237413_Packaged,_Outdoor,_Central_Station_Rooftop_Units.pdf
PDF 159 KB Posted
- Attached to
- Volusia County Branch Jail Air Handler-Fire Suppression System Removal, Replacement and Upgrade
- Solicitation number
- 26-B-110IF
- Issued by
- Volusia County, Florida
About this file
This is a specification document for packaged, outdoor, central station rooftop units prepared by Volusia County for the Branch Jail facility located at 1300 Red John Drive, Daytona Beach, Florida. The specification outlines requirements for chilled water cooling rooftop air handling units (RTUs) with hydronic heating coils, integral space temperature controls, and roof curbs designed to replace the facility's obsolete HVAC infrastructure. The units must comply with a basic wind speed rating of 170 mph and include direct-digital controls (DDC) with BACnet or LonWorks compatibility for integration with the facility's building automation system. Approved manufacturers include AAON, Inc., Addison Products Company, Carrier Corporation, Daikin, Lennox Industries Inc., McQuay International, Trane, Temptrol, and YORK International Corporation. The specification requires comprehensive submittals including product data, shop drawings, wiring diagrams, delegated-design calculations for RTU supports, coordination drawings, field quality-control test reports, operation and maintenance manuals, and a manufacturer's warranty with a minimum three-year period for control boards.
The specification establishes detailed performance and quality requirements referencing ARI, ASHRAE, NFPA, and UL standards for equipment efficiency, sound performance, coil testing, electrical safety, and fire protection compliance. All RTU casings must feature double-wall galvanized steel construction with one-inch insulation thickness, stainless steel condensate drain pans, and factory-applied filtration systems meeting ASHRAE 52.2 standards. Roof curbs require NOA Florida Approval with vibration isolators and must maintain a three-foot clearance from outdoor intake hoods to the roof surface. Installation requires factory-authorized service representatives to perform startup service, conduct comprehensive testing and performance measurements, calibrate controls, and provide training to facility maintenance personnel. The project mandates two sets of replacement filters and one set of fan belts be supplied as extra materials, with startup adjustments available for up to two site visits within 12 months of substantial completion.
View the file
Other files
Show 40 more
Latest 50 of 128 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID SET VOLUSIA COUNTY
DECEMBER 5, 2025 BRANCH JAIL
PACKAGED, OUTDOOR, CENTRAL STATION ROOFTOP UNITS 237413.00 - 1
SECTION 237413 - PACKAGED, OUTDOOR, CENTRAL STATION ROOFTOP UNITS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes packaged, outdoor, central-station air-handling units (rooftop units) with the following components and accessories:
1. Chilled water cooling.
2. Hydronic heating coils.
3. Integral, space temperature controls.
4. Roof curbs.
1.3 DEFINITIONS
A. DDC: Direct-digital controls.
B. ECM: Electrically commutated motor.
C. Outdoor-Air Chilled Water Coil: Refrigerant coil in the outdoor-air stream to reject heat during cooling operations and to absorb heat during heating operations. "Outdoor air" is defined as the air outside the building or taken from outdoors and not previously circulated through the system.
D. RTU: Rooftop unit. As used in this Section, this abbreviation means packaged, outdoor, central-station air-handling units. This abbreviation is used regardless of whether the unit is mounted on the roof or on a concrete base on ground.
E. Supply-Air Fan: The fan providing supply air to conditioned space. "Supply air" is defined as the air entering a space from air-conditioning, heating, or ventilating apparatus.
F. Supply-Air Chilled Water Coil: Refrigerant coil in the supply-air stream to absorb heat (provide cooling) during cooling operations and to reject heat (provide heating) during heating operations. "Supply air" is defined as the air entering a space from air-conditioning, heating, or ventilating apparatus.
G. VVT: Variable-air volume and temperature.
PACKAGED, OUTDOOR, CENTRAL STATION ROOFTOP UNITS 237413.00 - 2
1.4 PERFORMANCE REQUIREMENTS
A. Delegated Design: Design RTU supports to comply with wind performance requirements, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated.
B. Wind-Restraint Performance:
1. Basic Wind Speed: 170 mph
2. Unit curb must be provided with NOA Florida Approved number.
1.5 SUBMITTALS
A. Product Data: Include manufacturer's technical data for each RTU, including rated capacities, dimensions, required clearances, characteristics, furnished specialties, and accessories.
B. Shop Drawings: Detail equipment assemblies and indicate dimensions, weights, loads, required clearances, method of field assembly, components, and location and size of each field connection.
