This is a Schedule of Values document for the Pinellas County Solid Waste Administration Building HVAC Renovation project in Florida. The project encompasses a complete replacement of the existing building HVAC systems, including demolition of existing units and installation of new systems with all associated electrical, controls, piping, and necessary work for complete system installation. The scope includes two 15-ton VAV DX Split systems, a decoupled 100% outside air DX split system, new VAV terminal units for zone control, a new DDC control system, modifications to existing ductwork, new exhaust fans, and all necessary equipment for complete HVAC renovation. Additional recommended work includes sealing the attic space, repairing or replacing damaged batt insulation, or providing spray-on foam insulation for the roof deck underside.

The total Guaranteed Maximum Price (GMP) for the project is $686,580.00. Major cost components include electrical panel and equipment ($100,000.00 or 14.6% of total), overhead and profit ($103,000.00 or 15.0%), DX split systems condensing units and AHUs ($47,600.00 or 6.9%), ductwork supports and insulation ($50,500.00 or 7.4%), electrical wiring and conduit ($65,000.00 or 9.5%), and VAV boxes ($31,200.00 or 4.5%). Additional line items cover bond premium, mobilization, general conditions, selective demolition, concrete work, fencing, drywall, ceilings, paint, insulation repairs, HVAC controls, testing and balancing, system commissioning, electrical demolition, lighting, communications and fire alarm systems, permits and fees, and contingency reserves totaling $40,000.00 or 5.8% of the total project cost.

View the file

Other files

File Type Posted
MDP.pdf PDF
Panel_PP-1_Outer_Casing.pdf PDF
MDP.pdf PDF
SOLID_WASTE_ADMINISTRATION_BUILDING_HVAC_RENOVATION.pdf PDF
SOLID_WASTE_ADMINISTRATION_BUILDING_HVAC_RENOVATION.pdf PDF
Pricing_Proposal_26-0394_(reference_only).pdf PDF
Pricing_Proposal_26-0394_(reference_only).pdf PDF
QUALIFICATION_SUBMITTAL_FORM_.pdf PDF
QUALIFICATION_SUBMITTAL_FORM_8-25.pdf PDF
QUALIFICATION_SUBMITTAL_FORM_8-25.pdf PDF
Sample_Agreement-26-0394.pdf PDF
Sample_Agreement-26-0394.pdf PDF
Foreign_Countries_of_Concern_Affidavit_02.05.2025_(1).pdf PDF
Common_Carrier_Attestation_02.05.2025.pdf PDF
Foreign_Countries_of_Concern_Affidavit_02.05.2025_(1).pdf PDF
Human_Trafficking_Affidavit_02.05.2025_(3).pdf PDF
Human_Trafficking_Affidavit_02.05.2025_(3).pdf PDF
Human_Trafficking_Affidavit_02.05.2025_(3).pdf PDF
Common_Carrier_Attestation_02.05.2025.pdf PDF
2022-Pinellas-County-Division-27.pdf PDF
2022-Pinellas-County-Division-27.pdf PDF
Pinellas_County_Solid_Waste_100%_CD_DS01202026.pdf PDF
Pinellas_County_Solid_Waste_100%_CD_DS01202026.pdf PDF
Pinellas_County_Solid_Waste_100%_CD_DS01202026.pdf PDF
Pinellas_County_Solid_Waste_HVAC_Renovation_100%_CD_Review_-_Specifications_-_DS01.20.2026.pdf PDF
Pinellas_County_Solid_Waste_HVAC_Renovation_100%_CD_Review_-_Specifications_-_DS01.20.2026.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
Non-Competitive_Oversight_Committee_Justification_Form.docx DOCX document
Sample_Change_Order.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
RE__For_Review__Draft_CIP_HVAC_Replacement_Construction_RFB.pdf PDF
Sample_Application_for_Payment.pdf PDF
Non-Competitive_Oversight_Committee_Justification_Form.docx DOCX document
Sample_Change_Order.pdf PDF
Airport_Security_Program.pdf PDF
E-Verify_Affidavit.pdf PDF
OpenGov_Fillable-_Final.pdf PDF
Non-Competitive_Oversight_Committee_Justification_Form.docx DOCX document
OpenGov_Fillable-_Final.pdf PDF
Performance_and_Payment_Bonds.pdf PDF
SBE_Compliance_Form.pdf PDF
Affdavit_of_Release_and_Guarantee.pdf PDF
E-Verify_Affidavit.pdf PDF
OpenGov_Fillable-_Final.pdf PDF
Sample_Application_for_Payment.pdf PDF
Affdavit_of_Release_and_Guarantee.pdf PDF
Performance_and_Payment_Bonds.pdf PDF
RE__For_Review__Draft_CIP_HVAC_Replacement_Construction_RFB.pdf PDF
Sample_Application_for_Payment.pdf PDF
25002_PCSW_HVAC_Renovation_Schedule_of_Values.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A B C D C

