in current Key Rating Guide as issued by A.M.
Best Company, Oldwick, NJ.
(2) Licensed to do business in the State of Georgia.
I. Payment Conditions
1. The County Inspector will collect material tickets, measure and inspect work completed to date on said job and report to the Project Manager for payment.
2. A 10% retainage will be withheld from each payment until final payment is made.
The Owner will only pay for items used and actual work performed.
3. Change orders are issued for any variance from contract or plan sheets.
4. Any unauthorized work or material change will not be paid for unless a change order has been issued.
J. Excise Taxes
1. Any material that is to be incorporated into the work of this project may be consigned to
Macon-Bibb County in care of the contractor. If the shipping papers show clearly that any such materials are consigned, the shipment shall be exempt from the tax on transportation of property under the provisions of Section 3478(b) of the Internal
Revenue Code, as amended by Public Law 180-78th Congress.
2. The Contractor shall pay all transportation charges.
3. Each bidder shall take this exemption into account in calculating his bid.
K. Insurance
1. Insurance coverage shall be carried with an insurance company licensed to do business in the State of Georgia.
2. Insurance shall be obtained prior to commencement of work and shall remain in force throughout the period of the contract.
3. Macon-Bibb County shall be named as additional insured on the policy.
4. Coverage shall include water damage.
5. Contractor is responsible for any and all deductibles.
6. Required coverage:
a) Worker’s Compensation: Statutory
b) General Liability:
(1) $1,000,000.00 combined single limit for B.I., P.D.
(2) Maximum deductible: $5,000.00
(3) To include:
(a) Premises – Operations
(b) Products & Completed Operations
(c) Broad form Contractual
(d) Independent Contractor and Subcontractor
(e) Underground explosion and collapse
c) Automobile Liability:
(1) $1,000,000.00 combined single limit for B.I. and P.D.
(2) Maximum deductible: $5,000.00
(3) To include:
(a) Owned Automobiles
(b) Hired Automobiles
(c) Non-Owned Automobiles
II. INSTRUCTIONS TO BIDDERS
A. Definitions
1. Wherever the term “Owner”, “County”, or “Macon-Bibb County” occur in these specifications, it shall mean Macon-Bibb County, a political subdivision of the State of
Georgia acting through the Macon-Bibb County Board of Commissioners.
2. Wherever the term “Engineer” occurs in these specifications, it shall mean the engineer of the Owner, the County Engineer, or his representative.
3. Wherever the term “work” occurs in these specifications, it shall mean the work as defined herein, including, all labor, materials, equipment, transportation, and supervision necessary to complete the contract.
4. Wherever the term “D.O.T.” occurs in these specifications, it shall mean the Georgia
Department of Transportation.
B. Related Documents
1. Quantity Worksheet (Attachment “B”)
2. Bid Form
3. Bidder’s Qualification Form
4. Financial & Legal Stability Statement
5. Bidder MBE Plan Form
6. List of Sub-contractors
7. Bond Forms
8. E-Verify Affidavit
9. Title VI non-discrimination Notice
C. Document Discrepancies
1. Should the bidder find discrepancies in, or omissions from the documents, he shall at once notify the Macon-Bibb County Procurement Department.
2. Requests for Interpretations of Drawings and Specifications shall be submitted via email to Lhardwick@maconbibb.us no later than September 12, 2025, by 3:00 pm.
3. Any subsequent instructions to bidders will be issued in the form of addenda to the specifications and sent to the bidder. All addenda shall be enumerated in the Bid Form.
mailto:Lhardwick@maconbibb.us
D. Bidder’s Representation
1. Each bidder, by making his bid, represents that he has:
a) Read and understand the bidding documents; and,
b) Visited the site and became familiar with the local conditions under which the work is to be performed.
(1) Bidders shall examine the areas wherein work of this project is to be carried out and shall take into consideration all conditions that might affect his work.
(a) Failure of the bidder to inspect firsthand the areas affected by work in this project shall not relieve him of the obligation to comply fully with the scope of the work as defined herein.
(b) No consideration will be given any claim based on lack of knowledge of existing conditions, except where the Contract
Documents make definite provisions for adjustment of cost or extension of time due to existing conditions that cannot be readily ascertained.
2. All definitions set forth in the specifications are applicable to this Instruction to Bidders, the Bid Form and the proposed Contract Documents including, but not limited to, drawings, project manual, and any addenda issued prior to receipt of bids.
a) Addenda are written or graphic instruments issued prior to the execution of the
Contract that may modify or interpret the bidding documents by deletion, additions, clarifications or corrections.
b) Addenda will become part of the Contract Documents when the Construction
Contract is executed.
