This document is a submittal package for trench drain materials for the VA Replacement Medical Center Facility project located in Aurora, Colorado. The submittal was submitted by Kiewit-Turner, a joint venture general contractor, on behalf of The Mechanical Diamond Partners (mechanical contractor) and C and B Plumbing (subcontractor/supplier). The primary submittal item is Trench Drain 3 (specification section 22 13 00), with the manufacturer listed as Quickdrain USA, specifically a ProLine Drain Body model TD-3.

The submittal was initially submitted on March 27, 2014, with a requested return date of April 17, 2014. The contractor's submittal (numbered 22 13 00-31) was received and reviewed by the Department of Veterans Affairs on April 18, 2014, and subsequently returned as "Approved, as Noted" on May 5, 2014. The VA's approval conditions specified that the trench drain must: (1) be installed with a 6-inch membrane per specifications, (2) provide a diagonal pattern as per specification requirements, and (3) be in compliance with ANSI A 112.6.3 standard. The contract number is VA101CFM-C-0100, project number 554-501, and the facility location is the VA Medical Center in Denver, Colorado.

View the file

Other files

File Type Posted
Attachment D - Floor Detail RFI.pdf PDF
36C25926R0038 0002.docx DOCX document
Answers to RFRs 3.06.2026.pdf PDF
S04 - Site Visit Attendance rd2.pdf PDF
S04 - Site Visit Meeting Doc.docx DOCX document
SOW Attachment C Phasing 554-26-101 Reslope Shower Floors.pdf PDF
SOW 554-26-101 Reslope Shower Floors in Bldg H_K Final.docx DOCX document
36C25926R0038 0001.docx DOCX document
Prime and Sub Contractor Construction Breakdown.xlsx XLSX spreadsheet
22 13 00_JSI041 - Facility Sanitary and Vent Piping.pdf PDF
Specifications 554-26-101 Reslope Shower Floors in Bldg H_K.pdf PDF
ICRA 554-26-101 Reslope Shower Floors in Bldg H_K.docx DOCX document
Answers to RFR.pdf PDF
SOW Attachment A rooms 554-26-101 Reslope Shower Floors.pdf PDF
Tile Enchant_HDP_Technical_Sheet_Oct_2022.pdf PDF
52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026 Deviation NOV 2025.docx DOCX document
852.219-75 LOS Certification.docx DOCX document
Bathroom Photos.pdf PDF
SOW Attachment B procedure 554-26-101 Reslope Shower Floors.docx DOCX document
52.222-54 Employment Eligibility Verification Deviation NOV 2025.docx DOCX document
36C25926R0038.docx DOCX document
Past Performance Questionnaire_Blank.docx DOCX document
Self-Performed and Subcontracted Worksheet.docx DOCX document
Drawings 554-26-101 Reslope Shower Floors in Bldg H_K.pdf PDF
09 67 23 20 Decorative Mosaic Flake submittal.pdf PDF
Tile Enchant_Literature.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

q Department of Veterans Affairs

RETURN OF SUBMITTAL VA File No: 22 13 00-31 Title or Description Date Spec. Section

Trench Drain 3 6 , 22 1300

Contractor's Name and Address Station Location VA Medical Center

Kiewit-Turner, a Joint Venture Denver, CO

7200 S. Alton Way, Suite A-300 Contract No. Project No.

Englewood, CO 80112 VA101CFMC01 00 554-501 Transmittal Date VA File No.