ITEM

NO.

DESCRIPTION OF WORK

SCHEDULED

VALUE

% OF

TOTAL

NOTES

1 BOND PREMIUM $10,000.00 1.5%

2 MOBILIZATION $15,000.00 2.2%

3 GENERAL CONDITIONS $20,500.00 3.0%

4 SELECTIVE DEMOLITION $12,500.00 1.8% REMOVE EXISTING HVAC SYSTEMS AND DISPOSAL

5 CONCRETE $4,500.00 0.7% HOUSEKEEPING PADS FOR NEW CUS

6 FENCING $2,500.00 0.4% FENCED ENCLOSURE FOR NEW CUS / MECH YARD

7 DRYWALL $5,000.00 0.7% AS REQUIRED FOR HVAC RENOVATIONS

8 CEILINGS, OTHER $7,500.00 1.1% AS REQUIRED FOR HVAC RENOVATIONS

9 PAINT AND WALL COVERINGS $2,500.00 0.4% AS REQUIRED FOR HVAC RENOVATIONS

10 INSULATION - MINOR REPAIRS $6,000.00 0.9% AS REQUIRED FOR HVAC RENOVATIONS

11 GENERAL HVAC REQUIREMENTS $12,500.00 1.8% BASIC MECHANICAL REQUIREMENTS, SUPPORTS, ANCHORS, ETC.

12 DX SPLIT SYSTEMS - CONDENSING UNITS, AHUS $47,600.00 6.9% QTY. 2 - 15 TON VAV DX SPLIT SYSTEMS

13 VAV BOXES $31,200.00 4.5% QTY. AS SCHEDULED ON PLANS, WITH ELECTRIC HEAT

14 100% OA DX SPLIT SYSTEM $27,840.00 4.1% 1500 CFM DOAS DX SPLIT SYSTEM

15 REFRIGERANT PIPING, SUPPORTS, AND INSULATION $6,300.00 0.9% NEW REFRIGERANT LINES

16 DUCTWORK, SUPPORTS, AND INSULATION $50,500.00 7.4% NEW SHEET METAL DUCTWORK, SUPPORTS AND INSULATION

17 AIR DEVICES, GRILLES, REGISTERS $22,640.00 3.3% NEW AIR DEVICES

18 HVAC CONTROLS $22,500.00 3.3% NEW HVAC CONTROLS

19 HVAC TEST AND BALANCE (T&B) $6,500.00 0.9% AABC OR NEBB CERTIFIED T&B OF ALL HVAC SYSTEMS

20 SYSTEM COMMISIONING (CxA) $3,500.00 0.5% CxA OF NEW HVAC SYSTEMS BY APPROVED COMMISIONING AGENT

21 ELECTRICAL PANEL AND EQUIPMENT $100,000.00 14.6%

22 ELECTRICAL WIRING AND CONDUIT $65,000.00 9.5%

23 ELECTRICAL DEMOLITION - VARIOUS $25,000.00 3.6%

24 ELECTRICAL LIGHTING/CONFERENCE ROOM $10,000.00 1.5%

25 CONDUIT FOR MECHANICAL CONTROLS $5,000.00 0.7%

26 COMMUNICATIONS - FIRE ALARM $20,000.00 2.9%

27 CONTINGENCY, OTHER $40,000.00 5.8%

28 PERMITS, FEES, OTHER $1,500.00 0.2%

29 OVERHEAD AND PROFIT (OH&P) $103,000.00 15.0%

TOTAL GMP = $686,580.00

PINELLAS COUNTY SOLID WASTE ADMINISTRATION BUILDING HVAC RENOVATION - PAY LIST ITEMS / SCHEDULE OF VALUES