E. Submittals
1. In order for bids to be considered, the complete bid document package should be submitted including each of the following completed documents.
a) Bid Form
b) Bidder’s Qualification Form
c) Financial & Legal Stability Statement
d) List of Sub-Contractors
e) Minority Participation Goal
f) Bid Bond in amount of 5% of the total base bid
g) E-Verify Affidavit
h) Disbarment Form
F. Reservations
1. The bidder acknowledges that Macon-Bibb County reserves full freedom (in addition to the right to reject any and all bids) in awarding bids to consider all available factors including, but not limited to, price, the provision of needed and unneeded features, usefulness to the using department and prior County experience. In addition, the bidder recognizes the right of the Owner to reject a bid if the bidder failed to furnish any required submittals on the date required by the bidding documents, or if the bid is in any way incomplete or irregular. Hence the County may award bids to other than the lowest bidder if in the judgment of the Board of Commissioners the interest of the County will be best served by award to another.
G. Surety and Insurance Companies
1. The Contract provides that the surety and insurance companies must be acceptable to the
Owner. The bidder shall require the attorney in fact who executes the required bonds on behalf of the surety to affix thereto a certified and current copy of his power of attorney indicating the monetary limit of such power.
III. SPECIAL CONDITIONS
A. General
1. All work to be performed as part of this specification shall comply with all codes, ordinances and regulations applicable to the contract, including, but not limited to:
a) International Building Code
b) State and Local Building Code
c) Georgia Department of Transportation (D.O.T.)
d) Occupational Safety and Health Administration (OSHA)
e) Other Federal, State, or Local Codes
B. Permits and Licenses
1. Contractor shall obtain all permits and licenses, paying all fees as required, for execution of the Contract. In addition, the Contractor shall arrange for necessary inspections required by the City, County, State and other authorities having jurisdiction, and submit certificates of approval to the Owner or his designated representative.
C. Layout of Work
1. The Contractor shall verify all existing conditions and contiguous work and lay out his work there from, providing for himself all other necessary measurements, lines and levels, and shall assume the responsibility for the correctness of the layout of the work.
D. Work Area
1. The Contractor shall confine his operations to as small an area as possible, using only the areas designated for on-site storage.
2. The Contractor shall protect all surrounding adjoining private and public property, taking every precaution to prevent damage or injury to trees, shrubs, curbs, sidewalks, driveways and fences along or adjacent to the work. Should damage occur, the
Contractor shall restore, at his expense, any such property damage or injuries by his operations to a condition equal to that existing before such damage or injury was done, by repairing, rebuilding or otherwise restoring as may be directed by, and to the satisfaction of the Owner.
3. In case of failure on the part of the Contractor to restore such property, or make good such damages or injury, the Owner may, after forty-eight (48) hours written notice, proceed to repair, rebuild, or otherwise restore such property as may be deemed necessary, and the cost thereof shall be deducted from any monies due or which may become due the contractor under this contract.
E. Underground Utilities
1. The Contractor shall verify all underground utilities and their locations prior to commencing any work under this contract. Damage to underground utilities, and costs to repair same, shall be the responsibility of the Contractor.
F. Traffic Control
1. It shall be the responsibility of the Contractor to maintain traffic by utilizing adequate construction signs and flagmen at all times.
2. The Contractor shall furnish, install, maintain and eventually remove all traffic control devises necessary to properly protect and divert traffic. Such barricades and detour signs shall be illuminated at night.
3. All costs associated with traffic control shall be the responsibility of the Contractor.
4. The Contractor shall assume all responsibility for damages resulting from the failure of the signs and/or barricades to properly protect the work from traffic.
G. Erosion Control
1. The Contractor shall control all erosion by incorporating temporary grassing, mulch, baled straw, or silt fencing wherever required.
H. Vandalism
1. The Contractor shall take every precaution not to leave equipment and materials where they can be reached and used for defacing new or existing work at any time.
I. Material Disposal
1. The Contractor shall allow no trash, dirt, stumps, tree trunks, or excess material to accumulate and shall be responsible for removing same from the premises.
a) Such items shall be disposed of off the premises.
b) Burning of material on the site will not be permitted.
c) All costs of removing trash shall be the responsibility of the Contractor.
d) Place and method of disposal shall be the responsibility of the Contractor.
