1-TB2625-SIT - Attachment F - Highland High General Timeline.docx

DOCX document 126 KB Posted

Attached to
RFP - SLC School District - Special Inspections and Testing of Construction Material
Solicitation number
TB2625-SIT
Issued by
Salt Lake County, Salt Lake City, Utah

About this file

This document is a project timeline for the Salt Lake City School District's Highland High School construction project. The timeline spans from March 2026 to May 2031, detailing key milestones for a multi-phase construction effort. Specific phases include mass excavation and site utility work in March 2026, with Phase 1 full building bid packages due in the same month. Phase 1 construction is scheduled for completion in December 2028, followed by existing building demolition in Spring 2029. The project's second phase, encompassing a new building, fieldhouse, parking structure, tennis facilities, and site construction, is set to begin in May 2029 and complete by May 2031.

The timeline is part of a broader Request for Proposal (RFP) for special inspections and materials testing, with participation limited to pre-approved vendors including Applied Geotechnical, CMT Technical, Professional Service Industries, and Western Technologies. The project is specifically located in Salt Lake City, Utah, and is being managed by the Salt Lake City School District. The document emphasizes the competitive sealed proposal process and highlights the district's commitment to a structured procurement approach, with all communications and modifications to be processed through the Bonfire system to ensure transparency and fairness in the vendor selection process.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AUXILIARY SERVICES

995 West 2480 South Salt Lake City, Utah 84119 801.974.8367

Document Title Salt Lake City School District High School Special Inspections and Material Testing

Milestone dates

Highland High School

· March 2026 – Mass excavation for footings and deep foundation work. Site utility (temporary and new point of connections) work.

· March 2026 – Phase 1 full building bid packages due.

· December 2028 – Phase one construction complete.

· Spring 2029 – Existing building demolition.

· May 2029 – Phase 2 building, fieldhouse, parking structure, tennis and site construction begins.

· May 2031 – Phase 2 complete.

Excellence and Equity: every student, every classroom, every day www.slcschools.org Auxiliary Services Page 2 of 2 995 West 2480 South, Salt Lake City, Utah 84119 | www.slcschools.org | Phone: 801.974.8367 image1.png image2.png

File details come from the government source that posted it. Updated .