1. Wiring Diagrams: Power, signal, and control wiring.
C. Delegated-Design Submittal: For RTU supports indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.
1. Design Calculations: Calculate requirements for selecting vibration isolators and for designing vibration isolation bases.
2. Detail mounting, securing, and flashing of roof curb to roof structure. Indicate coordinating requirements with roof membrane system.
D. Coordination Drawings: Plans and other details, drawn to scale, on which the following items are shown and coordinated with each other, using input from installers of the items involved:
1. Structural members to which RTUs will be attached.
2. Roof openings
3. Roof curbs and flashing.
E. Field quality-control test reports.
F. Operation and Maintenance Data: For RTUs to include in emergency, operation, and maintenance manuals.
G. Warranty: Special warranty specified in this Section.
1.6 QUALITY ASSURANCE
A. ARI Compliance:
PACKAGED, OUTDOOR, CENTRAL STATION ROOFTOP UNITS 237413.00 - 3
1. Comply with ARI 210/240 and ARI 340/360 for testing and rating energy efficiencies for RTUs.
2. Comply with ARI 270 for testing and rating sound performance for RTUs.
B. ASHRAE Compliance:
1. Comply with ASHRAE 33 for methods of testing cooling and heating coils.
2. Comply with ASHRAE/IESNA 90.1 for minimum efficiency of heating and cooling.
C. NFPA Compliance: Comply with NFPA 90A and NFPA 90B.
D. UL Compliance: Comply with UL 1995.
E. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.
1.7 WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to replace components of RTUs that fail in materials or workmanship within specified warranty period.
1. Warranty Period for Control Boards: Manufacturer's standard, but not less than three years from date of Substantial Completion.
1.8 EXTRA MATERIALS
A. Furnish extra materials described below that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.
1. Fan Belts: One set for each belt-driven fan.
2. Filters: Two sets of filters for each unit.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
1. AAON, Inc.
2. Addison Products Company.
3. Carrier Corporation.
4. Daikin
5. Lennox Industries Inc.
6. McQuay International.
7. Trane; American Standard Companies, Inc.
8. Temptrol
9. YORK International Corporation.
PACKAGED, OUTDOOR, CENTRAL STATION ROOFTOP UNITS 237413.00 - 4
2.2 CASING
A. General Fabrication Requirements for Casings: Formed and reinforced double-wall insulated panels, fabricated to allow removal for access to internal parts and components, with joints between sections sealed.
B. Exterior Casing Material: Galvanized steel with factory-painted finish, with pitched roof panels and knockouts with grommet seals for electrical and piping connections and lifting lugs.
1. Exterior Casing Thickness: 0.079 inch (2.0 mm) thick.
C. Inner Casing Fabrication Requirements:
1. Inside Casing: Galvanized steel, 0.034 inch (0.86 mm) thick.
D. Casing Insulation and Adhesive: Comply with NFPA 90A or NFPA 90B.
1. Materials: ASTM C 1071, Type I.
2. Thickness: 1 inch (25 mm).
3. Liner materials shall have air-stream surface coated with an erosion- and temperature-resistant coating or faced with a plain or coated fibrous mat or fabric.
4. Liner Adhesive: Comply with ASTM C 916, Type I.
E. Condensate Drain Pans: Formed sections of stainless-steel sheet, a minimum of 2 inches (50
mm) deep, and complying with ASHRAE 62.
1. Double-Wall Construction: Fill space between walls with foam insulation and seal moisture tight.
2. Drain Connections: Threaded nipple both sides of drain pan.
3. Pan-Top Surface Coating: Corrosion-resistant compound.
2.3 FANS
A. Direct-Driven Supply-Air Fans: Double width, forward curved, centrifugal; with permanently lubricated, multispeed or ECM motor installed on an adjustable fan base resiliently mounted in the casing. Aluminum or painted-steel wheels, and galvanized- or painted-steel fan scrolls.
B. Condenser-Coil Fan: Propeller, mounted on shaft of permanently lubricated motor.
C. Fan Motor: Comply with requirements in Section 230513 "Common Motor Requirements for HVAC Equipment."
2.4 COILS
A. Supply-Air Chilled Water Coil:
1. Aluminum-plate fin and seamless internally grooved copper tube in steel casing with equalizing-type vertical distributor.