04/18/2014 22 13 00-31

Form of Submittal

Letter of Affidavit Shop Drawings Data Sheets Brochure Physical Sample of Compliance

Manufacturers Literature Test Reports Other or Catalog Cuts

Submittal Scope

22 13 00-31 - Trench Drain 3

Department of Veterans Affairs Actions Authority for Approval/Disapproval (Check appropriate box - Approvals subject to compliance with all contract requirements and to notations/corrections noted)

Approved X Approved, as Noted Approved, as Noted, Resubmit Disapproved, Resubmit No Action No Action, Resubmit

Submittal Items Acted Upon Submittal Item Status

001 Trench Drain 3 AN

Supplier or Manufacturer

Notes/Comments

1. Install with 6" membrane per the specifications.

2. Provide trench drain with diagonal pattern as per spec.

3. Trench drain shall be in compliance with ANSI A 112.6.3.

SturfA7izing Official

Date

PARAGON Project Management System Va Form 08-6225 Page 1 SijBMOO-25.Denver VA Return of Submittal

Received 05/05/2014

Fax: 303.930.9001

303.930.9000Tel:

Kiewit - Turner a Joint Venture

Suite A-300 7200 S. Alton Way

Englewood, CO 80112

Job: 15387 - Replacement Medical Center Facility

Product Data

Sample

Other

Shop Drawing

Resubmittal

First Submittal X

VA Proj #:

To: H+L Architecture 1755 Blake Street

Suite 400

Denver, CO 80202

DESCRIPTIONSpecificationSUBMITTAL

ItemQuantity Section Sub./SupplierNo. Mfgr.

ACTION

DCBA E

Kiewit Submittal No. 22 13 00-01

Architect's Submittal No. 00008

Review Cycle: 001

Attn: Chuck Adkisson

1 SWPPP - CBS & RFP #3 OnlyKiewit - Turner a

Joint Venture

01 573

ACTION TAKEN

CONTRACTOR'S SIGNATURE:

CONTRACTOR'S NOTES:

DATE: 7/12/2011

Reviewed Only for Revisions to

Reviewed: Incorporate Changes

Reviewed=

A

B

C

Previous Submittal

Revise and Resubmit=D

Rejected =E

ARCHITECT/ENGINEER RESPONSE:

REMARKS:

BY: DATE:

Expedition f_sb_pks_01a

VA101CFM-C-0100

Cc: Tim Pogany, U.S. Dept. of Veterans Affairs

Received By ___________________

Date _______________

REQUESTED RETURN DATE:

22 13 00

X

Trench Drain 3 Submittal

X

C & b Plumbing

22 13 0031

04/17/2014

04/21/2014

Kiewit-Turner Submittal No.

VA 1

JVT 1

By VACO BoltonT at 2:53 pm, Apr 30, 2014

04/17/14

22 13 00 - 31 x

04/18/2014

221300-31

Cator, Ruma & Assoc ( MRD)

4/29/2014

Transmittal of Submittal

March 27, 2014

Kiewit �� Turner 7200 South Alton Way Englewood, CO 80112

Attention: Matt Pothoven

Reference: VA Replacement Medical Center Facility

Subject: Submittals for Specification Section 221300

Dear Matt:

RK Mechanical, Inc is providing Kiewit 11 Turner the enclosed submittals for Specification Section 221300 � Facility Sanitary and Vent Piping (CDI 12 Additions) by RK, as listed below:

ITEM COPIES REV SUBMITTAL DESCRIPTION STATUS DUE BACK

1 1 1 2.8 Trench Drains For Approval 04/17/2014

Your immediate review and processing is requested to ensure these submittals are returned back to The Mechanical Diamond Partners on or before the DUE BACK date(s) listed above.

We are available to discuss any comments or questions you may have concerning these submittals.

Sincerely, The Mechanical Diamond Partners

Date Submitted: March 27, 2014

Date Due Back: April 17, 2014

RK Submittal No.:

Specification Section: 221300 " Facility Sanitary and Vent Piping (CDI 12 Additions) by RK

Project Name: VA Replacement Medical Center Facility 13611 East Colfax

General Contractor: Kiewit "" Turner 7200 South Alton Way Englewood, CO 80112

Mechanical Contractor: The Mechanical Diamond Partners

Subcontractor/Supplier:

