This is a Scope of Work document for a Multiple Building Flooring Project at Camp Lejeune, North Carolina (MACC# 24-0419, PROJECT# 24MO52CN, MAXIMO# 5422382). The project requires carpet removal and replacement with vinyl cove base installation across three buildings.
The scope encompasses three distinct project areas: Building 24, Room 210 (288 SF of carpet and 110 LF vinyl cove base); Building 1011, Rooms 202, 203, 206, 208, 209, and 210 (2,585 SF of carpet and 546 LF vinyl cove base); and Building 8, Command Deck, Meeting Room, offices and S4 wing (26,000 SF of carpet and 3,240 LF vinyl cove base). For all areas, the contractor must demo existing carpet, prep floors, apply Ardex Concrete Floor Sealer or equivalent, and install new carpet tiles with matching vinyl cove base. Building 24 and Building 1011 require Tarkett Abrasive Action 19101 Midnight Blue carpet tiles, while Building 8 requires Tarkett Abrasive Action Winter Grey 19103 carpet tiles. The contractor is responsible for taking field measurements, replacing any disturbed thresholds and vinyl wall base, cleaning all debris and over-spray, and repairing areas damaged by new work. Work must be coordinated with building occupants through designated points of contact and completed during standard working hours (0730-1800 Monday-Friday), with the option to schedule weekend and holiday work by agreement. The contractor must submit manufacturer's product specifications and technical data for approval and provide warranty coverage per the Combined Division 01 Specifications. Asbestos Reports are attached as hazardous materials documentation.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DISTRIBUTION: DoW COMMUNITY ONLY
MACC# 24-0419
PROJECT# 24MO52CN
MAXIMO# 5422382
TITLE: MULTIPLE BUILDING FLOORING PROJECT
ATTACHMENTS: 1. Scope, Specs, and ACM Reports
SCOPE OF WORK: The contractor shall provide all material, labor, equipment, and supervision required to accomplish the following:
General Description: This scope of work is to be accomplished at Buildings 24, 1011, and 8 at Camp Lejeune, North Carolina. The contractor shall remove carpet in specified areas and replace along with any baseboard for those said areas.
General Specifications: The contractor shall follow the general specifications unless noted in the project area description section. All measurements are for reference use only. THE
CONTRACTOR SHALL TAKE THEIR OWN FIELD MEASUREMENTS IN DETERMINING
REQUIRED MATERIAL AND COSTS. ALL WORK PERFORMED SHALL MEET OR EXCEED NC
MACC GENERIC SPECIFICATIONS THAT ARE ATTACHED.
Project Area Descriptions:
1. Building 24, Room 210
a. The contractor shall demo approximately 288 sq ft of carpet 110 LF vinyl cove base. Prep floor and apply approximately 288 sq ft of floor sealer.
Install approximately 288 SF of carpet and approximately 110 LF of vinyl cove base. Floor sealer to be Ardex Concrete Floor Sealer or equivalent.
Carpet to be Tarkett Abrasive Action 19101 Midnight Blue carpet tiles or equivalent. Vinyl cove base to match existing cove base.
2. Building 1011, Rooms 202, 203, 206, 208, 209, 210
a. The contractor shall demo approximately 2585 SF of carpet and 546 LF of vinyl cove base. Prep floor and apply approx. 2585 SF of floor sealer. Install approx. 2585 SF of carpet and 546 LF of vinyl cove base. Floor sealer to Ardex Concrete Floor Sealer or equivalent. Carpet to be Tarkett Abrasive Action 19101 Midnight Blue carpet tiles or equivalent. Vinyl cove base to match existing cove base.
3. Building 8, Command Deck, Meeting Room, offices and S4 wing
a. The contractor shall demo approximately 26,000 SF of carpet and 3,240 LF of vinyl cove base. Prep floor and apply approximately 26,000 SF of floor sealer. Install approximately 26,000 SF of carpet and 3,240 LF of vinyl cove base. Apply floor sealer to be Ardex Concrete Floor Sealer or equivalent.
This shall be applied where all carpet was demoed. Carpet to be Tarkett Abrasive Action Winter Grey 19103 carpet tiles or equivalent. Vinyl Cove Base to match existing.
NOTE: All measurements are approximate and should be field verified by contractor.
PROCEDURE:
Preparation:
The contractor shall take the necessary precautions to prepare and protect personal property, government property, and work areas during the accomplishment of work for this scope.
Interior Floor Carpet, Wax, Buff and Repairs:
Contractor shall replace any threshold between carpet and VCT as needed.
Existing carpet should be removed and replaced to manufactures specifications.
Replace any vinyl wall base that is disturbed. Sealant shall be applied before carpet is installed.
SPECIAL CONDITIONS
1. Clean all over-spray, drips, splatters, and spills resulting from accomplishing work for this project.
2. Repair, refinish areas damaged or disturbed by new work to be provided under this contract.
3. Properly remove, haul, and dispose of all debris. The contractor shall not utilize the dumpster provided by Camp Lejeune for the occupants or the base landfill.
SCHEDULING AND ACCESS:
1. Building 24 - SSgt. Carlos Melchor 910-450-2113
2. Building 1011 - John Heffington 910-450-8422
3. Building 8 - Freddie McDonald Jr 910-451-4270
4. General
a. This schedule is event driven and may be deviated from if both the occupants and contractor agree. Once the work has been started this project shall be worked continuously during scheduling.
b. Working hours to ensure timely completion.
c. Working hours are from 0730 to 1800 Monday through Friday. Scheduling work for weekends and holidays can be arranged with the occupants upon request.
HAZARDOUS MATERIALS: See attached Asbestos Reports
ENVIRONMENTAL REQUIREMENTS: None Identified
SUBMITTALS:
The contractor shall submit to the contracting officer, the manufacturer’s product specifications, complete with technical products data being used for this project.
Submittal should be marked for PROJECT No.
MATERIAL SPECIFICATIONS (CARPET)
1. CARPET:
a. Bldg. 24
i. Carpet to be Tarkett Abrasive Action 19101 Midnight Blue carpet tiles or equivalent. Vinyl cove base to match existing cove base.
b. Bldg. 1011 Rooms 202, 203, 206, 208, 209, 210
i. Carpet to be Tarkett Abrasive Action 19101 Midnight Blue carpet tiles or equivalent. Vinyl cove base to match existing cove base.
c. Bldg. 8 Command Deck, Meeting Room, S4 Wing
i. Carpet to be Tarkett Abrasive Action Winter Grey 19103 carpet tiles or equivalent. Vinyl Cove Base to match existing.
2. SEALANT:
a. Ardex or equivalent sealant for moisture control.
WARRANTY
Flooring contractor shall provide per the attached Combined Division 01 Specifications.