2. Polymer strip shall prevent all copper coil from contacting steel coil frame or condensate pan.
PACKAGED, OUTDOOR, CENTRAL STATION ROOFTOP UNITS 237413.00 - 5
3. Coil Split: Interlaced.
4. Condensate Drain Pan: Stainless steel formed with pitch and drain connections complying with ASHRAE 62.
2.5 AIR FILTRATION
A. Minimum arrestance according to ASHRAE 52.1, and a minimum efficiency reporting value (MERV) according to ASHRAE 52.2. Provide two pre-filters
1. Pleated: Minimum 65 percent arrestance, and MERV 7.
2. Flat Filter: Minimum 05 percent arrestance and MERV 13.
2.6 DAMPERS
A. Outdoor- and Return-Air Mixing Dampers: Parallel- or opposed-blade galvanized-steel dampers mechanically fastened to cadmium plated for galvanized-steel operating rod in reinforced cabinet. Connect operating rods with common linkage and interconnect linkages so dampers operate simultaneously.
1. Damper Motor: Modulating with adjustable minimum position.
2.7 ELECTRICAL POWER CONNECTION
A. Provide for single connection of power to unit with control-circuit transformer with built-in overcurrent protection.
2.8 CONTROLS
A. DDC Controller:
1. Controller shall have volatile-memory backup and be compatible with existing campus System.
2. Safety Control Operation:
a. Smoke Detectors: Stop fan and close outdoor-air damper if smoke is detected.
Provide additional contacts for alarm interface to fire alarm control panel.
b. Fire Alarm Control Panel Interface: Provide control interface to coordinate with operating sequence described in Section "Fire Alarm."
c. Low-Discharge Temperature: Stop fan and close outdoor-air damper if supply air temperature is less than 40 deg F (4 deg C).
d. Defrost Control for Condenser Coil: Pressure differential switch to initiate defrost sequence.
3. Scheduled Operation: Occupied and unoccupied periods on 365-day clock with a minimum of two programmable periods per day.
4. Unoccupied Period:
a. Heating Setback: 60 deg F.
PACKAGED, OUTDOOR, CENTRAL STATION ROOFTOP UNITS 237413.00 - 6
b. Cooling Setback: 78 degrees F.
c. Override Operation: Three hours.
5. Supply Fan Operation:
a. Occupied Periods: Run fan continuously.
b. Unoccupied Periods: Cycle fan to maintain setback temperature.
6. Chilled Water Circuit Operation:
a. Occupied Periods: Modulate CHW valves to maintain room discharge temperature and humidity.
B. Interface Requirements for HVAC Instrumentation and Control System:
1. Interface relay for scheduled operation.
2. Interface relay to provide indication of fault at the central workstation and diagnostic code storage.
3. Provide BACnet or LonWorks compatible interface for central HVAC control workstation for the following:
a. Adjusting set points.
b. Monitoring supply fan start, stop, and operation.
c. Inquiring data to include outdoor-air damper position, supply- and room-air temperature.
d. Monitoring occupied and unoccupied operations.
e. Monitoring constant and variable motor loads.
f. Monitoring cooling load.
g. Monitoring economizer cycles.
h. Monitoring air-distribution static pressure and ventilation air volume.
i. Monitoring gas furnace operation.
2.9 ACCESSORIES
A. Duplex, 115-V, ground-fault-interrupter outlet with 15-A overcurrent protection. Include transformer if required. Outlet shall be energized even if the unit main disconnect is open.
B. Low-ambient kit using staged condenser fans for operation down to 35 deg F (1.7 deg C).
C. Filter differential pressure switch with sensor tubing on either side of filter. Set for final filter pressure loss.
D. Coil guards of painted, galvanized-steel wire.
2.10 ROOF CURBS
A. Roof curbs with vibration isolators meeting NOA Florida Approval.
PACKAGED, OUTDOOR, CENTRAL STATION ROOFTOP UNITS 237413.00 - 7
B. Materials: Galvanized steel with corrosion-protection coating, watertight gaskets, and factory-installed wood nailer; complying with NRCA standards.
1. Curb Insulation and Adhesive: Comply with NFPA 90A or NFPA 90B.
a. Materials: ASTM C 1071, Type I or II.
b. Thickness: 2 inches (50 mm).