Submittal Cover Sheet

ITEM COPIES REV SUBMITTAL DESCRIPTION DRAWING MANUFACTURER

1 1 1 2.8 Trench Drains TD"3 Quickdrain USA

Kiewit-Turner a Joint Venture

7200 S. Alton Way, Suite A-300, Englewood, CO 80112

Phone: 303-930-9000 FAX: 303-930-9001

Project Name:

Subcontractor Name: Submittal Date:

Contact Name: E-mail: Return By Date:

Contact Phone(s): Review Days:

Number: Name:

1.3 A,B

2.1

N Y N N N

N Y N N N

N Y N N N

N Y N N N

N Y N N N

2.2

N Y N N N

N Y N N N

2.3

N Y N N N

2.4

N Y N N N

N Y N N N

2.5

Perma-Pipe/RIC-WIL N Y N N N

2.6

Zurn N Y N N N

Zurn N Y N N N

2.7

22 13 00.09

Specialty Pipe Fittings

22 13 00.03

22 13 00.03R1

22 13 00.08

22 13 00.09

Exposed Waste Piping

22 13 00.01

Sanitary Waste, Drain, and Vent piping

22 13 00.01

22 13 00.03

22 13 00.03

Pumped Drain Piping

SUBMITTAL INDEX & COVER SHEET

Department of Veteran's Affairs

Replacement Medical Center

C and B Plumbing 03/27/14

Paul Scofield paul@candbplumbingcolorado.com 04/17/14

970-484-6578

Specification Section: 22 13 00_JSI-041 Facility Sanitary and Vent Piping

S p e c

S u b m it ta l

P a ra g ra p h

S p e c

P ro d u c t

P a ra g ra p h

S p e c if ie d o r

L is te d

M a n u fa c tu re r?

M e e ts

A ll

S p e c

R e q u ir e m e n ts

E x c e p ti o n s o r

V a ri a n c e s f ro m

S p e c

A p p ro v e r

In fo rm a ti o n

N e e d e d

I n

T h is P a c k a g e

Submittal Type

Submittal Item Description Manufacturer

Crestline, Charlotte

Oatey

Mainline

Tyler

Charlotte, Cerro, Mueller, JM Eagle

Watts

Merit Brass

Cerro, Mueller, Madeco, Mills, Pioneer

Fernco, Watts, Elster, Westerman

Fernco

22 13 00.03

Floor Drains

Grease Waste Piping

22 13 00.09

Cleanouts

22 13 00.01

SubmittalIndexForm_041009 Page 1 of 2 mailto:paul@candbplumbingcolorado.com

Number: Name: Specification Section: 22 13 00_JSI-041 Facility Sanitary and Vent Piping S p e c

S u b m it ta l

P a ra g ra p h

S p e c

P ro d u c t

P a ra g ra p h

S p e c if ie d o r

L is te d

M a n u fa c tu re r?

M e e ts

A ll

S p e c

R e q u ir e m e n ts

E x c e p ti o n s o r

V a ri a n c e s f ro m

S p e c

A p p ro v e r

In fo rm a ti o n

N e e d e d

I n

T h is P a c k a g e

Submittal Type

Submittal Item Description Manufacturer

Zurn N Y N N N

Zurn, Orion N Y N N N

Zurn N Y N N N

Zurn N Y N N N

2.8

Zurn N Y N N N

ACO, Quickdrain USA N Y Y N Y

2.9

Tyler

Tyler

2.10

Zurn

PPP, Zurn

2.11

Zurn

Zurn

1.3D

Submittal is in Compliance

Submittal is in Compliance with Variances from Specifications

Signature

DateReviewed By

Water Proofing

22 13 00.01

22 13 00.02

Sustainable Design Information

22 13 00.03

Trap Seal Primer Valves and Trap Seal Primer Systems

22 13 00.01

22 13 00.03

Trench Drains

22 13 00.09

22 13 00.03R2

Traps

22 13 00.01

FD-C, FD-R Floor Drains

22 13 00.01

22 13 00.03

22 13 00.15

22 13 00.21

SubmittalIndexForm_041009 Page 2 of 2

File details come from the government source that posted it. Updated .