2-TB2625-SIT - Attachment E - West High General Timeline.docx

DOCX document 126 KB Posted

Attached to
RFP - SLC School District - Special Inspections and Testing of Construction Material
Solicitation number
TB2625-SIT
Issued by
Salt Lake County, Salt Lake City, Utah

About this file

The document "2-TB2625-SIT - Attachment E - West High General Timeline.docx" appears to be a timeline attachment related to the Salt Lake City School District's Request for Proposal (RFP) for Special Inspections and Testing of Construction Material. The RFP is specifically limited to four pre-approved vendors: Applied Geotechnical, CMT Technical, Professional Service Industries, and Western Technologies. The solicitation seeks competitive sealed proposals for special inspections and testing of construction materials across various construction projects within the Salt Lake City School District.

The procurement is governed by Utah Procurement Code (UCA 63G-6a-507), which strictly limits proposal submissions to the named approved vendors. All questions and responses must be submitted through the Bonfire system, with only official addenda from the SLCSD Purchasing Department considered binding. The RFP emphasizes secure submission procedures, allowing vendors to modify their proposals up until the solicitation deadline without external visibility of their submissions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AUXILIARY SERVICES

995 West 2480 South Salt Lake City, Utah 84119 801.974.8367

Document Title Salt Lake City School District High School Special Inspections and Material Testing

Milestone dates

West High School

· November 2025 – Mass excavation, soil improvement, and utility work begins.

· Work will continue through the winter to ensure we are well-prepared to start the building construction in March 2026

· February 2026 – Phase 1 full building bid packages due.

· March 2026 – Building construction begins.

· June 2030 – Phase one construction complete.

· June 2030 – Rebuild sports complex. Work continues through summer of 2032.

· Summer 2032 – Project completion.

Excellence and Equity: every student, every classroom, every day www.slcschools.org Auxiliary Services Page 2 of 2 995 West 2480 South, Salt Lake City, Utah 84119 | www.slcschools.org | Phone: 801.974.8367 image1.png image2.png