2. Application: Factory applied with adhesive and mechanical fasteners to the internal surface of curb.
a. Liner Adhesive: Comply with ASTM C 916, Type I.
b. Mechanical Fasteners: Galvanized steel, suitable for adhesive attachment, mechanical attachment, or welding attachment to duct without damaging liner when applied as recommended by manufacturer and without causing leakage in cabinet.
c. Liner materials applied in this location shall have air-stream surface coated with a temperature-resistant coating or faced with a plain or coated fibrous mat or fabric depending on service air velocity.
d. Liner Adhesive: Comply with ASTM C 916, Type I.
C. Curb Height: 24 inches (610 mm) or as required to maintaince 3’ clearance from outdoor intake hood to top of roof/roof insulation.
D. Wind Restraints: Metal brackets compatible with the curb and casing, painted to match RTU, used to anchor unit to the curb, and designed for loads at Project site.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of RTUs.
B. Examine roughing-in for RTUs to verify actual locations of piping and duct connections before equipment installation.
C. Examine roofs for suitable conditions where RTUs will be installed.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Roof Curb: Install on roof structure, level and secure, according to NRCA's "Low-Slope Membrane Roofing Construction Details Manual," Illustration "Raised Curb Detail for Rooftop Air Handling Units and Ducts" and/or ARI Guideline B. Install RTUs on curbs and coordinate roof penetrations and flashing with roof construction specified in Section "Roof Accessories."
Secure RTUs to upper curb rail, and secure curb base to roof framing with anchor bolts.
PACKAGED, OUTDOOR, CENTRAL STATION ROOFTOP UNITS 237413.00 - 8
B. Unit Support: Install unit level on structural curbs. Coordinate wall penetrations and flashing with wall construction. Secure RTUs to structural support with anchor bolts.
C. Install wind and seismic restraints according to manufacturer's written instructions.
3.3 CONNECTIONS
A. Install condensate drain, minimum connection size, with trap and indirect connection to nearest roof drain or area drain.
B. Install piping adjacent to RTUs to allow service and maintenance.
C. Duct installation requirements are specified in other Division 23 Sections. Drawings indicate the general arrangement of ducts. The following are specific connection requirements:
1. Install ducts to termination at top of roof curb.
2. Remove roof decking only as required for passage of ducts. Do not cut out decking under entire roof curb.
3. Connect supply ducts to RTUs with flexible duct connectors specified in Division 23
Section "Duct Accessories."
4. Install return-air duct continuously through roof structure.
3.4 FIELD QUALITY CONTROL
A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust components, assemblies, and equipment installations, including connections.
Report results in writing.
B. Perform tests and inspections and prepare test reports.
1. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect components, assemblies, and equipment installations, including connections, and to assist in testing. Report results in writing.
C. Tests and Inspections:
1. After installing RTUs and after electrical circuitry has been energized, test units for compliance with requirements.
2. Inspect for and remove shipping bolts, blocks, and tie-down straps.
3. Operational Test: After electrical circuitry has been energized, start units to confirm proper motor rotation and unit operation.
4. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.
D. Remove and replace malfunctioning units and retest as specified above.
PACKAGED, OUTDOOR, CENTRAL STATION ROOFTOP UNITS 237413.00 - 9
3.5 STARTUP SERVICE
A. Engage a factory-authorized service representative to perform startup service.
B. Complete installation and startup checks according to manufacturer's written instructions and do the following:
1. Inspect for visible damage to unit casing.
2. Inspect for visible damage to coils and fans.
3. Inspect internal insulation.
4. Verify that labels are clearly visible.
5. Verify that clearances have been provided for servicing.
6. Verify that controls are connected and operable.
7. Verify that filters are installed.
8. Clean condenser coil and inspect for construction debris.
9. Remove packing from vibration isolators.
10. Verify lubrication on fan and motor bearings.
11. Inspect fan-wheel rotation for movement in correct direction without vibration and binding.
12. Adjust fan belts to proper alignment and tension.
13. Start unit according to manufacturer's written instructions.
a. Do not operate below recommended low-ambient temperature.
b. Complete startup sheets and attach copy with Contractor's startup report.
14. Inspect and record performance of interlocks and protective devices; verify sequences.
15. Operate unit for an initial period as recommended or required by manufacturer.
16. Calibrate thermostats.
17. Adjust and inspect high-temperature limits.
18. Inspect outdoor-air dampers for proper stroke and interlock with return-air dampers.
19. Start system and measure and record the following when ambient is a minimum of 15 deg F (8 deg C) above return-air temperature:
a. Coil leaving-air, dry- and wet-bulb temperatures.
b. Coil entering-air, dry- and wet-bulb temperatures.
c. Outdoor-air, dry-bulb temperature.
