2025-03-14 PN 1583808 Summit Bowl Dorm - Multi-Year Funding.docx

DOCX document 32 KB Posted

Attached to
Smithsonian Astrophysical Observatory Fred Lawrence Whipple Observatory (FLWO) Dormitory Replacement
Solicitation number
33330225RF0010020
Issued by

About this file

This document is a multi-year funding increment plan for the Smithsonian Astrophysical Observatory's Fred Lawrence Whipple Observatory (FLWO) Dormitory Replacement project located in Amado, Arizona. The construction project is valued over $10 million, with $4 million allocated in FY 2025 and the remaining balance to be obligated by December 1, 2026. The project involves constructing a new Summit Dormitory Addition connected to the existing Commons Building, including comprehensive building systems like HVAC, electrical, plumbing, fire suppression, and security infrastructure.

Key project details include a 520-calendar day performance period, subcontracting goals of 40% with small businesses (including 7% service-disabled veteran-owned), and applicable Davis Bacon wage determinations. The solicitation (33330225RF0010010) requires a pre-proposal meeting on May 6, 2025, with questions due by May 27, 2025, and proposals due on June 23, 2025, at 5:00 PM EST. Critical work elements involve construction management software, scheduling coordination with ongoing site operations, working in a remote National Forest site, and accommodating constraints like Spotted Owl mating season.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SAO-AZ: Replace Summit Bowl Dorm

PN: 1583808

The range for this construction project is over $10M

FY 2025 FUNDING INCREMENT: ($4M available in FY 2025)

General Conditions (6 months)
$
(assumes (1) 6-month demobilization)
Mobilization
$
(assumes 2 mobilizations)
Sitework
$
Demolition
$
Temporary Field Office
$
Submittals and Shop Drawings
$
Long Lead Item Purchases
$
Structural concrete, substructure, foundations (including excavation and dewatering), steel framing
$

Roofing & Envelope Enclosure

Masonry
$
Mechanical, Electrical and Plumbing
$
Fire Protection
$
Fire Alarm
$
Electronic Security
$
SUBTOTAL
$

Termination Cost (Cancellation Charge)

Other – Offerors shall clearly and completely describe items deleted/added to FY2025 Funding Phase

$
(Attach pages as necessary)

TOTAL FY2025: ________________________________________________________________ $ __________________ (Express in Words and Figures)

FY 2026 FUNDING INCREMENT: (Balance of funding obligated by 2026-12-01, or when available)

General Conditions (6 months)
$
Sitework
$
Temporary Field Office
$
Structural concrete, substructure, foundations (including excavation and dewatering), steel framing
$

Roofing & Envelope Enclosure

Masonry
$
Mechanical, Electrical and Plumbing
$
Fire Protection
$
Fire Alarm
$
Electronic Security
$
Interior Systems (partitions, walls, doors, ceilings, etc.)
$
Specialties
$
SUBTOTAL
$

Termination Cost (Cancellation Charge)

Other – Offerors shall clearly and completely describe items deleted/added to FY2026 Funding Phase

$
(Attach pages as necessary)

TOTAL FY2026: ________________________________________________________________ $ __________________ (Express in Words and Figures)