J. Extension of Time
1. In the event the work under this project is delayed by neglect, delay, or default of any other Contractor or the Owner, or by any damage which is the result of an Act of God, or by a general strike of the employees, the Contractor shall have reason to claim for delay and request an extension of time to complete the contract.
K. Liquidated Damages
1. Liquidated damages in the amount of $75 shall be charged to the contractor for each day that the project is delayed beyond the completion date of the contract. These charges are to defray the cost of inspection by Macon-Bibb employees assigned to the project.
L. Inspection
1. The Engineer may appoint inspectors to inspect all materials used and all work performed. Such inspection may extend to all or any part of the work and to the preparation of manufacture of the materials to be used. The inspectors will not be authorized to revoke, alter, enlarge or relax the provisions of this specification, nor will they be authorized to approve or accept any portion of the completed work or to issue instruction contrary to the plans and specifications. The inspector shall have authority to reject defective material and to suspend work that is being improperly done, subject to the final decision of the Engineer.
2. It is mutually agreed between the parties to the contract that to prevent all disputes and misunderstandings between them in relation to any of the provisions contained in these specifications, or their performance by either of said parties, the Engineer shall serve as the referee to decide all matters of construction of the specifications and of the terms of the contract, and as to all matters arising or growing out of said contract and his decision shall be final and binding upon both parties.
3. The Engineer and his inspectors shall have free access to all parts of the work, and to all material intended for use in the work. The work will be inspected as it progresses, but failure to reject or condemn defective work at the time it is done will in no way prevent its rejection whenever it is discovered before the work is finally accepted and approved, nor will final acceptance and approval constitute waiver by the County of any right of action for defective work or the failure to perform the contract according to its terms.
IV. EXECUTION
A. General
1. It is the intent of this specification to provide for the Paving the Way Project 1, for the
Macon-Bibb County Engineering Department, Macon, Georgia.
B. Specifications
1. The Contractor shall provide all services as outlined in this solicitation, See
Attachment “B” for Quantity Worksheet, attached hereto and incorporated herein
C. Schedule
1. The contractor shall commence work including applying for all needed railroad permits within 10 calendar days following issuance of notice to proceed, shall execute the work diligently, and shall complete all work requirements within 150 calendar days following the receipt of all necessary railroad permits. This time shall include all clean up, demobilization, and other necessary work to return the project area to its final state.
V. WARRANTY
A. The Contractor shall guarantee all labor and workmanship for minimum of one (1) year(s) from date of completion.
VI. SUBCONTRACTOR REPORTING REQUIREMENTS
A. Contractor shall submit a “Subcontractor/Supplier Participation Report” on this contract quarterly to the Macon-Bibb County Office of Small Business Affairs which shall include the following:
1. The name of each subcontractor or supplier participating in the contract.
2. A description of the work to be performed, materials, supplies, and services provided by each subcontractor or supplier.
3. Whether each subcontractor or supplier is a minority owned, woman owned, LGBTQIA+ owned, veteran owned, disabled person owned, Certified Disadvantaged Business Entity, non-profit, or local business.
4. Whether each subcontractor is a supplier, subcontractor, or other.
5. The dollar value of each subcontract or supply agreement.
6. The actual payment to date of each subcontractor or supplier participating in the contract.
B. The report shall be updated during the applicable quarter by the Contractor whenever any of the approved subcontractors or suppliers have completed the portion of the work they were contracted to perform. Copies of this report should be transmitted promptly to the Macon-
Bibb County Office of Small Business Affairs.
C. The County may withhold any payment due to the Contractor on any project for failure to submit the Subcontractor/Supplier Report within thirty (30) days following the end of the calendar quarter or for the failure to submit updates to the quarterly report within thirty (30) days of any subcontractor or supplier having completed the portion of work they were contracted to perform.
BID FORM
Macon-Bibb County Board of Commissioners
Laura Hardwick, Procurement Director
Macon-Bibb County, Procurement Dept.
700 Poplar Street, Suite 308
Macon, Georgia 31201
DATE: ___________________________________
Re: Paving The Way Project 1
Macon-Bibb County Engineering Department
Bibb County, Georgia
1. We have examined the Specifications, related documents and the site of the proposed Work, and are familiar with all the conditions surrounding this project, including the availability of materials and labor, and hereby bid to furnish all materials and labor, and to complete the project in accordance with the
Contract Documents, within the time set forth herein, and at the prices stated below. These prices are to cover all expenses incurred in performing the Work required under these Specifications, of which this bid is part.