20. Inspect controls for correct sequencing of heating, mixing dampers, and normal and emergency shutdown.
21. Measure and record the following minimum and maximum airflows. Plot fan volumes on fan curve.
a. Supply-air volume.
b. Return-air volume.
c. Relief-air volume.
d. Outdoor-air intake volume.
22. After startup and performance testing and prior to Substantial Completion, replace existing filters with new filters.
PACKAGED, OUTDOOR, CENTRAL STATION ROOFTOP UNITS 237413.00 - 10
3.6 CLEANING AND ADJUSTING
A. Occupancy Adjustments: When requested within 12 months of date of Substantial Completion, provide on-site assistance in adjusting system to suit actual occupied conditions. Provide up to two visits to site during other-than-normal occupancy hours for this purpose.
B. After completing system installation and testing, adjusting, and balancing RTU and air-distribution systems, clean filter housings and install new filters.
3.7 DEMONSTRATION
A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain RTUs. Refer to Division 1 Section "Demonstration and Training."
END OF SECTION 237413
| PART 1 - GENERAL |
| 1.1 RELATED DOCUMENTS |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. |
| 1.2 SUMMARY |
| A. This Section includes packaged, outdoor, central-station air-handling units (rooftop units) with the following components and accessories: |
| 1. Chilled water cooling. |
| 2. Hydronic heating coils. |
| 3. Integral, space temperature controls. |
| 4. Roof curbs. |
| 1.3 DEFINITIONS |
| A. DDC: Direct-digital controls. |
| B. ECM: Electrically commutated motor. |
| C. Outdoor-Air Chilled Water Coil: Refrigerant coil in the outdoor-air stream to reject heat during cooling operations and to absorb heat during heating operations. "Outdoor air" is defined as the air outside the building or taken from outdoors and ... |
| D. RTU: Rooftop unit. As used in this Section, this abbreviation means packaged, outdoor, central-station air-handling units. This abbreviation is used regardless of whether the unit is mounted on the roof or on a concrete base on ground. |
| E. Supply-Air Fan: The fan providing supply air to conditioned space. "Supply air" is defined as the air entering a space from air-conditioning, heating, or ventilating apparatus. |
| F. Supply-Air Chilled Water Coil: Refrigerant coil in the supply-air stream to absorb heat (provide cooling) during cooling operations and to reject heat (provide heating) during heating operations. "Supply air" is defined as the air entering a spac... |
| G. VVT: Variable-air volume and temperature. |
| 1.4 PERFORMANCE REQUIREMENTS |
| A. Delegated Design: Design RTU supports to comply with wind performance requirements, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated. |
| B. Wind-Restraint Performance: |
| 1. Basic Wind Speed: 170 mph |
| 2. Unit curb must be provided with NOA Florida Approved number. |
| 1.5 SUBMITTALS |
| A. Product Data: Include manufacturer's technical data for each RTU, including rated capacities, dimensions, required clearances, characteristics, furnished specialties, and accessories. |
| B. Shop Drawings: Detail equipment assemblies and indicate dimensions, weights, loads, required clearances, method of field assembly, components, and location and size of each field connection. |
| 1. Wiring Diagrams: Power, signal, and control wiring. |
| C. Delegated-Design Submittal: For RTU supports indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation. |
| 1. Design Calculations: Calculate requirements for selecting vibration isolators and for designing vibration isolation bases. |
| 2. Detail mounting, securing, and flashing of roof curb to roof structure. Indicate coordinating requirements with roof membrane system. |
| D. Coordination Drawings: Plans and other details, drawn to scale, on which the following items are shown and coordinated with each other, using input from installers of the items involved: |
| 1. Structural members to which RTUs will be attached. |
| 2. Roof openings |
| 3. Roof curbs and flashing. |
| E. Field quality-control test reports. |
| F. Operation and Maintenance Data: For RTUs to include in emergency, operation, and maintenance manuals. |
| G. Warranty: Special warranty specified in this Section. |
| 1.6 QUALITY ASSURANCE |
| A. ARI Compliance: |
| 1. Comply with ARI 210/240 and ARI 340/360 for testing and rating energy efficiencies for RTUs. |
| 2. Comply with ARI 270 for testing and rating sound performance for RTUs. |
| B. ASHRAE Compliance: |
