This is a Submittal Register template used for federal construction contracts to track contractor submissions and approvals throughout the project lifecycle. The form serves as a comprehensive checklist and management tool for all required submittals from preconstruction through project closeout.
The register organizes submittals into several categories: SD-01 Preconstruction Submittals (including Accident Prevention Plans, Quality Control Plans, Construction Schedules, Equipment Delivery Schedules, Activity Hazard Analysis, Crane Work Plans, Traffic Control Plans, Environmental Protection Plans, and Preconstruction Surveys); SD-03 Product Data (Backflow Preventers); SD-06 Test Reports (Backflow Preventer Tests); SD-07 Certificates (Confined Space Entry Permits, Certificates of Compliance, Third Party Certifications for Barge-Mounted Mobile Cranes, and Backflow Preventer Certifications); and SD-11 Closeout Submittals (Submittal Registers, Complete Submittal Packages, and Interim DD1354 Transfer & Acceptance documents). The template includes columns for tracking action codes, submission dates, approval needed dates, material needed dates, dates forwarded to approving authorities and other reviewers, receipt dates, and remarks. The form establishes a systematic approach for managing contractor compliance with specification section requirements and ensuring timely approvals from government representatives before work proceeds.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT NO.
CONTRACTOR
SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
01 20 00
1.3
01 30 00
1.4.1
01 31 50
1.2
01 32 16
1.2
1.3
01 33 00
1.4.1
1.6.1
01 35 29
1.9
1.10
1.9.1
1.9.1
1.7.1.4
1.14
1.14.1
1.14.3
1.14.4
1.14.5
1.11
1.14.6
1.14.7
01 45 10
1.6
01 50 00
1.6.2.1
2.1
3.1
SD-03 PRODUCT DATA
Backflow Preventers (If Applicable)
SD-06 TEST REPORTS
SD-07 CERTIFICATES
SD-01 PRECONSTRUCTION SUBMITTALS
Traffic Control Plan (If Applicable)
Crane Critical Lift Plan (If Applicable)
Crane Operators (If Applicable)
Reports
Accident Reports
Monthly Exposure Reports
Regulatory Citations and Violations
Crane Reports
(Enter Contract No. Here)
SD-01 PRECONSTRUCTION SUBMITTALS
Accident Prevention Plan (APP)
SD-01 PRECONSTRUCTION SUBMITTALS
Equipment Delivery Schedule
SD-01 PRECONSTRUCTION SUBMITTALS
SUBMITTAL REGISTER
P A R A G R A P H
N O
S P E C
S E C T
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W R
(Enter Contractor Name Here)
Qaulity Control Plan (QC Plan)
Crane Work Plan (If Applicable)
Activity Hazard Analysis (AHA)
SD-06 TEST REPORTS
Certificate of Compliance
SD-01 PRECONSTRUCTION SUBMITTALS
TITLE AND LOCATION
(Enter Contract Title and Locaiton Here)
Schedule of Prices
List of Contact Personnel
Construction Schedule of Military Real Property (If Applicable)
A C T I V I T Y
N O
T R A N S M I T T A L
N O
(d)
DESCRIPTION ITEM SUBMITTED
SD-11 CLOSEOUT SUBMITTALS
SD-11 CLOSEOUT SUBMITTALS
Interim DD1354, Transfer & Acceptance
SD-11 CLOSEOUT SUBMITTALS
Submittal Register
Complete Submittal Package
Backflow Preventer Tests (If Applicable)
SD-07 CERTIFICATES
Third Party Certification of Barge-
Mounted Movile Cranes
Confined Space Entry Permit
Approving AuthorityContractor Schedule Dates
Contractor Action
1.3
01 57 19
1.6.1
1.6.4
1.7.2
1.7
1.7
PAGE 1 OF _
Backflow Preventers Certificate (If Applicable)
SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE
MSDS for Class I ODS Waivered Product
SD-01 PRECONSTRUCTION SUBMITTALS
Permit for Storm Water Discharge (If applicable)
Environmental Protection Plan
Preconstruction Survey
Notice of Intent (If applicable)
Backflow Tester Certification (If Applicable)