2025-10-10_3_Birds_Bid_Schedule.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Heron Street, Egret Avenue, and Mallard Street Seawall Replacement Project
Solicitation number
26-B-38IF
Issued by
Volusia County, Florida

About this file

This is a bid tabulation schedule for Volusia County, Florida's seawall replacement project comprising three separate locations: Mallard Street, Egret Avenue, and Heron Beach. The project addresses post-hurricane coastal restoration at beachfront properties in Wilbur by the Sea damaged during Hurricanes Ian and Nicole. Work scope includes demolition and excavation, sand fill and grading, seawall construction, concrete plug and chemical grouting, beach access stairs and landings, concrete walkways, aluminum guiderails, native dune plantings (dune sunflower, sea oats, and sea grape), as-built surveys, and site restoration. Mallard Street requires 560 tons of sand fill, a 1 lump-sum seawall, 166 square feet of beach access stairs, 107 square yards of concrete walkway, 151 linear feet of guiderail, and 1,796 total dune plants. Egret Avenue requires 510 tons of sand fill, 121 linear feet of seawall, 178 square feet of beach access stairs, 92 square yards of concrete walkway, 230 linear feet of guiderail, and 1,304 total dune plants. Heron Beach requires 150 tons of sand fill, 111 linear feet of seawall, 178 square feet of beach access stairs, 107 square yards of concrete walkway, 160 linear feet of guiderail, and 1,731 total dune plants. The contract timeline specifies 120 calendar days for substantial completion and 150 calendar days for final completion, with liquidated damages assessed at $500 per day for delays. Sealed bids were due electronically on February 19, 2026, at 3:00 p.m., with a non-mandatory pre-bid meeting held on January 29, 2026.

The estimated total construction cost for all three project locations is $2,112,580.80, with pricing structured as unit prices multiplied by estimated quantities. The project is federally funded through FEMA and subject to Davis-Bacon Act prevailing wage requirements, E-Verify employment verification, and domestic material preferences. Contractors must provide a bid bond of not less than five percent of the total bid amount and performance and payment bonds equal to 100 percent of the contract price upon award. Required insurance includes $1,000,000 commercial general liability per occurrence with $2,000,000 aggregate, $1,000,000 auto liability combined single limit, $1,000,000 excess liability, and $1,000,000 contractors pollution liability, with Volusia County named as additional insured. The County is exempt from Florida sales tax and federal excise tax, with tax exemption procedures allowing deductive change orders for qualifying materials. No specific set-asides for small businesses or minority-owned enterprises are identified; however, federal provisions encourage subcontracting with disadvantaged business categories. Award will be granted to the lowest responsive and responsible bidder, with full payment on undisputed invoices remitted within 20 business days of receipt.