| 1. Comply with ASHRAE 33 for methods of testing cooling and heating coils. |
| 2. Comply with ASHRAE/IESNA 90.1 for minimum efficiency of heating and cooling. |
| C. NFPA Compliance: Comply with NFPA 90A and NFPA 90B. |
| D. UL Compliance: Comply with UL 1995. |
| E. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. |
| 1.7 WARRANTY |
| A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to replace components of RTUs that fail in materials or workmanship within specified warranty period. |
| 1. Warranty Period for Control Boards: Manufacturer's standard, but not less than three years from date of Substantial Completion. |
| 1.8 EXTRA MATERIALS |
| A. Furnish extra materials described below that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. |
| 1. Fan Belts: One set for each belt-driven fan. |
| 2. Filters: Two sets of filters for each unit. |
| PART 2 - PRODUCTS |
| 2.1 MANUFACTURERS |
| A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: |
| 1. AAON, Inc. |
| 2. Addison Products Company. |
| 3. Carrier Corporation. |
| 4. Daikin |
| 5. Lennox Industries Inc. |
| 6. McQuay International. |
| 7. Trane; American Standard Companies, Inc. |
| 8. Temptrol |
| 9. YORK International Corporation. |
| 2.2 CASING |
| A. General Fabrication Requirements for Casings: Formed and reinforced double-wall insulated panels, fabricated to allow removal for access to internal parts and components, with joints between sections sealed. |
| B. Exterior Casing Material: Galvanized steel with factory-painted finish, with pitched roof panels and knockouts with grommet seals for electrical and piping connections and lifting lugs. |
| 1. Exterior Casing Thickness: 0.079 inch (2.0 mm) thick. |
| C. Inner Casing Fabrication Requirements: |
| 1. Inside Casing: Galvanized steel, 0.034 inch (0.86 mm) thick. |
| D. Casing Insulation and Adhesive: Comply with NFPA 90A or NFPA 90B. |
| 1. Materials: ASTM C 1071, Type I. |
| 2. Thickness: 1 inch (25 mm). |
| 3. Liner materials shall have air-stream surface coated with an erosion- and temperature-resistant coating or faced with a plain or coated fibrous mat or fabric. |
| 4. Liner Adhesive: Comply with ASTM C 916, Type I. |
| E. Condensate Drain Pans: Formed sections of stainless-steel sheet, a minimum of 2 inches (50 mm) deep, and complying with ASHRAE 62. |
| 1. Double-Wall Construction: Fill space between walls with foam insulation and seal moisture tight. |
| 2. Drain Connections: Threaded nipple both sides of drain pan. |
| 3. Pan-Top Surface Coating: Corrosion-resistant compound. |
| 2.3 FANS |
| A. Direct-Driven Supply-Air Fans: Double width, forward curved, centrifugal; with permanently lubricated, multispeed or ECM motor installed on an adjustable fan base resiliently mounted in the casing. Aluminum or painted-steel wheels, and galvanized... |
| B. Condenser-Coil Fan: Propeller, mounted on shaft of permanently lubricated motor. |
| C. Fan Motor: Comply with requirements in Section 230513 "Common Motor Requirements for HVAC Equipment." |
| 2.4 COILS |
| A. Supply-Air Chilled Water Coil: |
| 1. Aluminum-plate fin and seamless internally grooved copper tube in steel casing with equalizing-type vertical distributor. |
| 2. Polymer strip shall prevent all copper coil from contacting steel coil frame or condensate pan. |
| 3. Coil Split: Interlaced. |
| 4. Condensate Drain Pan: Stainless steel formed with pitch and drain connections complying with ASHRAE 62. |
| 2.5 AIR FILTRATION |
| A. Minimum arrestance according to ASHRAE 52.1, and a minimum efficiency reporting value (MERV) according to ASHRAE 52.2. Provide two pre-filters |
| 1. Pleated: Minimum 65 percent arrestance, and MERV 7. |
| 2. Flat Filter: Minimum 05 percent arrestance and MERV 13. |
| 2.6 DAMPERS |
| A. Outdoor- and Return-Air Mixing Dampers: Parallel- or opposed-blade galvanized-steel dampers mechanically fastened to cadmium plated for galvanized-steel operating rod in reinforced cabinet. Connect operating rods with common linkage and interconn... |
| 1. Damper Motor: Modulating with adjustable minimum position. |
| 2.7 ELECTRICAL POWER CONNECTION |
| A. Provide for single connection of power to unit with control-circuit transformer with built-in overcurrent protection. |
| 2.8 CONTROLS |
| A. DDC Controller: |
| 1. Controller shall have volatile-memory backup and be compatible with existing campus System. |
| 2. Safety Control Operation: |
| a. Smoke Detectors: Stop fan and close outdoor-air damper if smoke is detected. Provide additional contacts for alarm interface to fire alarm control panel. |