2. ADDENDUM RECEIPT:
a. We acknowledge our responsibility to ensure that all addenda have been received prior to the submission of a bid.
b. Bidder acknowledges receipt of the following addenda:
Addendum No. Dated _________________________
Addendum No. Dated__________________________
Addendum No. Dated__________________________
3. We agree to commence actual physical work on site, with adequate force and equipment within the timeframe presented in the specifications and to complete fully all work within the stated timeframe following notice to proceed.
4. We agree that this bid may not be revoked or withdrawn after the time set for the opening of bids and shall remain open for acceptance for a period of sixty (60) days following such time.
5. In case of written notification by mail, telegraph, or delivery of the acceptance of this bid within sixty (60) days after the time set for the opening of bids, the undersigned agrees to execute within ten (10) days a
Contract for the Work for the below stated compensation and at the same time to furnish and deliver to the
Owner a Performance Bond and a Payment Bond, both in an amount equal to one-hundred-percent (100%) of the Contract Sum.
5. Enclosed herewith is a Bid Bond in the amount of five percent (5%) of the total base bid. We agree that the above stated amount is the proper measure of liquidated damages that the Owner will sustain by the failure of the undersigned to execute the Contract and to furnish the Performance Bond and the Payment
Bond.
6. If this bid is accepted within sixty (60) days after the date set for the opening of bids and we fail to execute the Contract within ten (10) days after written notice of such acceptance or if we fail to furnish both a
Performance Bond and a Payment Bond, the obligation of the bond will remain in full force and affect and the money payable thereon shall be paid into the funds of the Owner as liquidated damages for such failure; otherwise, the obligation of the bond will be null and void.
7. We hereby certify that we have not, nor have any member of the firm(s) or corporation(s), either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with this submitted bid.
8. We understand the total bid price listed below to be inclusive of all materials, labor, equipment, and other provisions necessary to provide the services in accordance with the associated specification.
Paving the Way Package 1 for Macon-Bibb County (Roadway Repair and Resurfacing)
Bid Schedule – Paving the Way Package 1
The quantities listed are an approximate estimate of the materials required to complete the roadway repair and resurfacing projects, for the Main Streets list. The “Total Bid
Price” is the bid amount which shall be used to award Paving the Way Package 1 paving contract to the successful bidder.
Prior to beginning contract paving work on the main streets, the successful bidder shall be required to contact Mike Beard with the Macon Water Authority, at (478) 256-9382, regarding coordination with MWA on locating /marking paved over sanitary manholes.
Contact Willie Sidney with the Macon Water Authority, at (478) 256-9400, to locate / mark paved over water valves.
Also, the successful bidder shall contact Monte Tolleson with the Macon Water
Authority Storm Water Office, at (478) 738-6520, regarding locating / marking paved over storm manholes.
The 120-day contract period shall proceed upon the successful bidder receiving the
“Notice to Proceed” from our Procurement Office.
Road Name From To Miles Fulton Mill Rd Jane Ann Dr US 80 0.38 Fulton Mill Rd US 80 Hunnicutt Rd 1.71 Fulton Mill Rd Western Cir Bethel Church Rd 1.05 Fulton Mill Rd Michael Dr Skyhawk Cir 0.22 Dixon Rd Bethel Church Rd Rogers Rd 1.42 Dixon Rd Fulton Mill Pine Bloom Pl 1.23 Rogers Rd Dixon Rd Fulton Mill 3.53
Total 9.53
Paving the Way Package 1
Item Unit Quantity Unit Price Total
Milling TONS 10146.7
Bituminous Tack GAL 7379.39
Roadway Patching SY 12298.98
12.5 mm Superpave Asphalt TONS 10146.7
9.5 mm Superpave Asphalt TONS 0
Install Furnished Sewer Manhole, Storm Manholes, EA 11
Install Furnished Water Valve Riser
Manhole (Adjustment) EA 11
Water Valve (Adjustment) EA 12
Traffic Signal Loop Install EA 0
Striping (Center Lines, Edge Lines, Lane Lines)
LF 201256
Painted Arrows EA 3
Bike Symbols EA 0
Painted Messages EA 0
Painted Crosswalks LF 0
Painted Stop Bars LF 56
Painted RR Symbols EA 0
Painted Hatching LF 340
Rumble Stripe SET 0
RPMs MILE 9.53
Clipping Grassed Shoulders MILE 19.06
Total Bid $ ___________________________________