View the file

Other files

File Type Posted
Heron_Street,_Egret_Avenue,_and_Mallard_Street_Seawall_Replacement_Project_(Addendum_#1_Revision).pdf PDF
Exhibit_G_-_Bid_Price_Sheet_26-B-38IF_-_REVISION_1.xlsx XLSX spreadsheet
Exhibit_K_-_Installation_Floater_Affidavit_26-B-38IF.docx DOCX document
Heron_Street,_Egret_Avenue,_and_Mallard_Street_Seawall_Replacement_Project.pdf PDF
Exhibit_J_-_FEDERAL_CONTRACT_PROVISIONS_(FEMA)_26-B-38IF.pdf PDF
Exhibit_I_-_Surveys_for_26-B-38IF_-_Heron_Street,_Egret_Avenue,_and_Mallard_Street.pdf PDF
Exhibit_H_-_Geotechnical_Data_for_26-B-38IF_-_Heron_Street,_Egret_Avenue,_and_Mallard_Street.pdf PDF
Exhibit_G_-_Bid_Price_Sheet_26-B-38IF.xlsx XLSX spreadsheet
Exhibit_F_-_Sales_Tax_Exemption_Procedure_26-B-38IF.pdf PDF
Exhibit_E_-_Technical_Specifications_26-B-38IF_for_Heron_Street,_Egret_Avenue,_and_Mallard_Street.pdf PDF
Exhibit_D_-_Construction_Plans_26-B-38IF_-_Heron_Street,_Egret_Avenue,_and_Mallard_Street.pdf PDF
Exhibit_C_-_Draft_Contract_26-B-38IF.pdf PDF
Exhibit_B_-_PRIME-SUB_FORM_for_Contractors_26-B-38IF.xls XLS spreadsheet
Exhibit_A_-_Insurance_Requirements_26-B-38IF.pdf PDF
Drawings_HERON.pdf PDF
Drawings_EGRET.pdf PDF
Drawings_MALLARD.pdf PDF
2c_-_Heron_Geotechnical_Data.pdf PDF
2a_-_Mallard_Geotechnical_Data.pdf PDF
2025-10-10_Tech_Specs_-_2_-_Egret.pdf PDF
2025-10-10_Tech_Specs_-_3_-_Heron.pdf PDF
1b_-_Egret_Survey_SIGNED.pdf PDF
2025-10-10_Tech_Specs_-_1_-_Mallard.pdf PDF
2b_-_Egret_Geotechnical_Data.pdf PDF
1a_-_Mallard_Survey_SIGNED.pdf PDF
1c_-_Heron_Survey_SIGNED.pdf PDF
2025-10-10_3_Birds_Bid_Schedule.xlsx XLSX spreadsheet
PRIME-SUB_FORM_for_Contractors_rev._01.15.2025_(lock_before_publishing).xls XLS spreadsheet
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Schedule

Mallard Street Beach Access
Replacement Seawall and Beach Access Stairs
Volusia County
Bid Tabulation
October 10, 2025
Item No.DescriptionQuantityUnit CostTotal Cost
1Mobilization/Demobilization1LSLS
2Demolition & Excavation1LSLS
3Sand Fill & Grading560TONS/TON
4Seawall1LS/LS
5Concrete Plug & Chemical Grout1LSLS
6Beach Access Stairs & Landing166SF/SF
7Concrete Walkway107SY/SY
8Aluminum Guiderail151LF/LF
9aDune Plants - dune sunflower164Plant/Plant
9bDune Plants - sea oats1,470Plant/Plant
9cDune Plants - sea grape162Plant/Plant
10As-Built Survey1LSLS
11Site Restoration1LSLS
Total Cost:
Contract Time (Calendar Days):
Egret Ave Beach Access
Replacement Seawall and Beach Access Stairs
Volusia County
Bid Tabulation
October 10, 2025
Item No.DescriptionQuantityUnit CostTotal Cost
1Mobilization/Demobilization1LSLS
2Demolition & Excavation1LSLS
3Sand Fill & Grading510TONS/TON
4Seawall121LF/LF
5Concrete Plug & Chemical Grout1LSLS
6Beach Access Stairs & Landing178SF/SF
7Concrete Walkway92SY/SY
8Aluminum Guiderail230LF/LF
9aDune Plants - dune sunflower119Plant/Plant
9bDune Plants - sea oats1,067Plant/Plant
9cDune Plants - sea grape118Plant/Plant
10As-Built Survey1LSLS
11Site Restoration1LSLS
Total Cost:
Contract Time (Calendar Days):
Heron Beach Access
Replacement Seawall and Beach Access Stairs
Volusia County
Bid Tabulation
October 10, 2025
Item No.DescriptionQuantityUnit CostTotal Cost
1Mobilization/Demobilization1LSLS
2Demolition & Excavation1LSLS
3Sand Fill & Grading150TONS/TON
4Seawall111LF/LF
5Concrete Plug & Chemical Grout1LSLS
6Beach Access Stairs & Landing178SF/SF
7Concrete Walkway107SY/SY
8Aluminum Guiderail160LF/LF
9aDune Plants - dune sunflower158Plant/Plant
9bDune Plants - sea oats1,417Plant/Plant
9cDune Plants - sea grape156Plant/Plant
10As-Built Survey1LSLS
11Site Restoration1LSLS
Total Cost:
Contract Time (Calendar Days):