| b. Fire Alarm Control Panel Interface: Provide control interface to coordinate with operating sequence described in Section "Fire Alarm." |
| c. Low-Discharge Temperature: Stop fan and close outdoor-air damper if supply air temperature is less than 40 deg F (4 deg C). |
| d. Defrost Control for Condenser Coil: Pressure differential switch to initiate defrost sequence. |
| 3. Scheduled Operation: Occupied and unoccupied periods on 365-day clock with a minimum of two programmable periods per day. |
| 4. Unoccupied Period: |
| a. Heating Setback: 60 deg F. |
| b. Cooling Setback: 78 degrees F. |
| c. Override Operation: Three hours. |
| 5. Supply Fan Operation: |
| a. Occupied Periods: Run fan continuously. |
| b. Unoccupied Periods: Cycle fan to maintain setback temperature. |
| 6. Chilled Water Circuit Operation: |
| a. Occupied Periods: Modulate CHW valves to maintain room discharge temperature and humidity. |
| B. Interface Requirements for HVAC Instrumentation and Control System: |
| 1. Interface relay for scheduled operation. |
| 2. Interface relay to provide indication of fault at the central workstation and diagnostic code storage. |
| 3. Provide BACnet or LonWorks compatible interface for central HVAC control workstation for the following: |
| a. Adjusting set points. |
| b. Monitoring supply fan start, stop, and operation. |
| c. Inquiring data to include outdoor-air damper position, supply- and room-air temperature. |
| d. Monitoring occupied and unoccupied operations. |
| e. Monitoring constant and variable motor loads. |
| f. Monitoring cooling load. |
| g. Monitoring economizer cycles. |
| h. Monitoring air-distribution static pressure and ventilation air volume. |
| i. Monitoring gas furnace operation. |
| 2.9 ACCESSORIES |
| A. Duplex, 115-V, ground-fault-interrupter outlet with 15-A overcurrent protection. Include transformer if required. Outlet shall be energized even if the unit main disconnect is open. |
| B. Low-ambient kit using staged condenser fans for operation down to 35 deg F (1.7 deg C). |
| C. Filter differential pressure switch with sensor tubing on either side of filter. Set for final filter pressure loss. |
| D. Coil guards of painted, galvanized-steel wire. |
| 2.10 ROOF CURBS |
| A. Roof curbs with vibration isolators meeting NOA Florida Approval. |
| B. Materials: Galvanized steel with corrosion-protection coating, watertight gaskets, and factory-installed wood nailer; complying with NRCA standards. |
| 1. Curb Insulation and Adhesive: Comply with NFPA 90A or NFPA 90B. |
| a. Materials: ASTM C 1071, Type I or II. |
| b. Thickness: 2 inches (50 mm). |
| 2. Application: Factory applied with adhesive and mechanical fasteners to the internal surface of curb. |
| a. Liner Adhesive: Comply with ASTM C 916, Type I. |
| b. Mechanical Fasteners: Galvanized steel, suitable for adhesive attachment, mechanical attachment, or welding attachment to duct without damaging liner when applied as recommended by manufacturer and without causing leakage in cabinet. |
| c. Liner materials applied in this location shall have air-stream surface coated with a temperature-resistant coating or faced with a plain or coated fibrous mat or fabric depending on service air velocity. |
| d. Liner Adhesive: Comply with ASTM C 916, Type I. |
| C. Curb Height: 24 inches (610 mm) or as required to maintaince 3’ clearance from outdoor intake hood to top of roof/roof insulation. |
| D. Wind Restraints: Metal brackets compatible with the curb and casing, painted to match RTU, used to anchor unit to the curb, and designed for loads at Project site. |
| PART 3 - EXECUTION |
| 3.1 EXAMINATION |
| A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of RTUs. |
| B. Examine roughing-in for RTUs to verify actual locations of piping and duct connections before equipment installation. |
| C. Examine roofs for suitable conditions where RTUs will be installed. |
| D. Proceed with installation only after unsatisfactory conditions have been corrected. |
| 3.2 INSTALLATION |
| A. Roof Curb: Install on roof structure, level and secure, according to NRCA's "Low-Slope Membrane Roofing Construction Details Manual," Illustration "Raised Curb Detail for Rooftop Air Handling Units and Ducts" and/or ARI Guideline B. Install RTUs o... |
| B. Unit Support: Install unit level on structural curbs. Coordinate wall penetrations and flashing with wall construction. Secure RTUs to structural support with anchor bolts. |
| C. Install wind and seismic restraints according to manufacturer's written instructions. |
