This is a Schedule of Values document prepared for Pinellas County, Florida's Solid Waste Administration Building HVAC Renovation project (ITB-C #26-0394-ITB-C), detailing the cost breakdown and payment allocation for the complete replacement of the facility's heating, ventilation, and air conditioning systems. The project scope encompasses demolition of existing HVAC equipment, installation of two 15-ton VAV DX split systems with condensing units and air handling units, one 1500 CFM 100% outside air DX split system, VAV terminal boxes for zone control, new DDC control systems, ductwork modifications, refrigerant piping, electrical panel upgrades, and comprehensive testing and commissioning services. The Step One qualification submissions deadline is April 21, 2026 at 3:00 p.m., with sealed bids due May 5, 2026 at 3:00 p.m. A non-mandatory pre-bid conference and site visit are scheduled for April 9, 2026 at 1:30 p.m. All work must be completed within 365 consecutive calendar days from the Notice to Proceed. Bidders must hold a Certified General Contractor license with electrical and demolition classifications, EPA Section 608 Technician Certification, and provide performance and payment bonds equal to 100% of the contract amount.
The total project budget is $686,580.00, with major cost allocations including overhead and profit at $103,000 (15.0%), electrical panel and equipment at $100,000 (14.6%), electrical wiring and conduit at $65,000 (9.5%), ductwork supports and insulation at $50,500 (7.4%), DX split systems condensing units and AHUs at $47,600 (6.9%), VAV boxes at $31,200 (4.5%), contingency reserves at $40,000 (5.8%), and bond premium at $10,000 (1.5%). Additional line items cover selective demolition, concrete housekeeping pads, fencing, drywall, ceilings, paint, insulation repairs, refrigerant piping, air devices, HVAC controls, test and balance by AABC or NEBB certified agencies, system commissioning, communications and fire alarm work, permits and fees, and electrical demolition. The County will retain 5% of monthly progress payments until final completion and acceptance, with liquidated damages assessed at $1,200 per calendar day for delays beyond the contract completion date. No incumbent contractor information is identified, and no small business enterprise set-asides or disadvantaged enterprise restrictions apply to bidder eligibility.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A B C D C
ITEM
NO.
DESCRIPTION OF WORK
SCHEDULED
VALUE
% OF
TOTAL
NOTES
1 BOND PREMIUM $10,000.00 1.5%
2 MOBILIZATION $15,000.00 2.2%
3 GENERAL CONDITIONS $20,500.00 3.0%
4 SELECTIVE DEMOLITION $12,500.00 1.8% REMOVE EXISTING HVAC SYSTEMS AND DISPOSAL
5 CONCRETE $4,500.00 0.7% HOUSEKEEPING PADS FOR NEW CUS
6 FENCING $2,500.00 0.4% FENCED ENCLOSURE FOR NEW CUS / MECH YARD
7 DRYWALL $5,000.00 0.7% AS REQUIRED FOR HVAC RENOVATIONS
8 CEILINGS, OTHER $7,500.00 1.1% AS REQUIRED FOR HVAC RENOVATIONS
9 PAINT AND WALL COVERINGS $2,500.00 0.4% AS REQUIRED FOR HVAC RENOVATIONS
10 INSULATION - MINOR REPAIRS $6,000.00 0.9% AS REQUIRED FOR HVAC RENOVATIONS
11 GENERAL HVAC REQUIREMENTS $12,500.00 1.8% BASIC MECHANICAL REQUIREMENTS, SUPPORTS, ANCHORS, ETC.
12 DX SPLIT SYSTEMS - CONDENSING UNITS, AHUS $47,600.00 6.9% QTY. 2 - 15 TON VAV DX SPLIT SYSTEMS
13 VAV BOXES $31,200.00 4.5% QTY. AS SCHEDULED ON PLANS, WITH ELECTRIC HEAT
14 100% OA DX SPLIT SYSTEM $27,840.00 4.1% 1500 CFM DOAS DX SPLIT SYSTEM
15 REFRIGERANT PIPING, SUPPORTS, AND INSULATION $6,300.00 0.9% NEW REFRIGERANT LINES
16 DUCTWORK, SUPPORTS, AND INSULATION $50,500.00 7.4% NEW SHEET METAL DUCTWORK, SUPPORTS AND INSULATION
17 AIR DEVICES, GRILLES, REGISTERS $22,640.00 3.3% NEW AIR DEVICES
18 HVAC CONTROLS $22,500.00 3.3% NEW HVAC CONTROLS
19 HVAC TEST AND BALANCE (T&B) $6,500.00 0.9% AABC OR NEBB CERTIFIED T&B OF ALL HVAC SYSTEMS
20 SYSTEM COMMISIONING (CxA) $3,500.00 0.5% CxA OF NEW HVAC SYSTEMS BY APPROVED COMMISIONING AGENT
21 ELECTRICAL PANEL AND EQUIPMENT $100,000.00 14.6%
22 ELECTRICAL WIRING AND CONDUIT $65,000.00 9.5%
23 ELECTRICAL DEMOLITION - VARIOUS $25,000.00 3.6%
24 ELECTRICAL LIGHTING/CONFERENCE ROOM $10,000.00 1.5%
25 CONDUIT FOR MECHANICAL CONTROLS $5,000.00 0.7%
26 COMMUNICATIONS - FIRE ALARM $20,000.00 2.9%
27 CONTINGENCY, OTHER $40,000.00 5.8%
28 PERMITS, FEES, OTHER $1,500.00 0.2%
29 OVERHEAD AND PROFIT (OH&P) $103,000.00 15.0%
TOTAL GMP = $686,580.00
PINELLAS COUNTY SOLID WASTE ADMINISTRATION BUILDING HVAC RENOVATION - PAY LIST ITEMS / SCHEDULE OF VALUES