| 3.3 CONNECTIONS |
| A. Install condensate drain, minimum connection size, with trap and indirect connection to nearest roof drain or area drain. |
| B. Install piping adjacent to RTUs to allow service and maintenance. |
| C. Duct installation requirements are specified in other Division 23 Sections. Drawings indicate the general arrangement of ducts. The following are specific connection requirements: |
| 1. Install ducts to termination at top of roof curb. |
| 2. Remove roof decking only as required for passage of ducts. Do not cut out decking under entire roof curb. |
| 3. Connect supply ducts to RTUs with flexible duct connectors specified in Division 23 Section "Duct Accessories." |
| 4. Install return-air duct continuously through roof structure. |
| 3.4 FIELD QUALITY CONTROL |
| A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust components, assemblies, and equipment installations, including connections. Report results in writing. |
| B. Perform tests and inspections and prepare test reports. |
| 1. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect components, assemblies, and equipment installations, including connections, and to assist in testing. Report results in writing. |
| C. Tests and Inspections: |
| 1. After installing RTUs and after electrical circuitry has been energized, test units for compliance with requirements. |
| 2. Inspect for and remove shipping bolts, blocks, and tie-down straps. |
| 3. Operational Test: After electrical circuitry has been energized, start units to confirm proper motor rotation and unit operation. |
| 4. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment. |
D. Remove and replace malfunctioning units and retest as specified above.
| 3.5 STARTUP SERVICE |
| A. Engage a factory-authorized service representative to perform startup service. |
| B. Complete installation and startup checks according to manufacturer's written instructions and do the following: |
| 1. Inspect for visible damage to unit casing. |
| 2. Inspect for visible damage to coils and fans. |
| 3. Inspect internal insulation. |
| 4. Verify that labels are clearly visible. |
| 5. Verify that clearances have been provided for servicing. |
| 6. Verify that controls are connected and operable. |
| 7. Verify that filters are installed. |
| 8. Clean condenser coil and inspect for construction debris. |
| 9. Remove packing from vibration isolators. |
| 10. Verify lubrication on fan and motor bearings. |
| 11. Inspect fan-wheel rotation for movement in correct direction without vibration and binding. |
| 12. Adjust fan belts to proper alignment and tension. |
| 13. Start unit according to manufacturer's written instructions. |
| a. Do not operate below recommended low-ambient temperature. |
| b. Complete startup sheets and attach copy with Contractor's startup report. |
| 14. Inspect and record performance of interlocks and protective devices; verify sequences. |
| 15. Operate unit for an initial period as recommended or required by manufacturer. |
| 16. Calibrate thermostats. |
| 17. Adjust and inspect high-temperature limits. |
| 18. Inspect outdoor-air dampers for proper stroke and interlock with return-air dampers. |
| 19. Start system and measure and record the following when ambient is a minimum of 15 deg F (8 deg C) above return-air temperature: |
| a. Coil leaving-air, dry- and wet-bulb temperatures. |
| b. Coil entering-air, dry- and wet-bulb temperatures. |
| c. Outdoor-air, dry-bulb temperature. |
| 20. Inspect controls for correct sequencing of heating, mixing dampers, and normal and emergency shutdown. |
| 21. Measure and record the following minimum and maximum airflows. Plot fan volumes on fan curve. |
| a. Supply-air volume. |
| b. Return-air volume. |
| c. Relief-air volume. |
| d. Outdoor-air intake volume. |
22. After startup and performance testing and prior to Substantial Completion, replace existing filters with new filters.
| 3.6 CLEANING AND ADJUSTING |
| A. Occupancy Adjustments: When requested within 12 months of date of Substantial Completion, provide on-site assistance in adjusting system to suit actual occupied conditions. Provide up to two visits to site during other-than-normal occupancy hours... |
| B. After completing system installation and testing, adjusting, and balancing RTU and air-distribution systems, clean filter housings and install new filters. |
| 3.7 DEMONSTRATION |
| A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain RTUs. Refer to Division 1 Section "Demonstration and Training." |